November 16, 2012 Synchrophasor Meeting Dynamic Model Validation Project Jonathan Rose Engineer, Resource Integration Sidharth Rajagopalan Engineer, Dynamic.

Slides:



Advertisements
Similar presentations
WECC JSIS Update Dmitry Kosterev, BPA.
Advertisements

BPAs Generator Model Validation Technique/Tool MVWG Denver, CO May 18-19, 2009 Steve Yang Bonneville Power Administration.
Using Synchrophasors for Preventing Cascading Outages
New Energy Horizons Opportunities and Challenges Fault Current Contributions from Wind Plants Dean Miller PacifiCorp July 25,
ISO New England Smart Grid Investment Grant Update David Bertagnolli – NASPI Working Group Meeting October 12-13,
Marianna Vaiman, V&R Energy
Multi Functional Digital Fault Recorder
The Model Validation Story 1. You’ve heard this story before August 10, 1996 Accurate and up-to-date models are needed for reliable and economic grid.
Idaho Power Update JSIS Meeting March 3, Infrastructure PMU installations: 24 PMU sites: 15 WISP PMU Installations: 5 WISP PMU sites: 3 WISP installations.
Development of Damping Algorithm Olof Samuelsson Industrial Electrical Engineering and Automation
and Trend for Smart Grid
Frankfurt (Germany), 6-9 June 2011 Douglas Wilson Psymetrix Ltd, UK Douglas Wilson Psymetrix Ltd, UK D. Wilson – UK – Session 4 – Paper ID 0497 Connection.
ERCOT VRT Study, Phase I ERCOT ROS Meeting December 10, 2009.
Using Synchrophasor Data to Diagnose Equipment Mis-operations and Health Alison Silverstein WECC JSIS Meeting, September 10,
© Electric Power Group All rights reserved. W IND F ARM O SCILLATION D ETECTION AND M ITIGATION WECC Joint Synchronized Information Subcommittee.
Prepared by Tony Weekes Husam Al Hadidi Brian Archer.
1 1 Office of Science Lawrence Berkeley National Laboratory Distribution µ PMU Applications Joe Eto Emma Stewart
Introduction to Phasor Measurements Units (PMUs)
Damping assessment using relative phase information from PMU data
1 New Resource Qualification Testing Sandip Sharma Supervisor, Operations Analysis New Generation Information Forum ERCOT Public November 4, 2014.
NERC Lessons Learned Summary
SCADA and Telemetry Presented By:.
Generator Data Submittals 5/8/ Transmission Customer Forum Bob Jones Transmission Planning Southern Company Transmission 5/8/ Transmission.
Review of BPA Voltage Control Conference
Academic Experience with Wide Area Sensors by Virgilio Centeno Virginia Tech PSC, Distributed Generation, Advanced Metering and Communications March 9,
SSR Control of Power Systems
Synchrophasor Measurement Implementation in ERCOT
From Fault Recording to Disturbance Recording
Synchrophasor: Implementation,Testing & Operational Experience
PROJECT NO PUCT STAFF WORKSHOP 11/19/14 Julia Harvey Kristi Denney Kevin Mathis Jasmin Thevaril.
Lessons Learned from the Texas Synchrophasor Network by Presented at the North American Synchrophasor Initiative (NASPI) Meeting Toronto, Ontario Thursday,
1 U.S. Energy Information Administration, Annual Energy Review All energy input US average = 90.3 MWh per person, per year. Corresponds to 10.3 kW.
V&R Energy’s Project under PRSP: Grid Operator’s Monitoring & Control Assistant (GOMCA) Marianna Vaiman, V&R Energy JSIS Meeting.
NERC Event Analysis Update Member Representatives Committee Meeting October 28, 2008 Robert W. Cummings NERC Director of Event Analysis & Information Exchange.
1 Application of Synchrophasor Technology To CREZ System CREZ Technical Conference January 26, 2010 Navin Bhatt American Electric Power.
Frankfurt (Germany), 6-9 June 2011  PV in Spain: Basically Large plants connected to MV or HV Mainly in rural areas (generation exceeds consumption) 3,000.
CASE STUDY Disturbance event comparing PMU and SE voltage angle difference in ERCOT Prakash Shrestha Operations Engineer Advanced Network Application.
SRWG Meeting 15-2 Power Plant Validation Tools Eric Bakie July 2015.
©2009 Mladen Kezunovic. Improving Relay Performance By Off-line and On-line Evaluation Mladen Kezunovic Jinfeng Ren, Chengzong Pang Texas A&M University,
ECE 476 Power System Analysis Lecture 22: System Protection, Transient Stability Prof. Tom Overbye Dept. of Electrical and Computer Engineering University.
PMUs for NERC Reliability Standards Ryan D. Quint, Ph.D., P.E. Staff Coordinator, NERC SMS, SAMS WECC JSIS Meeting September 22, 2015.
JSIS Report for PCC Donald Davies for Dmitry Kosterev, JSIS Chair W ESTERN E LECTRICITY C OORDINATING C OUNCIL.
Model Validation using PSS®E
Imagination at work. Paddy McNabb Senior Engineer January 2016 Grid Stability Applications Wide Area Monitoring System.
Voltage Control Brad Calhoun Consultant, Sr. Trainer Spring 2016.
Protection of Power Systems
WECC Joint Synchronized Information Subcommittee Report Planning Coordination Committee Meeting March 22,
Slaven Kincic MVWG March System Model Validation Task Force (SMVTF) System Events for System Model Validation o 21th January event:  Colstrip.
1 PSSE Playback Model Validation with PMU Data Damien Sommer, P.E. Senior Transmission Planning Engineer.
SEMINAR PRESENATATION ON WIDEAREA BLACKOUT (AN ELECTRICAL DISASTER) BY:Madhusmita Mohanty Electrical Engineering 7TH Semester Regd No
| Electric Power Group Presents Maximizing Use of Synchrophasor Technology for Everyday Tasks Welcome! The meeting will begin at 2:00 p.m. EDT / 11:00.
Discovery Across Texas: Technology Solutions for Wind Integration in ERCOT Using Synchrophasor Technology for Wind Integration and Event Monitoring in.
2017 WECC JSIS Report March 21, 2017.
ISO-NE Synchrophasor Related Projects
Western Electricity Coordinating Council
PSCAD models.
Progress Report for the May 26th 17:31 Event
CCET Discovery Across Texas Data Quality Plan - Overview
Texas Nodal Load Frequency Control (LFC) EDS 3 R6
Gaurav Sharma John Hannah Vivekanand Sivaraman
Electric Power Group Presents Maximizing Use of Synchrophasor Technology for Everyday Tasks Welcome! The meeting will begin at 2:00 p.m. EDT / 11:00.
Gaurav Sharma John Hannah Vivekanand Sivaraman
Wind Farm Oscillation Detection and Mitigation
PSSE Playback Model Validation with PMU Data
2017 WECC JSIS Report March 21, 2017.
NASPI PMU Data Application Classification
WECC Joint Synchronized Information Subcommittee
Model Validation for Large Scale PV Plants
SRWG Meeting 15-2 Power Plant Validation Tools
2018 CG MOD 33 updates CG Planning Meeting June 7, 2018
Presentation transcript:

November 16, 2012 Synchrophasor Meeting Dynamic Model Validation Project Jonathan Rose Engineer, Resource Integration Sidharth Rajagopalan Engineer, Dynamic Studies

2 Need for Model Validation… Synchrophasor MeetingNovember 16, 2012 Source: sentations/1/ %20Power%20Plant%20Model%20Validation%20Using%20Disturbance%20Data.pdf

3 Validation Methodology Compare computer simulations to actual generator behavior, measured during a disturbance. Synchrophasor MeetingNovember 16, 2012 Compare Results Field Measurements PMUs, DFRs... Pass / Fail

4 Overview Near Term Goals –Validate a few generator dynamic models based on available measured response during system events. Long Term Goals –Develop plan to systematically validate generator models in ERCOT. –New responsibilities? (NERC MOD Standard) Resource Entities, ERCOT, TSP –Install measurement devices PMU at every power plant Synchrophasor MeetingNovember 16, 2012

5 Challenge #1: Gathering Measurements Existing PMUs available to ERCOT –Installed for specific purpose of transmission observability. –none measure generator output Some gen companies have continuous fault recorders –Difficult to access data. “Leap-frog” communication. –Need coordination on setting up recorders. This issue is unresolved. –Only attempted to validate Governor models. Synchrophasor MeetingNovember 16, 2012 POI Generator High-speed measurements of V, , P, Q, Hz. >= 30 samples / second. Measure unit output, not plant.

