ADT re-commissioning after LS1 A. Butterworth, W. Höfle, F. Killing, G. Kotzian, T. Levens, D. Valuch with many thanks to BE/OP LBOC, 15.7.2014 ADT re-commissioning.

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
LHC progress Thursday 30 th April 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Friday, h10: Stable beams at 1.38 TeV. 09h03: Beam dump.  One bunch dropped too much in intensity and gave BPMS interlock (dump protection). 10h36:
“What you get” Transverse damper system (ADT) F. Dubouchet W. Höfle G. Kotzian D. Valuch Special thanks to: A. Boucherie, A. Butterworth, S. Calvo, G.
Commissioning requirements for Trajectory, Orbit and Tune measurements T. Lefevre on the behalf of the BI teams involved LBOC 9 September 2014.
W. LHC Studies WG Day Review MDs Transverse Damper from Run1 to Run2 reported by W. Hofle for ADT & friends LHC MSWG Special Meeting.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
LHC transverse feedback W. Höfle, G. Kotzian, T. Levens, D. Valuch 1 Special thanks to: A. Boucherie, A. Butterworth, J.C. Guillaume, D. Jacquet, M. Jaussi,
Design and operation of existing ZS B.Balhan, J.Borburgh, B.Pinget B.BalhanDesign and operation of existing ZS SPS ZS Electrostatic Septum Upgrade Review.
BI day 2011 T Bogey CERN BE/BI. Overview to the TTpos system Proposed technical solution Performance of the system Lab test Beam test Planning for 2012.
Beam expected in the afternoon PM: – Establish first-turn – Establish closed orbit – Rough correction of machine parameters Evening: – RF capture Night:
RF strategy, limits and issues A. Butterworth L. Arnaudon, Ph. Baudrenghien, O. Brunner, E. Ciapala, W. Hofle, J. Molendijk, E. Shaposhnikova, J. Tuckmantel,
Measurement opportunities with the LHC transverse damper W. Hofle, D. Valuch.
BBQ system Tatiana and Benoit, thanks to a lot of help from Christian Boccard, Marek Gasior and Ralph Steinhagen (BE/BI-QP)
Friday to Saturday 02:00: Machine closed. 09:00: Cryogenics all OK. Preparing pre-cycle. 10:00: Pre-cycle started. 11:30: Pre-cycle finished. 14:00: Beam.
1 Beam Dumping System MPP review 12/06/2015 Jan Uythoven for the ABT team.
W. Hofle LIU-SPS Meeting SPS BA2 Damper LS1 Progress and plans reported by W. Hofle LIU-SPS Meeting G. Kotzian T. Levens D. Valuch.
High Bandwidth damper Input from W.Hölfe Acknowledgement to all collaborators at SLAC, INFN, LBNL and CERNL Presentation of recent MD results (J.Cesaratto):
Status from the collimator impedance MD in the LHC Collimation team:R. Assmann, R. Bruce, A. Rossi. Operation team:G.H. Hemelsoet, W. Venturini, V. Kain,
00:15: Stable beams fill 1883, 1.1E33 cm-2s-1.  Seems the 144 bunches beam 1 doe not fit properly on the injection kicker waveform. Systematically the.
ADT Tune Measurement F. Dubouchet, W. Hofle, D. Valuch Acknowledgement: R. Calaga, F. Roncarolo, E. Bravin, shift crews New developments and tests on August.
LHC RF re- commissioning for run 2 with planned operation at 6.5 TeV/c and 0.55 A DC current P. Baudrenghien BE-RF with contributions from J.E. Muller,
LHC machine status ~ Daily Summary ~ Daily beam commissioning meeting Week 42 - October 14 th, 2015 CERN, Geneva, CH M. Lamont and S. Redaelli for the.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
04:01 Injection kicker timing problems B2  Injection pre-pulse shifted, causing BETS to inhibit beam injection. 144 bunches on TDI.  Run without ROF.A81B2.
Bunch Numbering P. Baudrenghien AB/RF for the LHC/RF team.
