Thurel Yves – CERN / Chamonix 2010

Slides:



Advertisements
Similar presentations
Chamonix 2010: January 27 th Session 6 – Radiation To Electronics: R2E Summary Radiation 2 Electronics Session th January 2010 Radiations to Electronics.
Advertisements

K. Potter RADWG & RADMON Workshop 1 Dec WELCOME TO THE 4th RADWG & RADMON WORKSHOP 1 December 2004.
LHC UPS Systems and Configurations: Changes during the LS1 V. Chareyre / EN-EL LHC Beam Operation Committee 11 February 2014 EDMS No /02/2014.
CLIC Workshop 2009 Power Converters implications for CLIC machine protection 25/05/2015TE-EPC / S. Pittet1.
Vegard Joa Moseng BI - BL Student meeting Reliability analysis summary for the BLEDP.
Consolidation program SPS Main Power Converters (Dipole & Quadrupole) K. Kahle / Q. King / G. Le Godec (TE-EPC) IEFC Workshop, 9 March 2012.
Crab Cavities in IR1 and IR5 Some considerations on tunnel integration What will be the situation in the tunnel after the LHC IR Phase-1 Upgrade. What.
TS-LEA, CERN, 1211 Geneva 23 1 T. Wijnands TS/LEA, C. Pignard AB-CORADWG-RADMON day – 1 December 2004 LHC Power Converters & Radiation T. Wijnands TS/LEA.
COMPONENT TEST H4IRRAD 15 TH NOVEMBER 2011 G. Spiezia, P. Peronnard, G. Foucard, S. Danzeca, P. Gander, E. Fadakis (EN/STI/ECE)
J. MEKKI (1/14) 05/12/12 – RadWG meeting Summary of the radiation levels of the equipments at CNRAD RF MosFETs Cryogenics TE/EPC LED warning system BPM.
LHC Beam Screen Heaters: System overview, consolidation needs and project planning 4 February TE-CRG/JCC (Beam Screen Heater Review) 1.
Powering the main linac implications Daniel Siemaszko, Serge Pittet OUTLINE : Cost impact of power converters, power consumption and powering.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
LHC ARC Commissioning report during LS1 Agenda: VRGPE documentation (former VRJGE) Active Penning modification By-Pass Valves modification LHC ARC commissioning.
Drive beam magnets powering strategy Serge Pittet, Daniel Siemaszko CERN, Electronic Power Converter Group (TE-EPC) OUTLINE : Suggestion of.
Accelerator Consolidation Workshop TE/EPC consolidation plan 2 Jean-Paul Burnet ACC consolidation day, 12/09/2013.
LHC Power Converters And their SEE design
Chamonix Risks due to UPS malfunctioning Impact on the Superconducting Circuit Protection System Hugues Thiesen Acknowledgments:K. Dahlerup-Petersen,
R2E Report M. Brugger for the R2E Study Group RadWG Meeting, August 20 th 2009.
1 LHC Project Seminar - 06/05/99Raymond RAUSCH - SLRAD-WG Radiation Tests on Electronics for the LHC Machine u Presentation - Objectives of the Radiation.
Y. ThurelCERN / November / xxY. Thurel AB/PO Equipment irradiation test in CNGS Phase 1: [ … : Crash Event ] Phase 2 : [ :
Issues in Accelerator Control Bob Dalesio, December 23, 2002.
ICALEPCS 2005 Advanced uses of the WorldFIP fieldbus for diverse communications applications within the LHC power converter* control system Quentin King.
Electronic Systems Support Power Supply Joint Activity Chris Parkman EP Electronic Systems Support (EP-ESS) February 26, 2003.
Nov 28, 2013 Power Converters Availability for post-LS1 LHC TE-EPC-CCE.
CLIC/CLEX controls Radiation issue August 29 th, 2012 F.Locci - BE/CO-FE.
LHC Collimators low level control rack test experience in CNGS A Masi, LHC Collimators low level control rack test experience in CNGS LHC Collimators low.
R2E Mitigation Project P5 Relocation Options - Discussion R2E Mitigation Project CMS Relocation Options Towards An R2E Baseline 1 M. Brugger for the R2E.
Simulation results for powering serial connected magnets Daniel Siemaszko, Serge Pittet OUTLINE : Serial configuration of full rated converters.
K. Foraz & Perrot A. L., EN/MEF - R2E Project LMC 25th May 2011 Thanks to EN/EL, EN/HE, EN/MEF, equipment owners the LHC integration team & the R2E team.
FPGAs in ATLAS Front-End Electronics Henrik Åkerstedt, Steffen Muschter and Christian Bohm Stockholm University.
