ISO Proposed Flexible Capacity Requirements Stephen Keehn Senior Advisor California ISO CPUC Workshop January 26, 2012.

Slides:



Advertisements
Similar presentations
Pacific Gas and Electric Company Long Term Procurement Plan Proceeding Renewable Integration Model Results and Model Demonstration October 22, 2010 Workshop.
Advertisements

Demand Resource Operable Capacity Analysis – Assumptions for FCA 5.
TIM MASON RENEWABLE RESOURCE INTEGRATION IEP ASSOCIATION ANNUAL MEETING FALLEN LEAF LAKE 5 October 2011.
ENERGY VALUE. Summary  Operational Value is a primary component in the Net Market Value (NMV) calculation used to rank competing resources in the RPS.
Amendment 3/5 Workshop.
Preliminary Impacts of Wind Power Integration in the Hydro-Qubec System.
R RA Phase II Proposals Workshop (day 2) January 25, 2011 Court Yard room 10:00 am- 2:45 pm.
1 R Phase I Resource Adequacy Workshop presentation March 30, am to 5 pm California Public Utilities Commission 505 Van Ness Ave.
Power Supply Adequacy Assessment Model/Methodology Review Steering Subcommittee Meeting January 29, 2010.
CPUC Procurement Policies Robert L. Strauss California Public Utilities Commission Energy Division - Procurement Section.
1 Resource Adequacy (RA) Workshop Presentation by: Sue Mara On Behalf of: Alliance for Retail Energy Markets (AReM) January 18, 2011.
California Energy Commission Resource Adequacy Demand Forecast Coincidence Adjustments R Resource Adequacy Workshop January.
1 R : LTPP Track II Workshop – Operating Flexibility Modeling Results Patrick Young Analyst, Generation & Transmission Planning California Public.
Jim Mcintosh Director, Executive Operations Advisor California ISO Independent Energy Producers 2011 Annual Meeting - October 5, 2011 Stanford Sierra Conference.
Compare and Contrast ELCC Methodologies Across CPUC Proceedings
ENERGY ONLY RESOURCES & THE RPS CALCULATOR. Deliverability Overview Most resources procured to date have been procured to be fully deliverable – CAISO.
INTEGRATION COST. Integration Cost in RPS Calculator While “Integration Cost” is included in NMV formulation, the Commission stated that the Integration.
Resource Adequacy Forecast Adjustment(s) Allocation Methodology
The impacts of hourly variations of large scale wind power production in the Nordic countries on the system regulation needs Hannele Holttinen.
Utah Schedule 37 Update June 25, Schedule 37 Background Schedule 37 – Published rates for standard power purchase agreements with qualifying facilities.
Wind Cost Allocation Task Force Update to WMS February 17, 2009.
National Renewable Energy Laboratory Innovation for Our Energy Future * NREL July 5, 2011 Tradeoffs and Synergies between CSP and PV at High Grid Penetration.
Joel Koepke, P.E. ERCOT Operations Support Engineer ERCOT Experiences During Summer 2011.
Long Term Study Task Force Update to ETWG ERCOT Long-Term Study: Scenarios, New Software, and Emerging Technology Assumptions January 27, 2012.
IEGC PROVOSIONS FOR RENEWABLE GENERATION SCHEDULING & UI SETTLEMENT 1.
ERCOT Tool to manage unexpected incremental load November 16, 2006.
Julia Matevosyan, Resource Adequacy January, 2014 Application of KERMIT in the DOE LTS process.
Sai Moorty ERCOT Integration Options into ERCOT systems.
Resource Adequacy Workshop: DG Deliverability and Flexible Capacity Procurement R January 23, 2012 CPUC Auditorium Phone ‐ ; Code:
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N 2009 Draft Resource Program Released: September 30, 2009 Accepting Comments until: November 30,
ENERGY CENTER State Utility Forecasting Group (SUFG) Alternative Resources and Energy Capacity Presented by: Douglas J. Gotham Purdue University Presented.
PRS - RPRS Task Force Status Summary - August 14, PRS RPRS Task Force Status Summary Prepared for WMS and PRS August 2006.
California ISO – Internal Use Only Flexible Capacity Requirement CPUC RA Workshop March 30, 2012 Mark Rothleder Executive Director Market Analysis and.
