B.GoddardChamonix 2009 - LHC Performance1 Chamonix 2009 – LHC Performance Workshop Worst case beam incident causes and protection B.Goddard TE/ABT Based.

Slides:



Advertisements
Similar presentations
Jan Uythoven, AB/BTLHCCWG, 3 May 2006 Page GeV Commissioning Machine Protection Needs to be commissioned to: Prevent damage with the used, higher.
Advertisements

8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
12/03/2013MPP Workshop Annecy Update on Beam Failure Scenarios Jan Uythoven Thanks to: T.Baer, R.Schmidt, J.Wenninger, D.Wollmann, M.Zerlauth, other MPP.
PAC June LHC Machine Protection Rüdiger Schmidt R.Assmann, E.Carlier, B.Dehning, R.Denz, B.Goddard, E.B.Holzer, V.Kain, B.Puccio, B.Todd, J.Uythoven,
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Concept & architecture of the machine protection systems for FCC
Injection test? Mike Lamont For initial discussion.
Failure mode impact studies and LV system commissioning tests
Beam Dumping System – Failure Scenarios Brennan Goddard, CERN AB/BT How the dump system can fail Catalogue of primary failures Failure classes and protection.
B.Goddard 08/11/04 HHH 2004 Workshop, CERN Beam Dump Brennan GODDARD CERN AB/BT The existing LHC beam dump is described, together with the relevant design.
Preconditions for operating at 5 TeV in 2010 Session th January 2010 J. Wenninger BE/OP How to safely reach higher energies and intensities? Settings.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
Overview of Machine Protection for the LHC
1 LBDS Testing Before Operation Jan Uythoven (AB/BT) Based on the work of many people in the KSL, EC and TL sections.
The LHC injection systems located in points 2 and 8 are comprised of several elements common to the LHC ring and the downstream ends of the TI 2 and TI.
Ralph Assmann What Do We Want To Measure (in 2009) R. Assmann S. Redaelli, V. Previtali CERN/BE discussed with W. Scandale CERN/EN26/3/2009CC09  See also.
LER Workshop, CERN, October 11-12, 2006Detector Safety with LER - Henryk Piekarz1 LHC Accelerator Research Program bnl-fnal-lbnl-slac Accelerator & Detector.
1 Beam Dumping System MPP review 12/06/2015 Jan Uythoven for the ABT team.
1 Will We Ever Get The Green Light For Beam Operation? J. Uythoven & R. Filippini For the Reliability Working Group Sub Working Group of the MPWG.
1 CC & MP - CC10 - CERN Crab LHC J. Wenninger CERN Beams Department for the LHC Machine Protection Panel.
Simulations of TCT beam impacts for different scenarios R. Bruce, E. Quaranta, S. RedaelliAcknowledgement: L. Lari, C. Bracco, B. Goddard.
18 July Reminder Dilution kicker system MKB is staged (2H, 2V) –Limits extracted intensity at 7 TeV to 50% of nominal –For 25ns spacing, this is.
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning.
LHC progress Sunday 3rd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Collimator settings for 2012 R. Bruce, R. Assmann for the collimation team
LHC beam dump, injection system and other kickers B.Goddard, with input from L.Ducimetière, W.Bartmann, V.Mertens, J.Borburgh, M.Barnes, C.Bracco, V.Senaj,
Injection and protection W.Bartmann, C.Bracco, B.Goddard, V.Kain, M.Meddahi, V.Mertens, A.Nord, J.Uythoven, J.Wenninger, OP, BI, CO, ABP, collimation,
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Beam absorbers for Machine Protection at LHC and SPS
LHC machine protection close-out 1 Close-out. LHC machine protection close-out 2 Introduction The problem is obvious: –Magnetic field increase only a.
LHC’s Modular Machine ITER – Machine ProtectionB. ToddJuly 2010 Thanks to : TE/MPE/MI, CERN Machine Protection Panel, et al 1v0 Protection System.
Monday 19 th March 07:33 Lost (another) beam in the squeeze, beyond 2 m, B2 hits 1/3 resonance. 08:30 Start (another) ramp  Try to correct coupling and.
HL-LHC WP14 2 nd meeting: Intercepting devices and failure cases to be studied Anton Lechner, Jan Uythoven.
Machine Protection Review, Markus Zerlauth, 12 th April Magnet powering system and beam dump requests Markus Zerlauth, AB-CO-IN.
Session 8: What we will do for beam preparation in 2009 G. Arduini, R. Giachino 1Session 8 – Summary - GA24/02/2009.
R.Schmidt and J.Wenninger - Lumi ‘061 Rüdiger Schmidt Jörg Wenninger CERN LUMI 06 in Valencia / Spain Friday 20 October 2006 Machine protection for PS2,
C. Bracco, R. Bruce, B. Goddard, C. Wiesner, A. Lechner, M. Frankl
The TV Beam Observation system - BTV
Dependability Requirements of the LBDS and their Design Implications
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Chamonix 2009 – LHC Performance Workshop
Surviving an Asynchronous Beam Dump?
The LHC Beam Dumping System
Introduction: FCC beam dumping system
LHC beam dump 7.56 TeV operation
The LHC - Status Is COLD Is almost fully commissioned
Potential failure scenarios that can lead to very fast orbit changes and machine protection requirements for HL-LHC operation Daniel Wollmann with input.
Jan Uythoven For discussion
Powering the LHC Magnets
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Joint Meeting SPS Upgrade Study Group and SPS Task Force
LHC Risk Review: Kicker Magnet Reliability
Overview on LHC Machine Failure Scenarios
Safe Injection into the LHC V.Kain AB/CO
Safe Injection into the LHC V.Kain AB/CO
Initial Experience with the Machine Protection System for LHC
Machine Protection Xu Hongliang.
LHC Injection and Dump Protection
Planning at 5 o’clock meeting Friday
Protection against accidental beam loss at the LHC
Machine Tolerances in Cleaning Insertions
Machine Protection System Commissioning plans
Chamonix Workshop XIV CERN - 17th-21st January 2005
Machine Protection Issues for LHCb
The LHC Beam Interlock System
What systems request a beam dump? And when do we need them?
Close-out.
Presentation transcript:

B.GoddardChamonix LHC Performance1 Chamonix 2009 – LHC Performance Workshop Worst case beam incident causes and protection B.Goddard TE/ABT Based largely on the work of R.Appleby, R.Assmann, E.Carlier, A.Gomez Alonso, V.Kain, T.Kramer, R.Schmidt, J.Strait, J.Wenninger, J.Uythoven

B.GoddardChamonix LHC Performance2B.GoddardChamonix LHC Performance2 Outline of talk Introduction Some worst case incidents…. –during beam dump –during injection –with circulating beam Discussion and conclusions This talk, by its nature, may not reassure…

B.GoddardChamonix LHC Performance3 What is WC and where could this happen? Exploring cases which have potential to stop LHC for more than 6 months Could be as a result of depositing a damaging beam in: –many arc magnets simultaneously –many collimators –a continuous cryostat interconnect –A DFB –several injection or extraction kickers –several RF cavities –an experimental beam pipe or detector –a triplet magnet Some “indirect” beam-provoked damage might also be possible –Large loss of vacuum plus contamination of RF cavities, injection kickers, experiment, … –Beam-induced quench in busbar cable? Collateral effects (He release, vacuum contamination) may take more time to recover from than direct beam damage

B.GoddardChamonix LHC Performance4 Catalogue of possible incidents and causes? No systematic catalogue of possible beam-induced incidents exists –Incidents due to single failures: already considered by individual systems designers, with lots of work on effects –Incidents due to multiple failures: patchy coverage, with obvious ones covered Should evaluate multiple failures (up to which order?!) –Beam dump, interlocks, BLMs, QPS, PIC & WIC, injections, collimators, operators, powering, … Impossible to be comprehensive – especially in a short talk –The incidents in the following are therefore only illustrative, concerning some of the critical elements mentioned previously