Power Converters and DC cablesSlide 1/.. LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005 Water cooled cables warm bus bars power converter.
LMC Update - R2E Failures December 5 th 2012 (R2E) Mitigation Project: LMC Update December 5 th 2012 R2E SEE Update M. Brugger on behalf.
Numerical signal processing for LVDT reading based on rad tol components Salvatore Danzeca Ph.D. STUDENT (CERN EN/STI/ECE ) Students’ coffee meeting 1/3/2012.
R2E Availability October 15 th 2014 Experience from Past LHC and Injector Operation and scaling to the future G. Spiezia.
Quench Detection System R. Denz TE-MPE-EP on behalf of the QPS team.
Ideas for Super LHC tracking upgrades 3/11/04 Marc Weber We have been thinking and meeting to discuss SLHC tracking R&D for a while… Agenda  Introduction:
R2E Availability October 17 th 2014 ADC and Common development options G. Spiezia.
R2E Mitigation Project Status Report 2 nd R2E Committee Meeting R2E Project Report.
Machine Protection Review, R. Denz, 11-APR Introduction to Magnet Powering and Protection R. Denz, AT-MEL-PM.
Mixed field irradiation -- Who answered ?  In total 36 forms filled / 34 persons answered: 38% 62% CERN: mainly LHC related topics CERF: beside LHC topics.
1 Radiation worries in the cavern L.Jirdén
FHCT SEB cross-section measurements at H4IRRAD and consequences for MKD reliability Viliam Senaj LIBD meeting 24/01/2012.
Geoff HallLECC LHC detector upgrades Introductory comments on electronic issues Organisation of this short session.
R2E Mitigation Project Review November 21 st – 24 th 2011 Intense program (link)link A few facts/highlights per session/task Calculations & Monitoring.
LHC Electronics irradiation tests in the CNGS side gallery September 2009 – partial results D.Kramer for the RADWG 30/9/09report to LMC Thanks to B.Todd,
TWEPP Paris, 09 Radiation Tests on the complete system of the instrumentation electronics for the LHC Cryogenics at the CNGS test facility Evangelia Gousiou.
Powering the damping rings wigglers Daniel Siemaszko, Serge Pittet OUTLINE : Powering superconductive magnets, Powering wigglers strategy, Existing.
TE-MPE-CP, RD, 28-Sep Problems with QPS DAQ Systems During LHC Operation, 1 st Results from 2010 CNRAD Tests R. Denz TE-MPE-CP.
Two half-day seminars on the remaining work packages to complete the MEDICIS Facility POWER CONVERTERS FOR MEDICIS Davide Aguglia & Julien Parra-Lopez.
CERN Converter Control Electronics Strategy for LHC Machine Electronics : Limitations & Risks
R2E/Availability Workshop Report - RadWG October 22 nd 2014 R2E/Availability Workshop 2014 October th 2014 R2E/Availability Workshop RadWG - Brief.
13 th September 2012 – 0v6 Radiation Tolerant Power Converter Controls thanks to: TE/EPC/CC, Y. Thurel, A. Masi, M. Brugger, G. Spiezia.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Planning and strategy for HL-LHC R2E
CONS and HL-LHC day Analysis of needs from TE-EPC
Irradiation test of Commercial (BASLER) digital cameras
Radiation monitoring and follow up during LHC commissioning
Outline Introduction to LHC Power Converters Remaining Inventory Observed Availability New inventory – FGClite Cumulative & SEE Effects Maintenance.
LIU – EVM status and next steps
RADMON Salvatore Danzeca (EN/STI) on behalf of the R2E Project and RADMON team Thanks to all the RADMON Team!
D.Kramer on behalf of the RADWG
Burst Test Test-Bed LHC120A-10V 4 Quadrant Converter: Burst Tests
Accelerator and Experiment Interface Session: LS2, LS3
PSU-Lab: A valuable expertise shared and open to CERN users
Programmable Logic Controllers (PLCs) An Overview.
Collimator Control (SEUs & R2E Outlook)
RADIATION induced failures in LHC 28th June 2011
Knowing When to Stop: An Examination of Methods to Minimize the False Negative Risk of Automated Abort Triggers RAM XI Training Summit October 2018 Patrick.
R. Losito – LHC Performance Workshop Chamonix Jan 2010
Presentation transcript:

