Review of MPE activities during LS1 and outlook for LS2/LS3 View from BE/CO V.Baggiolini, M.Vanden Eynden On behalf of the BE/CO APS, DA, DO and FE Sections.

Slides:



Advertisements
Similar presentations
FESA 3 Implementation Status Stephane Deghaye BE/CO On behalf of the FESA team and many users.
Advertisements

TE / CRG / Paulo Gomes The Control System for the LHC tunnel cryogenics, p. 1 CERN Portuguese Teachers Programme, 7 Sep 2011 Dr. Paulo Gomes on behalf.
UCB Innovation for Specialists™ A Global Biopharma Leader TELEWORKING.
1 SOFTWARE PRODUCTION. 2 DEVELOPMENT Product Creation Means: Methods & Heuristics Measure of Success: Quality f(Fitness of Use) MANAGEMENT Efficient &
WorldFIP optical repeaters 1 | status Feb 2013: 66 repeaters ordered to HLP; never delivered Feb 2014: HLP announced eminent closure Jun 2014: 40 of the.
Accelerator Complex Controls Renovation, LHC Excluded Purpose and Scope M.Vanden Eynden on behalf of the AB/CO Group.
Effective Methods for Software and Systems Integration
Quality of Information systems. Quality Quality is the degree on which a product satifies the requirements Quality management requires that : that requirements.
TE-MPE LS1 Review  The Software Developments and Related Support Jean-Christophe Garnier TE-MPE LS1 Review, 02/06/2015 On behalf of the TE-MPE-MS Software.
T Software Development Project I Customer Info Jari Vanhanen Ohjelmistoliiketoiminnan ja –tuotannon laboratorio Software Business and.
©Ian Sommerville 2000, Mejia-Alvarez 2009 Slide 1 Software Processes l Coherent sets of activities for specifying, designing, implementing and testing.
Mandate of CO/DO section and Status/Outlook for Build tools
Barriere O, Le Roux P
EMI INFSO-RI SA2 - Quality Assurance Alberto Aimar (CERN) SA2 Leader EMI First EC Review 22 June 2011, Brussels.
Roles Committees Meetings
LHC Access System August 2006 LHC Access System – Status and Planning August 2006 Elena Manola-Poggioli Eva Sanchez-Corral TS-CSE on behalf of the LHC.
LHC Cryogenics Control: INTEGRATION OF THE INDUSTRIAL CONTROLS (UNICOS) AND FRONT-END SOFTWARE ARCHITECTURE (FESA) APPLICATIONS Enrique BLANCO Controls.
Status and first objectives 14/06/2012Jean-Christophe Garnier1.
Eugenia Hatziangeli Beams Department Controls Group CERN, Accelerators and Technology Sector E.Hatziangeli - CERN-Greece Industry day, Athens 31st March.
Draft for approval in ABMB, 4 Feb 08 Andy Butterworth Claude-Henri Sicard for the Controls Coordination Committee (CO3) 22 Jan 20081ATC/ABOC Days.
Status Report – Injection Working Group Working group to find strategy for more efficient start-up of injectors and associated facilities after long stops.
T HE BE/CO T ESTBED AND ITS USE FOR TIMING AND SOFTWARE VALIDATION 22 June BE-CO-HT Jean-Claude BAU.
Nov 28, 2013 Power Converters Availability for post-LS1 LHC TE-EPC-CCE.
Debriefing of controls re-commissioning for injectors after LS1 TC 09 October 2014.
Nov, F. Di Maio, M.Vanden Eynden1 CO Proposal concerning AB Front-End Software Responsibilities First detailed proposal based on the global Front-end.
CERN Control Standards Front-End Computer Layer Stéphane Deghaye BE/CO/FE
CERN Raul Murillo Garcia BE-CO LS1 review – TE-EPC feedback BE-CO LS1 review TE-EPC feedback Raul Murillo Garcia on behalf of TE-EPC Daniel Calcoen Stephen.
BE-CO-DO - Development tools (Eclipse, CBNG, Artifactory, …) - Atlassian (Jira, Wikis, Bamboo, Crucible), CO Testbed - DIAMON/LASER - JMS (Java messaging.
MPE Review – June 2, 2015 A. Erokhin, TE-MPE-EE Upgrade, IST and Powering tests of the Upgrade, IST and Powering tests of the 600A Energy Extraction Systems.
Real time performance estimates of the LHC BPM and BLM system SL/BI.
Strategy to achieve smooth upgrades during operations Vito Baggiolini BE/CO 1.
BE-CO review Looking back at LS1 CERN /12/2015 Delphine Jacquet BE/OP/LHC Denis Cotte BE/OP/PS 1.
©Ian Sommerville 2004Software Engineering, 7th edition. Chapter 5 Slide 1 Project management.