Incidents during beam abort B.GoddardChamonix LHC Performance5B.GoddardChamonix LHC Performance5

B.GoddardChamonix LHC Performance6B.GoddardChamonix LHC Performance6 Dump kicker erratic plus failure of retriggering system 1/15 nominal kick - entire beam deflected by 12.1 and 17.8  at 7 TeV –Synchronous dump trigger then generated by BETs in ~5 turns B1: full beam impacts TCDQ and ~40% of H collimators on first turn –Huge beam loss and quenches - would trigger dump via BIS within 2-3 turns –85% of H collimators hit within 2 turns (assuming collimators consumed piecewise) –Damage to elements downstream of collimators (IR6.Q4 at least 2 J/cc in coil) B2: If TCDQ consumed, IR5 TCTs and triplets exposed (B1 extra 5m C, 3 m W) –Damage extent depends on mass-transport timescale – stopping 7 TeV beam in C/W IR7 IR6 IR5 TCT Triplet

Beam swept across LHC aperture –At 450 GeV, fixed 2 m Fe TCDQM (and Q4) protect arc…(for well-centred beam) –At 7 TeV with 0.5m  *, impacts IR 5 TCTs for B2 (IR1 better protected with IR7) Many concerns about protection against this scenario –Precision on beam position/collimator jaw specified to 0.5  Adequate? Feasible?? –TCTs are controlled and interlocked in common with TCDQ/TCSG so are there hidden common mode failures? Could then damage several of Q1, Q2 or Q3 –Does TCT fully protect triplets? Or will swept beam (few us) penetrate? Similar effect to asynchronous dump if abort gap is filled B.GoddardChamonix LHC Performance7B.GoddardChamonix LHC Performance7 TCDQ/TCSG retracted plus asynchronous beam dump Losses in arc 6-7 (450 GeV, TCDQ/M removed) Losses at collimators (450 GeV TCDQ/M removed) 2.3e94.3e11

B.GoddardChamonix LHC Performance8B.GoddardChamonix LHC Performance8 2 missing MKD kickers - switch or trigger failures Beam underkicked into TCDS (6m C/Ti/Fe) and MSD vacuum chamber If TCDS penetrated, damage MSDB and MSDC chambers, MSDC yokes Then TD vacuum line at Q4 and Q5 cryo jumpers, MKB kicker magnets, … –A lot of sensitive equipment here but not so much stopping power… –Sacrificial absorber at start of dump line? –Need much better knowledge on beam penetration depth and how materials fail Particles lost on TCDS

B.GoddardChamonix LHC Performance9 Simplistic energy balance estimates give 100s of metres in Cu or Fe! With 350 MJ 86  s long beam, cannot assume that processes are ‘adiabatic’ –Beam modifies material properties on timescales of beam passage – drills into target –Huge scattering from dense target will blow up the primary beam size Lacking coupled nuclear – thermo-mechanical simulations –Basic simulations of 7 TeV impact on 7.7m C dump core showed beam not contained –FLUKA output in hydrodynamic code: factor 10 density reduction after 2.5 us –Extrapolations give penetrations of m of Cu – “limited” to 3-4 SC magnets Essential to better understand processes to estimate direct and collateral damage to machine elements and vacuum/cryo sector(s) concerned Penetration of 7TeV LHC beam into matter Time evolution of phase changes in Cu Depth vs mass transport timescale

B.GoddardChamonix LHC Performance10 MKD energy tracking system failure – 30 kV at 450 GeV rigidity –Deflects whole 23 MJ beam at 4.2 mrad instead of 0.27 mrad –Beam impacts ~7.5m MKD ceramic chambers, 3m MKD coils, ~5m long Q4 and 2m Fe TCDQM. Probable destruction of all these elements. –Showering or further penetration – e.g. into tunnel wall (via QRL for B2…)? Stopping full 86  s long 450 GeV beam: again more data needed –Some suggestion from SPS experiment that mass transport can happen in ~5us –Experimental data could be possible at proposed HiRadMat facility B.GoddardChamonix LHC Performance10 Energy tracking failure – beam into MKD kickers IR6

