GLAST LAT Project LAT System Engineering 1 GLAST Large Area Telescope: LAT System Engineering Pat Hascall SLAC System Engineering Manager

Slides:



Advertisements
Similar presentations
GLAST LAT Project Online Peer Review – July 20, Integration and Test R. Claus 1 GLAST Large Area Telescope: I&T Integration Readiness Review.
Advertisements

GLAST LAT ProjectMarch 24, A Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS A: Tracker Test Plan Overview.
GLAST LAT Project I&T Integration Kickoff Meeting 03/09/04 Online 1 GLAST Large Area Telescope: I&T Integration Kickoff Meeting EGSE Hardware March 9th,
GLAST LAT ProjectLAT Engineering Meeting, April 1, 2003 GLAST Large Area Telescope: Performance & Safety Assurance Darren S. Marsh Stanford Linear Accelerator.
GLAST LAT Project LAT System Engineering 1 Test Definition Planning Pat Hascall SLAC System Engineering Gamma-ray Large Area Space Telescope.
GLAST LAT ProjectNovember 04, 2005 Phase 0 TRR 1 GLAST Large Area Telescope: Integration and Test -Electrical Test- Phase 0 TRR Key Requirements Documents.
GLAST LAT ProjectOnline Peer Review – July 21, Integration and Test A. T. Kavelaars 1 GLAST Large Area Telescope: I&T Integration Readiness.
GLAST LAT Project IA weekly meeting, February 3, 2006 ACD subsystem Alex Moiseev 1 ACD Pedestals ACD Team at Goddard: Alex Moiseev Dave Thomspon Bob Hartman.
GLAST June 8, 2000, P. Roger Williamson, BFP - 1 Balloon Flight Planning Roger Williamson June 8, 2000.
GLAST LAT Project Engineering Meeting – ISOC Peer Review 1 Gamma-ray Large Area Space Telescope GLAST Large Area Telescope ISOC Peer Review ISOC Detail.
GLAST LAT ProjectMarch 24, C Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS C: On-Orbit Calibration and.
GLAST LAT ProjectGLAST Flight Software IDT, October 16, 2001 JJRussell1 October 16, 2001 What’s Covered Activity –Monitoring FSW defines this as activity.
GLAST LAT Project Quarterly Review, Aug. 14, 2001 Gunther Haller1 GLAST Large Area Telescope: Electronics, DAQ & Flight Software Gunther Haller Stanford.
GLAST LAT Project4 April 2005 LAT System EngineeringLAT Test Planning Meeting GLAST LAT GLAST LAT System Engineering Gamma-ray Large Area Space Telescope.
GLAST LAT ProjectSLAC Pre - Baseline Review, April 16, 2002 ` 1 GLAST Large Area Telescope: I&T Overview WBS: Elliott D. Bloom Stanford Linear Accelerator.
GLAST LAT Project4.1.7 July 17, 03 LAT Meeting G. Haller V41 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S LAT.
GLAST LAT Project28 March 2005 LAT System EngineeringLAT Test Planning Meeting GLAST LAT GLAST LAT System Engineering Gamma-ray Large Area Space Telescope.
ISOC Peer Review - March 2, 2004 Section GLAST Large Area Telescope ISOC Peer Review Test Bed Terry Schalk GLAST Flight Software
GLAST LAT Project November 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: I&T Integration Readiness Review Integration, Facility, Configuration.
Page 1 GLAST LAT ProjectAugust 30, 2004 GLAST Large Area Telescope: LAT Accelerometer and Thermal Instrumentation Review Presented by Leonard Lee John.
GLAST LAT Project18 July GLAST Large Area Telescope: NCR 529 Systems Engineering R. Bright Gamma-ray Large Area Space Telescope.
GLAST LAT ProjectLAT Planning Meeting July 17 th and 18 th Integration and Test 1 GLAST Large Area Telescope: I & T Input to LAT Planning Meeting.
GLAST LAT Project Oct 5, GLAST Large Area Telescope Systems Engineering Test Status, NCRs and Verification Status Pat Hascall Systems Engineering.
GLAST LAT ProjectNovember 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: Integration and Test One and Two Tower Integration Readiness Review.
GLAST LAT ProjectDOE/NASA Peer Critical Design Review, March 19-20, 2003 G. Haller Monitoring V6 1 GLAST Large Area Telescope: Electronics, Data.