Thurel Yves – CERN / Chamonix 2010 LHC Power Converters, the proposed approach CERN - Chamonix 2010 Yves Thurel with help from Quentin King, Valérie Montabonnet, Jean-Paul Burnet, Markus Brugger, Daniel Kramer 27/10/2010 Thurel Yves – CERN / Chamonix 2010

Thurel Yves – CERN / Chamonix 2010 Contents Power converter overview Radiation Tests results Projections TO THE LHC MACHINE Conclusion 27/10/2010 Thurel Yves – CERN / Chamonix 2010

1. POWER CONVERTER OVERVIEW 27/10/2010 Thurel Yves – CERN / Chamonix 2010

Converter Architecture Converter design: Functions All highly sensitive devices are concentrated in FGC thanks to CERN choices Vout Iout Load Power Part (Voltage Source) FGC & PSU (Digital Electronic) digital .... analog Vref Sensors electronic I.A I.B A B AC Mains Supply Control WorldFip - I ref - Design not using highly radiation critical components (in LHC case) Design using known sensitive components (RAM, CPU, DSP...) 27/10/2010 Thurel Yves – CERN / Chamonix 2010

What is a Power COnverter Converter design: Hardware Control Part Sensitive devices Small size Radiation Test is relatively easy Electronic Chassis PSUs Digital Cards: FGC Sensor Part (DCCTs) Rad non-sensitive analog electronic Rad. Safe by design DCCT 60A & 120A DCCT 600A DCCT 4..8kA Power Part Lot of components Medium to XXL size Radiation test is only feasible for low power (<120A) LHC4..8kA-08V LHC60A-08V 27/10/2010 Thurel Yves – CERN / Chamonix 2010

Converters Manufactured LHC converters vs radiation [2000-2001] Rad Tolerant Design or standard Design with low Rad sensitivity (safe components) Standard Design and Rad sensitivity unknown (too many components, sub-assemblies...) 2 DCCTs PSU FGC LHC120A-10V 298 2 DCCTs PSU FGC LHC600A-10V 400 2 DCCTs PSU FGC LHC600A-40V 37 2 DCCTs PSU FGC LHC4..8kA-08V 188 2 DCCTs PSU FGC LHC13kA-18V 16 2 DCCTs PSU FGC LHC13kA-180V 8 FGC LHC60A-08V 2 DCCTs 752 Tunnel Under Dipole Radiation Risk 27/10/2010 Thurel Yves – CERN / Chamonix 2010

