Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)

Slides:



Advertisements
Similar presentations
Spectrometer Solenoid Update Steve Virostek - LBNL MICE VC 150 August 23, 2012.
Advertisements

Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
Magnet Cooldown Scheme 17 th February 2012 Roy Preece (STFC RAL)
Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.
MICE Collaboration meeting May 31 st – June 3 rd 2009 RAL Tim Hayler, Andy Lintern DRAFT SEQUENCE OF EVENTS STEPS
Spectrometer Solenoids MICO 146 Steve Virostek LBNL June 6, 2011.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab MICE Video Conference 114 September 18, 2008.
128 April 2008 Spectrometer Solenoid Fabrication Update MICO Meeting 19 May 2008 S. Virostek, M. Zisman LBNL.
Spectrometer Solenoid Design and Procurement Review Steve Virostek Mike Green Mike Zisman Lawrence Berkeley National Lab MICE Collaboration Meeting October.
MICE Collaboration meeting at CERN March 28 – April 1, 2004 MICE Cooling Channel --- AFC Module work group report Wing Lau – Oxford.
23 October 2005MICE Meeting at RAL1 MICE Tracker Magnets, 4 K Coolers, and Magnet Coupling during a Quench Michael A. Green Lawrence Berkeley Laboratory.
Spectrometer Solenoid Report and Coupling Coil Update Michael S. Zisman MICE Operations Manager Center for Beam Physics Lawrence Berkeley National Laboratory.
Spectrometer Solenoid Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICO.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 14, 2009.
Spectrometer Solenoid Update Steve Virostek - LBNL MICE Video Conference #129 February 25, 2010.
MICE Video Meeting, 10 Jan 081 Spectrometer Magnet Progress Michael A. Green Lawrence Berkeley Laboratory.
1S. Virostek - LBNL Spectrometer Solenoid Fabrication Update S. Virostek and M. Green are visiting vendor today for progress update Vendor expects to complete.
Spectrometer Solenoid Update Steve Virostek - LBNL MICE Video Conference #145 December 15, 2011.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM24 at RAL June 1, 2009.
1S. Virostek - LBNL Spectrometer Solenoid Fabrication Update Vendor still expecting to complete first magnet by the end of November, before X-mas more.
Spectrometer Solenoid Testing Update S. Virostek and M. Zisman Lawrence Berkeley National Laboratory MICO Meeting—RAL June 7, 2010.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Spectrometer Solenoid Update Steve Gourlay Steve Virostek Lawrence Berkeley National Lab Steve Gourlay Steve Virostek Lawrence Berkeley National Lab MICE.
Spectrometer Solenoids and Coupling Coils Primary Activities and Risks Going Forward Spectrometer Solenoids Completion of SS#2 magnetic mapping Completion,
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab Roy Preece Rutherford Appleton Lab October 28, 2011 MICE Collaboration Meeting.
MICE - UK Project Progress Roy Preece 30 th April 2013.
Office of Science 3/8/ LBNL MICE Project Status Spectrometer Solenoids, Coupling Coils and RFCC Modules Steve Gourlay MICE Project Board March.
Status and Integration of the Spectrometer Solenoid Magnets Steve Virostek Lawrence Berkeley National Lab MICE RAL June 15, 2007.
Magnet quench during a training run Successfully trained to peak currents and operationally tested Thermal performance requirements met 3D magnetic bore.
Spectrometer Solenoid Test Plan Workshop: Spectrometer Solenoid Overview Steve Virostek - LBNL February 17, 2012.
Instrumentation and Controls Test Plan Review 17 th February 2012 Roy Preece (STFC RAL)
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
MICE CC Test Status Ruben Carcagno 11/06/13 1. Cooldown Coil Temperature (calculated average in each of 8 coil segments) SC Transition (voltages across.
Spectrometer Solenoids MICO 214 Steve Virostek LBNL February 6, 2013.
MICE VC Alain Blondel 1 MICE NEWS MICE VC Next Collaboration meeting will be Jun at IIT and the 19th at Fermilab right before the.
Spectrometer Solenoids MICO 197 Steve Virostek LBNL August 15, 2012.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
Spectrometer Solenoid Overview Roy Preece 31 st January 2011.
Compressor status AWAKE Technical Board meeting 19 August 2015.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM25 at RAL November 6, 2009.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab MICE Collaboration Meeting #28 Sofia, Bulgaria.
Spectrometer Solenoid – Quench Analysis The LBNL version of the quench model has been further refined - Heng Pan is finishing various quench scenarios.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
MPB 31 October 2012 and FAC 15 November monitor how well we are doing in assembling step IV ! -- should deliver a ‘realsitic schedule scenario’
2011 Calendar Important Dates/Events/Homework. SunSatFriThursWedTuesMon January
Spectrometer Solenoid Fabrication Status and Schedule RF Cavity / Coupling Coil Module Plan and Progress Steve Virostek Lawrence Berkeley National Lab.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab NFMCC at LBNL January 25, 2009.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
22 October 2005MICE Meeting at RAL1 Tracker Solenoid Overview Michael A. Green Lawrence Berkeley Laboratory MICE Collaboration Meeting 22 October 2005.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
MICE Prototype Coupling Coil Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM38 - Napa California February 25, 2014 February.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab MICE Video Conference 120 May 7, 2009.
Spectrometer Solenoid Design and Test Results Steve Virostek Lawrence Berkeley National Lab Spectrometer Solenoid Review November 18, 2009.
Spectrometer Solenoid Background Info Steve Virostek Lawrence Berkeley National Lab MICE Spectrometer Solenoid Review: Phone Meeting October 5, 2009.
Spectrometer Solenoids MICO 194 Steve Virostek LBNL July 25, 2012.
MICE – UK Plan Roy Preece STFC RAL DOE Review of MAP Brookhaven National Laboratory 13 th August 2014.
MICE Coupling Coil Update Allan DeMello Lawrence Berkeley National Laboratory Illinois Institute of Technology June 17, 2013 June 17, 2013.
MICE Spectrometer Solenoid Recovery Review - December 3-4, Steve Virostek MICE Spectrometer Solenoid Design and Assembly.
MICE CC Magnet Cryostat Design Overview Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory MICE CC Cryostat Design Review LBNL, February.
MICE Coupling Coil Fabrication Steps to Complete Allan DeMello Lawrence Berkeley National Laboratory Coupling Coil Working Group January 28, 2014 January.
MICE Coupling Coil Vacuum Vessel Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory Coupling Coil Working Group January 28, 2014 January.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
Radiation Shutter Re-Purposing Roy Preece STFC RAL 18 th December 2014.
Spectrometer Solenoid Update
Spectrometer Solenoid Fabrication Status and Schedule
SC1R Cold Box PDR Assembly Sequence
2015 January February March April May June July August September
Presentation transcript:

Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)

Sections –Construction Cold Mass – Reworking for the additional cryo coolers, resistor conduction, fill / vent tubes. Cooler Towers – Reworking for the additional cryo coolers, flanges and access ports. Instrumentation – New sensors, harness and feedthroughs. External cabling and hardware. MLI – Focus on each part to be insulated. –Assembly Sequential process for assembly with control points for quality checking. –Testing Cool down, instrumentation, magnetic training and mapping. –Shipping / Integration Method of packing and shipping to RAL.

Construction Conservative estimates for timescales –Estimate from previous experience of the construction –Slack included in the estimate. Risk –Quality checks – MLI, instrumentation...etc –Periodic review – MICO, Collaboration Meetings, MAP PMG, in house meetings –Documentation / Drawings / Models / Pictures Parallel work –Personnel and work space an issue. –Instrumentation, MLI, documentation, models and drawings. –Vacuum Vessel and Radiation shield

Assembly / Test Sequence of assembly –Utilising the crane structure and support beam. –Working space. –Only one magnet at a time. Cool down and Test –Initial cooldown – semi automated LN2 cooling –He fill –Run the cryo coolers and stabilise – Allow for 2 weeks –Limit to 1 quench / day and then stabilise again –Continue until stable running of coils and cryo coolers – at least 24h continuous running –Characterise under various operation modes Magnet mapping –Can be carried out when stable operations can be replicated.

Shipping / Integration –Pack into standard / open topped / High ball shipping container, 20’ or 40’. –Lift in and out from top – Advantage of open topped container –Truck overland to New York / Ship to Folkestone 1 week truck 4 weeks shipping (including truck Folkstone – RAL ~ 1 day) –Ship without the stand welded to the vacuum vessel Reduces height Possibly eases integration issues – weld into position at RAL –Discussions with RAL team.

Milestones Major milestones taken from current schedule –Upstream Spectrometer Solenoid Cold Mass ready for assembly – 7 th July Upstream and Downstream Radiation Shields ready for installation – 22 nd July Assembly starts – 25 th July Cold Mass Aligned to Vacuum Vessel – 22 nd August Vacuum Vessel closed – 12 th October Ready for pump down, cooling and training – 27 th October Ready for Magnetic measurements – 25 th January Ready to Ship – 22 nd February Arrival at RAL – 26 th March –Downstream Spectrometer Solenoid Cold Mass lifted onto beam – 19 th August Assembly starts – 10 th October Cold Mass Aligned to Vacuum Vessel – 29 th November Vacuum Vessel closed – 21 st December Ready for pump down, cooling and training – 2 nd February Ready for Magnetic measurements – 24 h April Ready to Ship – 25 th May Arrival at RAL – 3 rd July