6 Possible Solution #1: Gathering Measurements Install PMU or proper set Continuous DFR at each generator –Does not need to stream live data. (Communication $$). –PMU preferred over DFRs. –Installation and Maintenance Provide easy access to data Synchrophasor MeetingNovember 16, 2012 POI Generator Need method to easily get data to ERCOT.

7 Challenge #2: Identifying Disturbances AvailableDifficult Frequency disturbancesVoltage disturbance (e.g. faults) Angle disturbance due to unit tripAngle disturbance due to line open Synchrophasor MeetingNovember 16, 2012 Problem: Some stochastic disturbances difficult to monitor and identify. Possible Solution: Move a nearby switched shunt. Change generator voltage set point.

8 Brainstorming A Synchrophasor Plan… PMUs for Operational Needs –Stream live data. –Penetration: capture system condition PMUs for Generator Model Validation –Archive data for 30 days. Data downloaded as needed. –Measure terminal behavior of each plant. Overlap? –Some generator PMUs stream data for Operations. Synchrophasor MeetingNovember 16, 2012

Questions? Thank You November 16, 2012Synchrophasor Meeting

10 Synchrophasor MeetingNovember 16, 2012 ADDITIONAL MATERIAL

11 Overview of Validation Process 1.Capture electrical measurements during a disturbance using PMU. Need plant-level or unit-level measurements. 2.Introduce disturbance and measurements into simulation. 3.Check that the simulated response matches plant actual response. 4.If not, discuss the results with the resource entity. Synchrophasor MeetingNovember 16, 2012 Field Measurem ents POI Present independent variables (V, , Hz) to Generator Test Generator Comparison Measure vs. Simulation  Pass /Fail.

12 Example – Simple Model Validation Exercise SPWG MeetingNovember 16, 2012Synchrophasor Meeting

13 Types of Measurement Devices Phasor Measurement Units –Stand-alone measurement device. High-fidelity. Synchrophasors –Relay with PMU-like features. High-fidelity. –E.g. Schweitzer 421. Digital Fault Recorders (Continuous) –Predecessor to synchrophasors. –Similar to PMUs except no GPS-clock and cannot measure angle. –May or may not be able to stream live measurements. Digital Fault Recorders (Triggered) –Oscilloscope-type measurements that are triggered. Used for relay performance reviews, event forensics, etc. SCADA Synchrophasor MeetingNovember 16, 2012

14 Measurement Device Comparison High Speed Real Time GPS Clock Angle Meas Penetra- tion Model Validation PMU & Synchroph. ~50 DFR 100’sDifficult SCADA 1000’s Governor Only November 16, 2012Synchrophasor Meeting

15 ResponseDisturbances GENFastFault, sudden angle shift due to nearby unit trip / line open. AVRFastFault, switched shunt adjust, V-schedule adjust. GOVSlowLarge unit trip anywhere. PSSFastNearby unit trip or line open. Gathering Measurements – Need a Good Disturbance! AVR GOV PSS V meas Hz d  /dt Q gen P gen The nature of the disturbance determines which system is affected. –Multiple disturbances needed to validate all parts of model. d  /dt V P gen, Q gen Machine Synchrophasor MeetingNovember 16, 2012

16 Disturbances Voltage Disturbances are difficult to find! –Wait for a fault? How know when it happened? WECC creates their own disturbances –1400 MW Chief Joseph braking resistor. Could ERCOT do similar? –Disturb generator by adjusting nearby tap, switched shunt or change Voltage set point. Chief Joseph: November 16, 2012Synchrophasor Meeting

17 Synchrophasor MeetingNovember 16, 2012