Thurel Yves – CERN / Chamonix 2010 Converters Installed LHC converters vs radiation [2010] Rad Tolerant Design or standard Design with low Rad sensitivity (safe components) Standard Design and Rad sensitivity unknown (too many components, sub-assemblies...) 2 DCCTs PSU FGC LHC120A-10V 191 (298) 2 DCCTs PSU FGC LHC120A-10V 107 RR1x: 36 RR5x: 36 RR7x: 20 UJ1x: 10 UJ56: 05 2 DCCTs PSU FGC LHC600A-10V 272 (400) 2 DCCTs PSU FGC LHC600A-10V 128 RR1x: 28 RR5x: 28 RR7x: 48 UJ1x: 16 UJ56: 08 2 DCCTs PSU FGC LHC600A-40V 25 (37) 2 DCCTs PSU FGC LHC600A-40V 012 UJ76: 12 2 DCCTs PSU FGC LHC4..8kA-08V 122 (188) 2 DCCTs PSU FGC LHC4..8kA-08V 066 RR1x: 30 RR5x: 30 UJ1x: 04 UJ56: 02 Tunnel Under Dipole 2 DCCTs PSU FGC LHC13kA-18V 16 2 DCCTs PSU FGC LHC13kA-180V 8 FGC LHC60A-08V 2 DCCTs 752 Radiation Risk 27/10/2010 Thurel Yves – CERN / Chamonix 2010

2. Te-EPC Radiation tests TE-EPC Rad-Team Sylvie Dubettier Vincent Barbet Laurent Ceccone Philippe Semanaz Pierre Martinod Quentin King Yves Thurel CERN Rad-Team Thijs Wijnands Christian Pignard Real Manpower Effort & A lot of hours testing… 27/10/2010 Thurel Yves – CERN / Chamonix 2010

LHC-Environnement System Test Rack containing TE-EPC equipment Radiation Tests radiation susceptibility TESTS done on: LOUVAIN (2003 - FGCs) 60 MeV components tests LHC60A-08V FGC PSUs PROSPERO (2009 - FGCs) 1MeV validation tests CNGS (2008..2009 – FGCs, 60A, PSU) LHC-Environnement System Test TSG45 particules Rack containing TE-EPC equipment 27/10/2010 Thurel Yves – CERN / Chamonix 2010

Thurel Yves – CERN / Chamonix 2010 FGC / FGC PSU Results What did we learn on FGC & PSU THE GOOD FGC Rad-tolerant hardware design from beginning is OK FGC Very well tested: CNGS, Prospero, TCC2, Louvain PSU are not SEE sensitive and their T.I.D limit = 40 Gy THE BAD Xilinx CPLD used 11x in one FGC was chosen after good results in Louvain 2003 BUT CNGS showed that higher energy particles can lead to recoverable latch-ups (converter stops) and once a definitive burn-out. THE UNKNOWN One Xilinx CPLD died during CNGS tests, where up to 60 CPLD were tested in total. Was it isolated case? FGC Controller susceptibility T.I.D. Limit 60Gy (40Gy for PSU) which is > 20 years in 95% case S.E.E cross section FGC cross section = 2.10-11 cm² E>20MeV 27/10/2010 Thurel Yves – CERN / Chamonix 2010

Thurel Yves – CERN / Chamonix 2010 FGC Radiation Design Overview of FGC mitigation techniques used Main Processor: HC16 internal RAM not used DSP Co-Processor C32 Memories SEE Optimized Adequate Technology EDAC Corrections Power Cycle WordFip Magic (long) packet to remotely power cycle FGC Reset Automatic Reset operation-transparent in case corruption detected is possible (not yet implemented) 27/10/2010 Thurel Yves – CERN / Chamonix 2010

Power Converter: LHC60A-08V What did we learn on LHC60A-08V THE GOOD Rad-tolerant hardware design from beginning is OK Power Part is not sensitive to SEE SEE is then given by FGC, when T.I.D is given by power part. (50Gy) Operation can lose some 60A converters without losing beam Power Converter (FGC + Power Part) susceptibility T.I.D. Limit 50Gy (25 years min for LHC) S.E.E cross section given by FGC = 1 recoverable failure every 3-5 days Comments 0.3Gy/year, with 1 exception: 2-3 Gy/year 5.10E9/cm²/an E>20MeV 27/10/2010 Thurel Yves – CERN / Chamonix 2010

Thurel Yves – CERN / Chamonix 2010 3. LHC Projections Hadron fluence (E >20 MeV) [cm-2] 107 108 109 1010 106 105 104 103 Sea level [1 year] Airplane [1 year] Tunnel + RR1x,5x [1 year] UJ14-6, UJ56 [1 year] RR73 RR77 27/10/2010 Thurel Yves – CERN / Chamonix 2010