Beam Interlock System MPP Internal ReviewB. Puccio17-18 th June 2010.
Feedbacks from EN/STI A. Masi On behalf of EN-STI Mathieu Donze` Odd Oyvind Andreassen Adriaan Rijllart Paul Peronnard Salvatore Danzeca Mario Di Castro.
POST-ACCOR renovations until LS2 – DEBRIEFING – Marine Pace, CO3 – 17 September 2015 Input from Chris, Marc, Stephen, Stephane, Wojtek.
FESA S. Deghaye for the FESA team BE/CO. What happened since April? followed by “Our plans”
MPE activities within MP3 Arjan Verweij A. Verweij, MPE review, 2 June 2015 The questions: 1. Define the scope of work for your activity 2. Structure of.
MPE and BE-CO Collaborations  MPE and BE-CO collaborations Jean-Christophe Garnier 01/12/2015 On behalf of TE-MPE.
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
The Control System for the LHC tunnel cryogenics Controlling Cool Accelerators Controle da Criogenia de Aceleradores de Partículas Dr. Paulo Gomes CERN.
Final Report – Injector Re- Commissioning Working Group (IRWG) Working group to find strategy for more efficient start-up of injectors and associated facilities.
B.Puccio MPE Workshop for LS1 / 22 & 23 Nov Logistics for DYPB activities Bruno PUCCIO (TE/MPE)
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
Christophe Martin TE-MPE-EP 02/06/ The BIS and SMP activities during LS1 MPE Group Review, 2 June 2015 Christophe Martin, Stephane Gabourin & Nicolas.
LS1 – View from Applications BE-CO LS1 review – 1 December 2015 Greg Kruk on behalf of the Applications section.
TE-MPE, MPE Workshop 2010, G.D’Angelo, 14-Dec TE-MPE on-call service for the LHC Giorgio D’Angelo on behalf of TE-MPE On call team, with inputs.
Monitoring and Diagnostics infrastructure & SW for LHC QPS WorldFIP first analysis Michel Arruat, Frank Locci, Julien Palluel BE/CO1.
Proposal: Use of ECRs for “Controls” Changes and Renovations Rende Steerenberg, Samy Chemli, Marine Gourber-Pace, Klaus Hanke, Verena Kain, Bettina Mikulec,
HWC Review – Sequencer Vito Baggiolini AB/CO, with the team: Carlos Castillo, Daniele Raffo, Roman Gorbonosov.
Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 1 Claude DEHAVAY - CERN/AB/CO/HT Installation Readiness Report - Controls.
CERN GS Department CH-1211 Genève 23 Switzerland cern.ch/gs-dep Internet Services GS AIS General Services Department GS Advanced Information Services EVM.
JIRA in BE-CO for Exploitation Marine BI Seminar 20 November
 Automation Strategies for LHC System Tests and Re-Commissioning after LS1 Kajetan Fuchsberger TE-MPE LS1 Workshop On behalf of the TE-MPE-MS Software.
Feedback on Controls from 2015 Operation Marine Pace, on behalf of BE-CO. Evian Workshop Dec 2015 Marine Pace, BE-CO -Evian Workshop 2015.
MPE Workshop 14/12/2010 Post Mortem Project Status and Plans Arkadiusz Gorzawski (on behalf of the PMA team)
February 4 th, Quality assurance plan: production, installation and commissioning N.Vauthier TE-CRG Technical Review on Beam Screen Heater Electronics.
IS&T Project Reviews September 9, Project Review Overview Facilitative approach that actively engages a number of key project staff and senior IS&T.
 TE-MPE-PE Clean code workshop – R.Heil, M.Koza, K.Krol Introduction to the MPE software process Raphaela Heil TE-MPE-PE Clean code workshop - 9 th July.
EDMS N° V.1 TE-EPC Activities during LS1 V. Montabonnet [TE-EPC]
(Atlassian) Software Development tools used in BE/CO Jira, Bamboo, Fisheye+Crucible, Clover
LS1 Review BE-CO-SRC Section Contributions from: A.Radeva, J.C Bau, J.Betz, S.Deghaye, A.Dworak, F.Hoguin, S.Jensen, I.Koszar, J.Lauener, F.Locci, W.Sliwinski,
FGClite Feedback from BE-CO & SUWG(Smooth Upgrades)
V4.
CONS and HL-LHC day Analysis of needs from BE-CO
Status and Plans for InCA
R. Denz, A. Gomez Alonso, AT-MEL-PM
MPE main activities planned for LS2
GIS PORTAL RACKS Integration of Equipment Racks in the Geographic Information Service (SMB/SE) Olivier Barrière.
Benoît DAUDIN (GS-AIS-PM – CERN) 22-March-2012
Presentation transcript:

Review of MPE activities during LS1 and outlook for LS2/LS3 View from BE/CO V.Baggiolini, M.Vanden Eynden On behalf of the BE/CO APS, DA, DO and FE Sections 03/06/151 Review of MPE activities during LS1 and outlook for LS2/LS3 - BE/CO

Agenda Application Software Development Tools Extension of QPS WorldFIP Infrastructure 03/06/152 Review of MPE activities during LS1 and outlook for LS2/LS3 - BE/CO

Feedback from CO/APS (Application SW) Collaboration for PMA and HWC Sequencer General assessment The collaboration (mainly with TE/MPE/MS) is very good No difference between LS1 or any other period Good planning - No unexpected/unplanned work items imposed on BE/CO/APS 03/06/153 Review of MPE activities during LS1 and outlook for LS2/LS3 - BE/CO

CO/APS: Desirable improvements for QPS Standardize QPS PM data format QPS PM data format is different from all the other PM data Other systems (PCs, BIs, etc.) have coherent/consistent format Special treatment (development) needed for QPS PM data Simplify interactions with QPS from the controls system: We do not have documentation on how to interact with QPS systems we always need to ask QPS expert how to do it The proposed solutions by QPS experts do not always work: involves several iterations of trying, with help from OP people Controls interactions not intuitive and/or too low level (e.g. waiting for PM-data-sending-finished requires 3 steps as opposed to one status flag, SEQ-930) -> specific code needed to compensate for this 03/06/154 Review of MPE activities during LS1 and outlook for LS2/LS3 - BE/CO

Agenda Application Software Development Tools Extension of QPS WorldFIP Infrastructure 03/06/155 Review of MPE activities during LS1 and outlook for LS2/LS3 - BE/CO

Feedback from CO/DO (Dev Tools + SUWG) Collaboration for software development tools CO/DO provides development tools to the acc sector Atlassian tools (Wikis, JIRA, Bamboo, Crucible) Tools: Eclipse IDE, Java build tool (CBNG), SW Repositories MPE/MS contributes and extends and helps out Customizes Eclipse and helps with support and validation Provides SONAR Quality Assurance tool for BE/CO Early adoption and collaboration on CBNG Build tool (c.f. next slide) Smooth upgrade WG (headed by Vito Baggiolini) Timely announcements of planned MPE/MS changes before TS Efficient and reliable upgrades during Technical Stops Generally excellent collaboration, mutual respect and trust! 03/06/156 Review of MPE activities during LS1 and outlook for LS2/LS3 - BE/CO