GLAST LAT Project May 2, 2007 NCRs and Waivers 1 GLAST Large Area Telescope Systems Engineering Test Status, NCRs and Verification Status Pat Hascall Systems.
GLAST LAT ProjectOnline Peer Review – July 21, Integration and Test L. Miller 1 GLAST Large Area Telescope: I&T Integration Readiness Review.
GLAST LAT ProjectTower Power Supply Review Sept 22, 2003 Gunther HallerPart 2, Version 4 1 GLAST Large Area Telescope: Electronics, Data Acquisition &
GLAST LAT ProjectTower Power Supply Review Sept 22, 2003 Gunther HallerPart 1, Version 3 1 GLAST Large Area Telescope: Electronics, Data Acquisition &
GLAST LAT ProjectPDU/GASU MRR, February 3, DAQ & FSWV1 1 GLAST Large Area Telescope: B. Estey, G. Haller SLAC xxxx LAT Quality Engineer
GLAST Large Area Telescope:
GLAST LAT ProjectDelta PDR/Baseline Review July 29-August 1, 2002 Section 7.3 AntiCoincidnce Detector Technical Status 1 GLAST Large Area Telescope: AntiCoincidence.
GLAST Large Area Telescope Instrument Flight Software Flight Unit Design Review 16 September 2004 Diagnostics Framework James Swain Stanford Linear Accelerator.
GLAST LAT Project4 April 2005 LAT System EngineeringLAT Test Planning Meeting GLAST LAT GLAST LAT System Engineering Gamma-ray Large Area Space Telescope.
GLAST LAT ProjectMarch 24, F Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS F: On-Orbit Calibration and.
GLAST LAT ProjectFace to Face Managers Meeting 04/14/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Face to Face Managers.
GLAST LAT Project September 15, 2006: Pre-Shipment Review Presentation 8 of 12 Thermal Vacuum Test 1 GLAST Large Area Telescope LAT Pre-Shipment Review.
GLAST LAT ProjectCAL Peer Design Review, Mar 17-18, 2003 P. Prat CNRS/IN2P3-LLR Ecole Polytechnique GLAST Large Area Telescope Calorimeter Subsystem Gamma-ray.
GLAST LAT ProjectMarch 24, C Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS C: Electronics Module Testing.
GLAST LAT Project LAT System Engineering 1 GLAST Large Area Telescope: LAT System Engineering Pat Hascall SLAC System Engineering Manager
GLAST LAT ProjectCDR/CD-3 Review May 12-16, 2003 Document: LAT-PR Section 5 IOC Subsystem 1 GLAST Large Area Telescope: IOC Subsystems WBS: 4.1.B.
GLAST LAT Project Instrument Analysis Meeting– Feb 28, 2006 Tsunefumi Mizuno TowerTrend_ ppt 1 Tracker Parameters Trending Monitor GLAST I and.
GLAST LAT ProjectFace to Face, 14 April 2004 LAT System Engineering 1 GLAST Large Area Telescope: EGSE and Interface Verification Pat Hascall SLAC System.
GLAST LAT Project IFC Tour – Sep 5,2003 Larry Wai 1 GLAST Large Area Telescope: Integration and Facility Status Larry Wai SU-SLAC Integration and Facility.
GLAST LAT Project Test Beam Meeting, Apr 18, 2006 E. do Couto e Silva 1/2 Beam Test Hardware Delivery Status Eduardo do Couto e Silva February 18, 2006.
GLAST LAT ProjectDOE/NASA Peer Critical Design Review, March 19-20, 2003 D. Nelson 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Instrument.
GLAST LAT ProjectSLAC Internal Review, April 16-18, 2002 LAT-PR Electronics and Flight Software WBS GLAST Large Area Telescope: Electronics,
GLAST LAT Project13 June 2005 LAT System EngineeringLAT Test Planning Meeting GLAST LAT GLAST LAT System Engineering Gamma-ray Large Area Space Telescope.
GLAST LAT Project SE Test Planning Dec 7, 2004 E. do Couto e Silva 1/27 Trigger and SVAC Tests During LAT integration Su Dong, Eduardo do Couto e Silva.
GLAST Large Area Telescope:
I&T&C Organization Chart
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
Electrical Ground Support Equipment Verification Test Support
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope
GLAST Large Area Telescope:
GLAST LAT System Engineering
GLAST LAT System Engineering
Introduction and Overview
Overview Cost to Complete
Integration & Test Instrument Operations Coordination
GLAST Large Area Telescope:
GLAST Large Area Telescope:
Presentation transcript:

GLAST LAT Project LAT System Engineering 1 GLAST Large Area Telescope: LAT System Engineering Pat Hascall SLAC System Engineering Manager Gamma-ray Large Area Space Telescope

GLAST LAT Project LAT System Engineering 2 Topics Meeting goals –Review action items –Discuss TEM and TEM/PS subsystem testing –Define tests to be performed on the TEM and TEM/PS tests during LAT integration and acceptance testing –Gain a common understanding of “calibration” Team Goals –Define test requirements necessary through December Tracker and Cal post delivery tests Cal tests post integration with TEM and TEM/PS Tower integration tests Multi tower tests (without ‘final’ flight software) Third layer boxes tests as necessary –Testing with next delivery of flight software, all third layer boxes and ACD will be defined in the next phases

GLAST LAT Project LAT System Engineering 3 TEM Power Supply Testing This note summarizes the testing done on the TEM power supply to verify performance against it’s specification. The goal of the meeting Monday will be to define the testing that will be done on the TEM power supply during various phases of the Integration and Test sequence. There will be no attempt to measure lower level performance parameters (such as noise spikes) at the LAT level – the assumption is that the TEM power supply comes tested and certified to meet those requirements The expectation is that many of the LAT level TEM/PS tests will be covered as part of other planned LAT level tests. –Command functional test will include Turn on tower power supplies one at a time. Verify the telemetry from the TEM/PS shows expected voltages and currents based on subsystem test. Verify that the LAT current consumption delta matches expected values. Turn on the calorimeter and verify the expected change in current both through telemetry and at the power source. Turn on the tracker and verify the expected change in current through the telemetry and at the power source. (other calorimeter and tracker telemetry will also be verified separately)

GLAST LAT Project LAT System Engineering 4 TEM/PS Subsystem Test Summary Based on From Tower Power Supply Extended Test Procedures, LAT-TD , Draft dated 12/17/03 The following parameters are measured for the 1.5 VDC, 2.5 VDC, 3.3 VDC and variable bias voltages: –Accuracy –RMS noise –Bandwidth –noise spikes –line regulation –load regulation –power up output voltage rise time –power down voltage fall times

GLAST LAT Project LAT System Engineering 5 TEM/PS Subsystem Test Summary (continued) The specific voltages that are measured are: –CAL3_3V Dg –CAL3_3V An –CAL_Bias –TKR2_5 Dg –TKR1_5 An –TKR2_5 An –TKR_Bias –TEM2_5 Dg –TEM3_3V Dg

GLAST LAT Project LAT System Engineering 6 TEM/PS Subsystem Test Summary (continued) The two temperature sensors are monitored but not otherwise tested. The TEM/PS includes the capability to turn on or off the Calorimeter power conversion and to turn on or off the Tracker power conversion. That capability is not explicitly tested. The CAL bias and tracker bias both have an analog control signal (0-2V) that come from the TEMs. The bias circuits have a current monitor capability. The current test procedure does not explicitly test either capability. Voltage levels are routed to the TEM for telemetry purposes. (higher level spec says that these telemetry points will be calibrated)

GLAST LAT Project LAT System Engineering 7 LAT Level Tests on the TEM/PS Temperature sensors verified during thermal vac, sanity check performed during integration Calorimeter and Tracker turn-on and turn-off capability tested as part of command functional testing What are recommended tests for the Cal and tracker bias? Will the TEM and TEM/PS be tested as a pair and the telemetry calibrated as a pair? What is recommended receiving test at I&T?

GLAST LAT Project LAT System Engineering 8 TEM Testing TEM subsystem testing (From Tower Electronics Module (TEM) Extended Performance Test Procedures, LAT-TD , Draft dated 11/25/03) –Summary in table on next slide. Tests primarily focus on register testing Interface tests to the GASU are not yet defined Telemetry calibration and checkout are not yet defined Power consumption tests are not defined

GLAST LAT Project LAT System Engineering 9 TEM Subsystem Test Summary

GLAST LAT Project LAT System Engineering 10 Questions: What are recommended tests when TEM and TEM/PS are integrated What are recommended tests when TEM and TEM/PS are integrated to the calorimeter? What are recommended tests when the Tracker is integrated? What are recommended tests when the tower is integrated into the grid, and for later comprehensive tests?