Thurel Yves – CERN / Chamonix 2010 LHC OVERVIEW EPC Equipments in LHC Points Considered Safe All UAs & UJs not listed below (is it correct?) Tunnel LHC60A-08V (752) Point 7 – UJ76 LHC600A-40V (12)  relocation Critical 301 converters Point 1 & Point 5 LHC120A-10V (87) LHC600A-10V (80) LHC4..8kA-08V (66) Point 7 LHC120A-10V (20) LHC600A-10V (48) UJ14, UJ16, UJ56 .……....... 5.109 /[cm².year] 045 power converters Tunnel under dipole: …...... 5.109 /[cm².year] 752 RR13, RR17, RR53, RR57 .. 1.109 /[cm².year] 188 RR73, RR77 ………………... 1.108 /[cm².year] 68 27/10/2010 Thurel Yves – CERN / Chamonix 2010

Thurel Yves – CERN / Chamonix 2010 Controller / FGC Simplified & limited approach for hot points (1,5,7) The scope: FGC SEE focus ONLY, T.I.D only critical in UJ56 Only data on FGC available (Power Part unknown) All converters point 1, 5, 7 are considered as critical Simplified approach using approximate levels without shielding point 1 + 5: Fluence: 1..5x10E9 /cm² / year E>20MeV point 7(RR): Fluence: 2.10E8 /cm² / year E>20MeV The result of this approach based only on FGC reliability gives Point 1+5: 1 FGC  1 Power Converter failure every ~ 20 days RR73+ RR77: 1 FGC  1 Power Converter failure every > 03 years Comments on the results on FGC reliability FGC does the job. Figures are minimum failure rate since power part can / will also fail All location with T.I.D higher than 2-3 Gy / year are not compatible with our equipment (FGC + PSU) lifetime (40-50 Gy = 2 Gy x 25 years) 27/10/2010 Thurel Yves – CERN / Chamonix 2010

Thurel Yves – CERN / Chamonix 2010 Power Part Overview Power Part converters (Voltage source without controller) THE GOOD AC CERN Network is a severe environment (Over Voltage rating applied) All very sensitive devices are concentrated in FGC electronics (by Design) Power Part is mainly based on classical analog devices THE BAD LHC600A-10V, LHC4..8kA-08V external design. (re-design reaction time : years) Converter power part is hard / impossible to test under radiation (big volume, high number of components, water cooled...) [5V CPLDs] are used in LHC600A, LHC4..8kA-08V LHC120A & DIM card used for diagnostic are based on FGC Xilinx CPLD (NO remote power cycle feature integrated in 120A converter or DIM card) THE UNKNOWN A lot of DC-DCs are used in all converters Some integrated devices are used (IGBT drivers, AC-DC power supplies, CPLD...) 27/10/2010 Thurel Yves – CERN / Chamonix 2010

Thurel Yves – CERN / Chamonix 2010 Power Part EXAMPLE Power Part converters (Voltage source without controller) How does a Power Part look like and how complex it is? Up to 4 000 components Up to 700 different components Mainly analog components Sensors, Optocoupers, Transistors IGBTs, MOSFET, Bipolars AC-DC PSU DC-DCs 27/10/2010 Thurel Yves – CERN / Chamonix 2010

Thurel Yves – CERN / Chamonix 2010 Power Part: LHC120A-10V LHC120A-10V power Part (voltage source) CERN Internal Design Design was initially -2002- thought to be rad-tol “compliant” in case of... Critical interlock (current leads & earth) identified as UNSAFE under radiation, since using same FGC sensitive Xilinx CPLD This CPLD then can represent a real safety hole Te-EPC Possible future actions Rad Test of power unit really needed?  Why not to use LHC as a test facility since we can react quickly if...? Partial redesigned relatively easily (CERN Design), and rather quick.  CPLD Based card will be surely re-designed or modified (to be planned) Is non-proactive plan acceptable?  Would certainly liberate EPC Manpower  Would only cost some months of non-optimum LHC operation mode on low current converters... 27/10/2010 Thurel Yves – CERN / Chamonix 2010