CO/DO: Bumpy collaboration on CBNG tool Started collaboration on CBNG build tool in Summer 2013 for acc- testing, looked like win-win: DO provides a new tool, MS can use new functionality Acc-testing team validates gives early feedback … but in late 2013 Technical difficulties lead to delay and suffering for acc-testing team “Overwhelming” contribution from acc-testing team destabilized CO/DO team Different priorities and objectives lead to some frustration Since April 2014 problems mostly solved 03/06/157 Review of MPE activities during LS1 and outlook for LS2/LS3 - BE/CO

Agenda Application Software Development Tools Extension of QPS WorldFIP Infrastructure 03/06/158 Review of MPE activities during LS1 and outlook for LS2/LS3 - BE/CO

FEC Optical repeater Repeater FIPDiag BEFORE LS1 AFTER LS1 QPS agents Surface Tunnel FEC QPS agents Surface Tunnel Extension of the QPS WorldFIP Infrastructure 03/06/159 Review of MPE activities during LS1 and outlook for LS2/LS3 - BE/CO

What was your groups’ contribution to MPE work? and the other way round? BE/CO took responsibility for Design of the new WorldFIP segments Procurement of the components (repeaters, FECs, etc.) Cable/Fiber installation requests Preparation, assembly and installation in LHC surface and underground areas Network Qualification Global LS1 Planning with other partners (power distribution, cabling, fibers, Ethernet, etc.) Extension of QPS WorldFIP Infrastructure 03/06/1510 Review of MPE activities during LS1 and outlook for LS2/LS3 - BE/CO

What was the impact of MPE work on your own activities? Main BE-CO LHC Hardware activity during LS1: QPS extension R2E relocation all other efforts on the Injector Complex in the context of ACCOR BE-CO resources involved for QPS extension: Infrastructure (preparation, installation, qualification) 2 FSU 100% 1 CO-FE Staff 80% Data Bases 4-5 weeks of 1 FTE Extension of QPS WorldFIP Infrastructure 03/06/1511 Review of MPE activities during LS1 and outlook for LS2/LS3 - BE/CO

What were the interfaces (Material, Personnel…) with MPE work? Please define limits of responsibilities Planning of QPS Tests: Bruno Puccio Hardware questions : Knud Petersen, Reiner Denz Software integration, Layout DBs : H.Milcent BE/CO responsibility Provision and qualification of WorldFIP low-level HW infrastructure Timing distribution FESA3 Framework Layout DBs Extension of QPS WorldFIP Infrastructure 03/06/1512 Review of MPE activities during LS1 and outlook for LS2/LS3 - BE/CO

What worked well? Planning : we appreciate the flexibility and good communication of the QPS team for all aspects related to the qualification and testing Qualification : In general the results were good The few problems encountered during the qualification process (number of agents not well balanced, change of agent location) could easily be fixed thanks to a good collaboration between the teams Extension of QPS WorldFIP Infrastructure 03/06/1513 Review of MPE activities during LS1 and outlook for LS2/LS3 - BE/CO

What went wrong? … I would rather say “What can be improved” BE/CO not involved in QPS hardware changes, which had an impact on the WorldFIP infrastructure: Remove of 220V socket in QPS crates used for the repeaters Switch of the Bus Arbiter cycle from 200ms to 100ms Upgrade of QPS to double UPS Synchronization of the work on the WorldFIP bus: WorldFIP connectors dismantled by QPS team due to new QPS crates need for a second qualification by BE/CO Feedback: BE/CO suppressed the unused repeaters asking if any performance issue, no return (no problem?) – we are at the max number of agents/segment Extension of QPS WorldFIP Infrastructure 03/06/1514 Review of MPE activities during LS1 and outlook for LS2/LS3 - BE/CO

LS1 Both QPS and BE/CO teams performed an important work during LS1 Both teams showed good flexibility and collaboration, in particular during qualification Lesson for LS2,3 The WorldFIP infrastructure is shared and any important modification deserves some better formal upfront specifications involving BE/CO Extension of QPS WorldFIP Infrastructure Conclusion 03/06/1515 Review of MPE activities during LS1 and outlook for LS2/LS3 - BE/CO