Incidents during injection B.GoddardChamonix LHC Performance11B.GoddardChamonix LHC Performance11

B.GoddardChamonix LHC Performance12B.GoddardChamonix LHC Performance12 Injection kicker doesn’t trigger plus TDI and TCDD out MKI TDI TCDD D1 42mm TCDD open IR2 0.8 mrad angle error for injected 2.3 MJ beam Impact ~37 mm at D1 entrance, ~40 mm at exit –Exactly at cold bore and coil respectively D1 destroyed - if He into beam vacuum collateral damage probably an important issue –Injection kickers and experiments nearby

MBCXV at full current in IR8 Impact LHCb beam pipe B.GoddardChamonix LHC Performance13B.GoddardChamonix LHC Performance13 Injecting with (corrector) dipole field wrong Need Beam Presence flag failure plus PC current wrong (many sources) –Normal correctors ~1.3 mrad at injection…also D1, Xing/sep and compensation Could impact experimental beam pipes in IR2 and IR8 with 2.3 MJ beam –Safe limits of ~100  rad on corrector dipoles and ~3% on D1/D2 currents Also could happen in arc, possibly with several grazing incidence impacts –In arc, cold-bore damage might leak He into beam vacuum… Worrying cases because of ‘weak’ protection and large number of sources –BP flag produced from “normal” BCT, many hundred unsurveyed magnet circuits

Incidents with circulating beam B.GoddardChamonix LHC Performance14B.GoddardChamonix LHC Performance14

“Faster” powering failures Effects of powering failures of separate families extensively simulated (In)famous warm D1 (450 GeV and 7 TeV): if collimators in position –~10 turns for beam to reach jaws –~25 turns to start quenching downstream magnets –~30 turns to reach collimator damage level Correct BLM thresholds AND collimator positions critical –Extra protection already added to ~20 circuits in LHC/TLs B.GoddardChamonix LHC Performance15

B.GoddardChamonix LHC Performance16 “Slower” powering failures Trips, quenches, loading wrong settings for one or many magnets –Typical timescales factor 10 longer than fastest failures –Some self-inflicted scenarios possible (e.g. ramp down whole machine without dumping first… a la SPS ’08) Danger if collimators accidentally retracted… –BLMs will dump in 3-4 turns when beam reaches aperture…quick enough? –Simulations needed…e.g. MB quench, beam moves faster nearer aperture Even more dangerous if BLM thresholds globally wrong –Beam could destroy many collimators before dump triggered –“losses  quench  QPS  PIC  dump” reaction time is ~150 turns Near-beam detectors of concern due to proximity –TOTEM 10 , VELO at 5 mm, –Studied extensively for 450 GeV and 7 TeV for TOTEM and LHCb VELO, for failures of linear magnetic elements –Protection relies on correct positioning of primary and secondary collimators with correct BLM thresholds –Local closed orbit bumps at detectors a danger – orbit monitoring and intlk.

B.GoddardChamonix LHC Performance17 BIS beam permit signal not transmitted to LBDS The real WC failure “What do we do if the dump doesn’t react to a programmed request” is a popular question. Possible answers are –Call Bruno and Etienne in to fix the problem –Cut RF Revolution Frequency to LBDS, to provoke synchronous dump –Force access system door to produce asynch. dump trigger –Start blowing beam up slowly with tune kicker, or transverse damper –Scrape beam slowly away with collimators, while staying below quench limit –We should at least agree and maintain a procedure for the CCC… If dump fails to fire after an interlock, beam will probably already be long gone. How much of LHC machine will also be gone? –Maybe a few collimators, if losses at TCDQ provoke dump from “direct” BLM? –Maybe a lot more…magnets downstream of collimators –To date no studies have been made of this eventuality –Tevatron experienced something like this – lost 2 collimators and 3 corrector magnets (1.5 MJ beam energy)