Thurel Yves – CERN / Chamonix 2010 Power Part: LHC600A-10V LHC600A-10V power Part (voltage source) External Design EEI – CIRTEM [5V CPLD] same type used 5x – no rad. Info A lot of DC-DCs are used No CPU, No RAM, No DSP, No FPGA Te-EPC Possible future actions Testing power unit is almost impossible (water cooled converter, too complex design, external design...) A rad-tol power converter redesign coupled with Inner Triplet Upgrade [+/-3000A +/-10V]  6x [+/-600A +/-10V] in parallel in a N+1 converter 3-4 years to get COTS rad-tol converters Unit Cost estimation: 30kCHF (LHC converter : 25 kCHF)  LHC Rad-Upgrade : 4.2 MCHF (140 Units) 27/10/2010 Thurel Yves – CERN / Chamonix 2010

Thurel Yves – CERN / Chamonix 2010 Power Part: LHC4..8kA-08V LHC4..8kA-08V Power Part (Voltage source) External Design Kempower [5V CPLD] same type used 7..10 times – no rad. Info High precision version (Inner triplet) uses Xilinx CPLD based 22 bit sigma delta ADC unit Not a single DCDC being Used No CPU, No RAM, No DSP, No FPGA Te-EPC Possible future actions Testing power unit is impossible (water cooled converter, too big size, too complex design, external design...) Is a redesign realistic: Manpower, cost? Non Rad-tol Standard Unit price: 75 kCHF  LHC Rad-Upgrade > 5 MCHF (70 Units) Complete analysis and partial re-design of potentially unsafe cards can be a possible preventive solution, less costly.  Will require time and/or manpower.  Budget known after 1st analysis only 27/10/2010 Thurel Yves – CERN / Chamonix 2010

Thurel Yves – CERN / Chamonix 2010 4. Conclusions 27/10/2010 Thurel Yves – CERN / Chamonix 2010

Thurel Yves – CERN / Chamonix 2010 Conclusions (1/2) Conclusions LHC60A-08V: SAFE & under control LHC120A-10V: UNSAFE but limited action can/will correct CERN design - Question is: Is sleeping mode acceptable? LHC600A-10V: UNKNOWN and potentially CRITICAL - Complete redesign: possible  Inner Triplet Upgrade - Possible relocation has to deal with cables voltage drop: 600A-40V can replace a 120A/600A-10V but is costly. (LHC600A-40V = 80kCHF/Unit: replacing all 68 RR7xconverters being relocated with an existing LHC600A-40V = 5.4 MCHF) LHC600A-40V: SAFE by relocation (action already launched) LHC4..8kA-08V: UNKNOWN and potentially CRITICAL - Surely the most critical item (LHC need it 100%) - Redesign is far from EPC Manpower & Plans - Action Possible: Card analysis  card redesign & test - Relocation OK if cryo line added (Cable Voltage drop) - Inner Triplet Upgrade does not solve RR1&5 situation 27/10/2010 Thurel Yves – CERN / Chamonix 2010

Thurel Yves – CERN / Chamonix 2010 Conclusions (2/2) Conclusions EPC Position: We could “survive” 3-4 years, waiting for a civil engineering work upgrade if chosen Inner Triplet upgrade project can be used for a double goal (600A-10V redesign) Some locations have to be absolutely lowered in terms of radiation UJ56 is announced at 5 Gy/year, which means majority of our equipments are dead after only 8-10 years. Biggest fear is that troubles arrive in some years only (high luminosity) and could make LHC not useable for years!!! (crash program = long reaction time). EPC Recommendations: Our actual power converters should not be placed in areas more than 2-3 Gy/year In case converter redesign options are chosen, reaction time is around 4 years Relocation options must accommodate cost increase if voltage drop exceeds rating of existing power converters. A CERN or Department level service for Rad-Tests of component would improve the efficiency of choosing rad-tol components. 27/10/2010 Thurel Yves – CERN / Chamonix 2010