Benefits of a Multi-year Resource Adequacy Program May 20, 2014 Karl Meeusen, Ph.D., Market Design and Regulatory Policy Lead Market and Infrastructure.
Resource Adequacy for Distributed Generation January 27, :15 am to 12 noon Energy Division staff discussion Megha Lakhchaura.
Proposal to update default solar NQCs (R , Phase 2) Resource Adequacy Workshop January 25, 2011.
GHG, Renewables, and Reliability IEP ANNUAL MEETING SEPTEMBER 29, 2015 Carrie Bentley Resero Consulting
RGGI Workshop on Electricity Markets, Reliability and Planning Topic Session 3: RGGI Design, Markets and Reliability – Issues Relating to System Operations.
Renewables and System Services Ann Scully.
Resource Adequacy Steering Committee Meeting October 4, 2011.
1 1 Beacon Power Corporation Energy Storage – Regulation Issues Prepared for: Emerging Technologies Working Group January 5, 2011.
Power Association of Northern California Maintaining Grid Reliability In An Uncertain Era May 16, 2011 PG&E Conference Center Jim Mcintosh Director, Executive.
October 29, Organizational role of Short-Term Planning and Hydro Duty Scheduling Relationship to other groups in BPA Planning and analysis job.
SOUTHERN CALIFORNIA EDISON SM Southern California Edison Company’s Proposal to Participate in Convergence Bidding August 23, 2010.
09/17/2006 Ken Donohoo ERCOT Peak Day August Initial Settlement Data by Fuel Type.
Resource Adequacy Assessment for 2015 Resource Adequacy Forum Technical Committee Meeting October 1, 2010.
Long Term Study Resource Expansion Process: Study Findings and Lessons Learned Jenell Katheiser Doug Murray RPG May 21, 2013.
Presentation Title SOUTHERN CALIFORNIA EDISON® SM SOUTHERN CALIFORNIA EDISON® SM Regulatory Policy SCE Discussion on the Relationship Between NQC and EFC.
Presentation Title SOUTHERN CALIFORNIA EDISON® SM SOUTHERN CALIFORNIA EDISON® SM Regulatory Affairs Demand Response and Local RA Criteria Discussion
RFPEG2013 PRE-BID MEETING RFPEG2013 – Pre-Bid meeting January 9, 2014 Presentation by Derek Davis – Public Utilities Commission.
Future Ancillary Services Cost Benefit Analysis Overview Julia Matevosyan February 1, 2016 FAS Workshop.
Planning the Networked Grid Transmission Planning J.E.(Jeff) Billinton Manager, Regional Transmission - North Building the Networked Electricity Grid –
Understanding Value of Short-Duration Resources CPUC RA Workshop March 5, 2016.
April 5, 2016 CPUC. JDRP Proposal  Flexible RA Attributes and requirements should be unbundled from the underlying system RA and Local RA attributes.
1 Meredith Younghein Energy Division Local RA Requirements for Demand Response Resources: Staff Proposal.
1 PG&E Proposals for Refinements to the Resource Adequacy (RA) Program Compliance Year 2017 RA Workshop February 18, 2016.
1 R Phase I Resource Adequacy Workshop presentation – Day 1 January 26 and 27, am to 5 pm CPUC offices 505 Van Ness Ave San Francisco,
California Senate Energy, Utilities and Communications Committee Oversight Hearing May 10, 2016 Southern California Edison Colin Cushnie Vice President,
CPUC Resource Adequacy Program – LAO briefing May 25, 2009.
Capping Local RA Requirements at System RA Requirements February 9, 2015 Karl Meeusen California ISO.
Shaping Up The Duck Chart Independent Energy Producers Association Annual Meeting Mark Rothleder Vice President, Market Quality and Renewable Integration.
Variable Energy Resource Capacity Contributions Consistent With Reserve Margin and Reliability Noha Abdel-Karim, Eugene Preston,
Current FRRS Language & Explanation of Posted Data
Recommended Hydro Improvement April 11, 2017
Out of Region Market Assumptions
Resource Adequacy Demand Forecast Coincidence Adjustments
30 Minute Reserves EPFSTF January 4,
Recommended Hydro Improvement April 11, 2017
Forecasting and Operations CAISO Case
Jim Mcintosh Director, Executive Operations Advisor California ISO
Presentation transcript:

ISO Proposed Flexible Capacity Requirements Stephen Keehn Senior Advisor California ISO CPUC Workshop January 26, 2012

The ISO proposes adding flexible capacity requirements to the existing RA program The requirements: –Three flexible capacity categories based on system needs from Renewable Integration Studies Maximum ramping Load following Regulation –Applies system-wide to the entire RA fleet The ISO proposes for 2013 that the requirements be based on the capabilities of the 2012 RA fleet For subsequent years, the requirements will be calculated from historical analysis of system net load data

LSEs have the first opportunity to satisfy the requirement and cure any deficiencies The ISO will determine the amount of flexible capacity it requires in each category After LSEs make their 2013 RA showings, the ISO will determine if the 2013 RA showings in aggregate satisfy the requirements in the three flexible capacity categories If there is a deficit in any of the flexible capacity requirements, LSEs have the opportunity to cure the deficiency If the deficit remains, the ISO will exercise its backstop procurement authority to cure the deficiency

The cost of ISO backstop procurement will be assigned first to the deficient LSEs Backstop procurement costs will be allocated to those LSEs that did not satisfy the flexible capacity requirements –Example of how this could work: Assume RA requirement is 50,000 MW and load following flexible requirement is 10,000 MW Percentage is 20% Cost of backstop would be allocated to LSEs with less than 20% of their RA portfolio as load following in proportion to their shortage relative to all LSE shortages Exact mechanism will be developed in ISO stakeholder process Page 4

Flexible capacity procurement will require other changes to RA program Flexible capacity requirements will be assessed on a monthly basis –Allows resources to have different flexible capacity amounts in different months of the year –Flexible needs may not correspond directly to total RA needs Year-ahead RA showings will be for the entire year, not just the 5 summer months –Ramping needs are a concern in the shoulder months when renewable output is high but load is low

The CAISO proposes three flexible capacity categories, and, therefore, requirements Maximum Ramping –To meet maximum expected continuous ramp need Load Following –To meet dispatch needs Regulation –To ensure sufficient regulation capacity

Resources can have flexible capacity that fulfills requirements in the different categories

Flexible Capacity Requirements for the 2013 RA Compliance Year For 2013 ISO proposes basing requirements on capabilities of 2012 RA Fleet –Simple basis for 2013 needs determination –ISO believes that maintaining the same flexibility as the 2012 RA fleet will ensure reliability in 2013 –Allows time for further analysis and stakeholder discussions to refine requirements for 2014 and beyond For 2013, to calculate flexible capacity requirements: –Calculate annual fleet flexibility capability for peak summer month –Apply factor for each month Factor is ratio of monthly load level to peak summer month load level Page 8

ISO 2013 RA Flexible Capacity Requirements Based on the 2012 RA Fleet Capabilities Maximum Ramping22,055 MW –Includes steam and gas turbines, excludes hydro 30,955 MW (if incl. hydro) Load Following 9,696 MW –Includes steam and gas turbines, excludes hydro Regulation 1,380 MW –Includes hydro Page 9 These values are illustrative and based on August 2012 annual showings

