Internal H0/H- dump M. Delonca, C. Maglioni On behalf of EN/STI Thanks to: A. Christov, S. Mathot, C. Pasquino, A. Patapenka
Outline Issues to be addressed (from last follow-up) Loading cases (remember) FOMS and choice of material(s) Methods of fixation Space & layout Preliminary analyses : – Instantaneous DT – Transient to steady operation – Steady operation Does the dump need active cooling ? Conclusions and next steps 2C.Maglioni, M.Delonca - Review on PSB 160 MeV H - Injection20/03/2012
From last follow-up 3C.Maglioni, M.Delonca - Review on PSB 160 MeV H - Injection20/03/2012
Loading cases 4C.Maglioni, M.Delonca - Review on PSB 160 MeV H - Injection Operation: Three loading case (following stripping efficiency): (1) e = 98% (foil operational) (2) e = 90% (foil degraded) (3) e = 0% (foil accident) 4/4 Linac4 Beam loading case (foil accident + distributor failure) › Steady-state, 2% all H0, 0.8mA › Steady-state, 10% all H0, 4mA, 8h max › Transient 1/4 Linac4 pulse, 40mA, 100% H- (interlock after 1 pulse) › not considered EDMS /03/2012
5C.Maglioni, M.Delonca - Review on PSB 160 MeV H - Injection Copper part inserted into Steel flange Methods of fixation 20/03/2012 Metallization + Brazing Shrinking For both solution: - Copper part inserted into Steel flange
FOMS and choice of material(s) 6C.Maglioni, M.Delonca - Review on PSB 160 MeV H - Injection Ceramic material To be minimized 20/03/2012
FOMS and choice of material(s) 7C.Maglioni, M.Delonca - Review on PSB 160 MeV H - Injection Note: Boron Nitride and Aluminum Nitride as from first study (EDMS ) First test with Al300: possible to be welded to copper (already used at CERN) 20/03/2012 Which is an acceptable value ? Alternative solutions ?
Space & layout 8C.Maglioni, M.Delonca - Review on PSB 160 MeV H - Injection The flange has to be adapted to the assembly / fixation / cooling needs of the dump EDMS The instrumentation has to be fixed on the dump (front face) The dump is one-piece with the flange (ALARA, quick exchange / disassembly) 20/03/2012 Area to be modified for the cooling/bake-out of the dump, possibly no feed-through mm
Instantaneous T – Al300 9C.Maglioni, M.Delonca - Review on PSB 160 MeV H - Injection Half dump BOTTOM view, T due to 1/4 Linac4 pulse (3) 20/03/2012 Case 3 H- beam 33mrad
Instantaneous eq. Stassi – Al300 10C.Maglioni, M.Delonca - Review on PSB 160 MeV H - Injection Half dump BOTTOM view, T due to 1/4 Linac4 pulse (3) Limit in tension: 184 Mpa Safety factor tension : 6.3 Limit in compression: 1840 Mpa Safety factor compression : /03/2012 Case 3 Fixed support from the back H- beam 33mrad
Steady operation – Al300 11C.Maglioni, M.Delonca - Review on PSB 160 MeV H - Injection ~ 40 m expansion (case 2) Circulating H+ beam Half dump BOTTOM view, T due to steady-state operation H 0 beam 20/03/2012 Cooling due to radiation ONLY with Ambient – not conservative Case 1 Case 2 Temperature on back-flange
Transient to steady operation 12C.Maglioni, M.Delonca - Review on PSB 160 MeV H - Injection20/03/2012 Steady State considering radiation only with ambient – not conservative
Does it need active cooling? 13C.Maglioni, M.Delonca - Review on PSB 160 MeV H - Injection20/03/2012 First analysis with no active cooling show good results BUT – Radiation exchange with the ceramic chamber ↗ Steady state temperature in dump – Conduction between Cu insert and Steel flange Does the temperature in the back-flange stay within acceptable values? Detailed analyses are required.
Conclusions and next steps 14C.Maglioni, M.Delonca - Review on PSB 160 MeV H - Injection20/03/2012 New material configurations are under study: Ceramic dump: reduction of the dump length (avoid the risk of scraping of the H+ beam) Lower degasing / no (or less) baking required wrt Graphite possibility of brazing on Copper/Steel insert (for dump support) – better in case of active cooling possible only with some ceramics, analysis ongoing low electrical conductivity : the H + beam continuously charge the dump (H 0 H + from instrumentation on entrance face) electrical discharge through vacuum? To be studied Need of active cooling system to be detailed Beam instrumentation integration to be taken into account
Thank You 15C.Maglioni, M.Delonca - Review on PSB 160 MeV H - Injection20/03/2012