Discussion and conclusions B.GoddardChamonix LHC Performance18B.GoddardChamonix LHC Performance18

Elements ‘most at risk*’ IR7/IR3 collimators (possible to damage many at once) TCT collimators (exposed if TCDQ positioning bad wrt beam) MSD extraction septa (extraction errors, many can be damaged) TCDQ/TCSG protection device (TCDQ needs anyway upgrade) IR6.Q4 magnet(if high intensity impact on TCDQ) TCDS protection device(high beam load even for ‘design’ cases) Triplet beam screens/magnets (if TCT damaged or out) MQ beam screens/magnets (from several sources) MB beam screen/magnets (from several sources) SC D1 beam screens/magnets (from unprotected injection error) B.GoddardChamonix LHC Performance19 * a subjective, incomplete and loose attempt at a top 10 ranking...

B.GoddardChamonix LHC Performance20 We believe we’re well-protected against the many possible WC beam incidents –Hubris? –To date, loopholes in machine protection systems have been closed after a beam incident has occurred (see SPS in recent years) –Should step back and make analysis of “as built” system(s) with interdependencies It is presently difficult to pronounce on expected scale of damage, and very little analysis has been made of collateral effects –Direct and secondary consequences of these incidents must be better quantified –Impact on prevention/mitigation ‘weighting’, spares policy, procedures, etc Too easy to additionally stress Machine Protection (e.g. ramp down without dump) –Must define dangerous scenarios and find ways to avoid them “Formal commissioning of crucial MP systems essential – with procedures –Needs time in schedule (energy tracking in September ’08 was given no time. None) Concerns and ideas for follow-up

B.GoddardChamonix LHC Performance21 Concerns and ideas for follow-up Positioning and interlocking of TCDQ/TCSG devices wrt beam –Rely on rather ‘soft’ concepts (SW interlocks, SMP energy via timing system) –Investigate e.g. TCDQ position in BETs and reduced interlock BPM thresholds? Collimator positioning and BLM thresholds crucial for the many slow failures –Collimators ARE an important part of machine protection against failures –Again rely on rather ‘soft’ concepts (SW intlks, shared SMP energy, LSA, …) –Critically verify all aspects of actual implementation? LBDS energy tracking and (re)triggering systems absolutely crucial –Continue with as-built system analysis and reliability studies… –Formalise acceptance testing - with a review processes at pre-defined stage? –Review once more connections between LBDS and BIS… For longer term, other more speculative studies possible –sacrificial absorbers to mitigate direct / collateral damage where applicable…i.e. sacrificial TCDQ which can really ‘stop’ the full beam

B.GoddardChamonix LHC Performance22 Main gaps in knowledge Need an agreed of list of damage limits for many elements –Design choices for protection systems and devices based on sketchy data –Impact on scale of a particular incident Need to understand development of mutual beam ↔ matter interactions at high energy density and over 100  s timescales –Invaluable information (e.g. for sacrificial absorbers) but v.complicated to model –Coordinated R&D effort? In which framework? –Controlled experiment would help, possible at 450 GeV with HiRadMat Need a ‘full’ catalogue of multiple failures and effects –Could help to identify possible “birdstrikes” - single causes of multiple failures –Should include evaluation of elements likely to be damaged and collateral effects –Involves expertise from machine protection, accelerator physics, nuclear physics, materials, magnet, cryogenics, vacuum, powering, experiments, …

Fin B.GoddardChamonix LHC Performance23B.GoddardChamonix LHC Performance23

B.GoddardChamonix LHC Performance24 Machine protection strategy Analysis –A great deal of work done in past ~5 years on protection against failures for experiments, for injection, for circulating beam and for LHC dump. –R.Appleby, A.Gomez Alonso, V.Kain and T.Kramer tracking studies, + R.Schmidt Prevention –Equipment design and (to a lesser extent) operational procedures made to avoid potentially dangerous situations Protection –Active surveillance and interlocking system, to detect and react to dangerous faults in time (typical reaction time of ms). –Explicitly stated assumption that redundancy between detection systems greatly improves coverage… Mitigation –Fixed and movable devices designed to intercept mis-steered beams, where interlocking not possible