Requirements will be refined for 2014 and beyond To be determined by analysis of load (net of solar and wind) system variability –ISO is still studying and validating approach –Not just ramping need for the time period, but must account for: Units on forced outages Forecast errors Use limited resources Units on line vs. off-line –The load following and regulation requirement must account for both up and down capability –Flexibility requirements must link to obligations of units For example, resource may not self-schedule to qualify as a flexible capacity resource Page 10

Description- Maximum Ramping Units must be able to respond to ISO dispatch instructions –Intermittent generation, baseload units, and units that self-schedule do not count Requirement determined by largest continuous ramp –Total MW of ramp –Continuous ramp for 5 minute dispatch For 2013 propose to set requirement based on ramping capability from resources that are dispatchable and not use limited

Description- Maximum Ramping ( cont.) Each resource’s contribution to maximum ramping capacity over the time period is: –NQC - Pmin if the unit cannot start fast enough –NQC if the unit can start and get to its NQC in the ramp interval This may overstate the ramping capability of the fleet –Units requiring the full time to ramp their capacity can only provide their maximum ramp capacity if started ramping at the beginning of the ramp period –this must be accounted for in calculating the max ramping requirement in subsequent years Page 12

Description- Load Following For 2014 and beyond, requirement is the 15 minute ramping capacity need based on the ISO’s largest 15 minute net load ramp expected for the month For 2013 this value will be based on the amount of 15 minute ramp capability of the dispatchable 2012 RA fleet Each resource’s contribution is the minimum of NQC – Pmin RampRate * 15 minutes Where: RampRate is the unit’s MW/min weighted average ramp rate

Description- Regulation The regulation requirement is expressed in MW/min Units must be regulation certified by the ISO Ramp rate is based on a unit’s MW weighted average ramp rate as certified by the ISO

A unit may fulfill requirements in several flexible capacity categories- Example 1 Example 1: –NQC = 500 MW, Pmin = 300 MW –Ramp rate =10MW/min, regulation certified –3 hour start-up –Not self-scheduled Provides the following RA capacity: Generic:500 MW (NQC) Maximum Ramping500 MW (NQC, start < Max Ramp Time) Load Following150 MW (10 MW/min * 15 min) Regulation 10 MW/min Page 15

A unit may fulfill requirements in several flexible capacity categories- Example 2 Example 2: –NQC = 500 MW, Pmin = 200 MW –ramp rate =5 MW/min, not regulation certified –18 hour start-up –not self-scheduled Provides the following RA capacity: Generic:500 MW (NQC) Maximum Ramping300 MW (NQC - Pmin, start > Max Ramp Time) Load Following150 MW (10 MW/min * 15 min) Regulation 10 MW/min (not regulation certified) Page 16

Use limited resources need further consideration in the context of flexible capacity The ISO has not fully determined the potential impacts of Use Limited Resources (ULRs) on the flexible capacity requirements For this year, the ISO believes that the Energy Division proposal for revised MCC buckets that incorporate dispatchability may have potential to address ULRs –May require refinements to the definitions of some of the buckets Excluding hydro for 2013 should also be considered Page 17

ISO Proposed Flexibility Requirements and Potential Relationship to Energy Division Proposed Buckets Page 18 CurrentProposedISO Recommended Flexibility Requirements Bucket Name Monthly hours of operatio n Maximum cumulativ e percentag e of resources Operatio nal Characte ristics Hours of operation Maximum Cumulative percentage of resources Operation Characteristi cs Capacity (MW) Ramp Duration -15 minute ramp -Longest Duration (minutes) Average Speed (MW/min) Comment Bucket 4 All hours 100%NoneAll hours100%Dispatchable 7,736 20, Steam Turbines Bucket %NoneAll hours>60% Non- dispatchable Bucket %None Limited hours <50%Dispatchable 1,960 2,011 ~8, GT Hydro Bucket %None Limited hours <25% Non- dispatchable ,830 7,403 Regulation These values are illustrative and based on August 2012 annual showings