B.GoddardChamonix LHC Performance25 Single “functional” failures Functional failures in critical MP systems could lead to WC –There is only one energy tracking system –There is only one interlock system –There is only one beam dump system Single failures are (relatively) easy to analyse and design for –To meet “beyond-design” criterion, reliability analyses and technical audits –Audits gave positive feedback on critical subsystem design –Safety Integrity Levels (SIL) quantified and as good as requirements Design reliability using fault tolerance/redundancy within a critical system Chamonix LHC Performance LBDS triggering uses redundancy and fault-tolerance to meet required reliability We can dump with 14 out of 15 MKD kickers each MKD kicker has 2 separate switches each switch has 2 redundant Power Triggers each Power Trigger has 2 redundant triggering lines each triggering line comes from 2 redundant fan-outs each fan out comes from 2 redundant TSUs each TSU gets inputs from 2 redundant permit loops

B.GoddardChamonix LHC Performance26B.GoddardChamonix LHC Performance26 Multiple failures Many WC incidents possible if multiple failures “allowed” inside or across systems Overall, faith in LHC machine protection strategy is based on: –“The chance of (failure A) + (failure B) + (failure C) happening is very small” But…danger of using the fallacious Argument of Personal Incredularity* –“I personally find it very hard to believe that these things could all fail at once. I therefore assume that they cannot all fail at once” Sometimes these conjunctions do occur –Example from 2008 in LHC: failure on beam interlocking of a vacuum valve which could only happen because of 5 separate faults –“Personally I find it very hard to believe that this could happen”. –But it did. And the more often we test (stress) the system, the more failures there will be *as popularised by R.Dawkins

For multiple failures, increased complexity makes failure modes much more difficult to analyse and understand Interdependencies between LHC systems mean that we should worry about common single causes for multiple failures (birdstrikes) –e.g. collimator position interlock AND BLM thresholds are “controlled” by the ENERGY value distributed over the Safe LHC Parameters system, Also must avoid situations where operator error makes single failure dangerous –e.g. an operator loads the wrong functions for extraction septum MSD - then we rely ONLY on the BEI card supplying correct MSD current to BETS B.GoddardChamonix LHC Performance27 Multiple failures II Birdstrikes – single causes can lead to multiple failures

B.GoddardChamonix LHC Performance28 A real beam incident 2004 TT40 extraction of 2.3 MJ 450 GeV LHC beam from SPS –Transfer line QTRF vacuum chamber destroyed in beam incident –Simulation very sensitive to input – no full self-consistent model found –Need controlled experiment! Cut in outside of chamber Damage to inside of chamber Projected molten steel on opposite side of chamber Damage zone observed 316LN MP 1400 C

MKD energy tracking system failure - 9 kV at 7 TeV rigidity (c.f. 30 kV nominal) –Whole beam deflected at ~60 sigma (misses 6m C TCDS) –Impacts 7m of C in TCDQ, 2m of Fe in TCDQM, 5m of Q4 coldbore/coil –Certainly will damage/destroy TCDQ, TCDQM, Q4 –Possibly damage to MKDs (other beam), Q5 –Further damage not excluded (e.g. fraction into arc?) depending on details of how beam is stopped in the first elements B.GoddardChamonix LHC Performance29 Energy tracking failure – IR6 elements TCDS (6 m C) TCDQ/TCSG (7m C) TCDQM (2m Fe) Q4 IR6

Cataloging failures Considerable effort to produce – who drives it and find manpower? –Many possible combinations of failures Beam tracking to find out impact locations and parameters –Evaluation of potentially damaged elements Needs simulations, penetration depths, damage limits –Evaluation of collateral damage needs knowledge of risks for all local systems B.GoddardChamonix LHC Performance30B.GoddardChamonix LHC Performance30