Experience and Perspectives of Transverse Feedback Systems for Scrubbing Thanks to: SPS OP crew and colleagues from BE-ABP and BE-RF, for their support.
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
LS1 Mid-Point Status Report of the PSB Low Level RF, Transverse Feedback & High Level RF. Autumn 2013 A. Akroh, M.E. Angoletta, A. Blas, L. Arnaudon, A.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
Lumi scan limits checked (in preparation for next fill VdM scans).  Trims of up to 150 um per beam in IP1 & IP2 both planes both beams were done (IP5.
Thursday 20 th April 01:53 RCBV17.R7B2 tripped as happened few days ago: SIS intercepted. 05:54 Stable beams, 1380b, still RF problems B1, abort gap cleaning.
Controlled Transverse Blowup with ADT MD block #3 / th August 2011 presented by W. Hofle T. Levens, S. Redaelli, F. Roncarolo, R. Schmidt, D. Valuch.
ADT kickers and amplifiers in tunnel point 4 of LHC, RB44 and RB46 1 W. Hofle LHC Transverse Damper LARP CM20 Napa April 8-10, 2013 LHC Transverse Damper.
07:00 Dump fil #2219, 123 pb -1 delivered. Trim TDI parking position to +/- 55 mm in the collimator BP trimmed the temperature kicker limit to 62 degrees.
ADT Post-LS1 16 Dec 2015 Evian 2015 / ADT Post-LS1 – G. Kotzian G. Kotzian, W. Hofle, D. Valuch Special thanks to: L. Arnaudon, A. Boucherie, A. Butterworth,
Summary of ions measurements in 2015 and priorities for 2016 studies E. Shaposhnikova 3/02/2016 Based on input from H. Bartosik, T. Bohl, B. Goddard, V.
RF Commissioning D. Jacquet and M. Gruwé. November 8 th 2007D. Jacquet and M. Gruwé2 RF systems in a few words (I) A transverse dampers system ACCELERATING.
PSB HW Commissioning Meeting 8 February 2016 A. Akroh, B. Mikulec.
W. Hofle / March 5, 2008 Extended LTC meeting 1/22 Acknowledgements: P. Baudrenghien, A. Butterworth, E. Ciapala, B. Goddard, A. Koschik, F. Killing, G.
Readiness for RF capture Cavities – all 16 cavities commissioned with RF feedback loops closed klystron polar loop still to commission on 2 cavities 2.
PU Choices for ADT Plans for Run 2 ADT Team W. Hofle / G. Kotzian / D. Valuch PU Choices for ADT - Plan for Run 2 14 April LBOC 1.
RF acceleration and transverse damper systems
Jorge Sánchez-Quesada BE-RF-FB
Excitation by ADT and active bunch-by-bunch tune measurements
-9:00: Test IP transverse adjustment (CMS) and optics verification.
ADT and ObsBox in 2016 W. Hofle, M. Jaussi, G. Kotzian, S. Rains,
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Digitizers in CCR for transverse wide-band pick-ups
Monday 14th March Second fill with pilot + 3 nominal bunches
RF and Sequences Andy Butterworth BE/RF
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Thursday morning – optics correction
Status from the collimator impedance MD in the LHC
Scrubbing progress - 10/12/2012
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Summary Thursday h21: Stable beams fill #1303.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Friday 8/10/10 - Morning Planned to keep fill until the afternoon
Summary for LPC (March 7th, Ralph Assmann)
LHC - Week 38 Technical stop: Katy Foraz
Sat 18/3 - Ramp to 4 TeV Again glitch on the safe beam flag for beam 2. Cause identified: noise on BCT2B giving values above the safe beam limit (2.4×1010.
Friday 28 October 2011.
Summary Tuesday h23: Machine closed. Precycle started.
Wednesday 23/2 Thanks CRYO!!!.
Wednesday :35 : Beam lost because of trip of RCBXH3.L1
Daniel, Gianluca and Belen (for the Collimator team)
Presentation transcript:

ADT re-commissioning after LS1 A. Butterworth, W. Höfle, F. Killing, G. Kotzian, T. Levens, D. Valuch with many thanks to BE/OP LBOC, ADT re-commissioning after LS11

Motivation Requirements for commissioning time with beam and for the ramp- up in intensity (including scrubbing) (assume the requirements for the preparation without beam will be dealt by the cold check-out team) A list of the modifications/improvements occurred during LS1 if not presented yet and a break-down of the activities and preparation required for: operation with pilot bunches, operation with a single nominal bunch, operation with trains (low number), operation with trains (large number). The goal of each step should be identified and the minimum beam characteristics and time requirements should be indicated. ADT re-commissioning after LS1 LBOC,

ADT after LS1 (low level RF system) ADT undergoes a major upgrade during the LS1 2x number of pickups New Beam Position hardware/firmware/FESA/software New Digital Signal Processing hardware/firmware/FESA/software Many new properties/functionalities New FGCs (2x number of functions) New cabling (different delays and transfer functions) Number of significant changes is large  we consider it to be a new system Procedures well established, all experience from Run I. …and number of experts increased by 3.5dB for Run II! LBOC, ADT re-commissioning after LS13

ADT after LS1 (power system) Power amplifiers Maintenance (cleaning, divider calibration, re-commissioning in B.867) New relay plates New air cooling system New air cooling pipes New 200W loads Removal of pre-heating resistances New water flow meters in RB44 – RB46 New clamp between amplifiers and kickers New clamp between kickers striplines and feedthroughs Additional vacuum gauge in RB44 (3 gauges per beams and on each sides, 12 in all) Anode Power converters Cleaning Exchange all fans Adding new H.V. switches (command off/online remotely) LBOC, ADT re-commissioning after LS14

Cold check-out activities (phase 1) Check all pickup cables are correctly connected in the tunnel Pickup swap with BI HOM port VNA measurements for all kickers Once water and HV is available at P4 check all power amplifiers and measure the transfer function (via HOM ports) Once all systems are powered at P4, need to conduct a series of EMC measurements – new UPS seems to produce more noise than the previous one: Conducted UPS noise was a major problem in 2010 Ongoing activity (involving EN/EL, BE/RF, BE/BI, TE/EPC) LBOC, ADT re-commissioning after LS15

Cold check-out activities (phase 2) Check all FGCs, define new functions in the control system (TE/EPC, BE/RF, BE/OP) Installation ~ September-October Gains, phase shifts… Define new timings (BE/RF, BE/OP) Multiple independent DACs for different functions (main feedback loop, witness bunches, AGC/IGC…) Dry runs, once SR4 is back in operation (electricity, air conditioning). Expected September-October (BE/RF, BE/OP) LBOC, ADT re-commissioning after LS16

ADT re-commissioning with beam (phase 3) Basic LLRF setting up (phase 3.A): Could be done in a shadow of other activities. Local work in SR4 (access to the analogue signals) Beam Position module expert settings (sampling, bucket 1…) Digital Signal Processing module expert settings (pickup alignment, signal chain up to the driver amplifier) Beam: pilots circulating for sufficient length of time (>30 minutes) Time: few shifts in a shadow of other commissioning LBOC, ADT re-commissioning after LS17

ADT re-commissioning with beam (phase 3) Waiting for beam in SR4 during summer is not that terrible… LBOC, ADT re-commissioning after LS18

ADT re-commissioning with beam (phase 3) Operation with pilot bunches (phase 3.B) Beam Position module setting up: Dedicated setting up with orbit bumps (phase rotation, intensity related settings) Beam: single pilot circulating Time: provided our Matlab tools work with FESA 3 AND we can still access the FBCT and the BPM (orbit feedback) classes: ~4 hours per beam per plane Potential problem – some classes still FESA 2.10, new damper FESA 3? In case our Matlab tools do not work: ~2 days per beam per plane LBOC, ADT re-commissioning after LS19

ADT re-commissioning with beam (phase 3) Operation with pilot bunches (phase 3.C) Digital Signal Processing Unit setting up: Setting up of the “bunch 1” Setting up of a coarse 1-turn delay (prerequisite for any excitation or cleaning!!) Beam: single pilot circulating. Destructive test, need occasional refill Time: ~ 2 hours per beam per plane LBOC, ADT re-commissioning after LS110

ADT re-commissioning with beam (phase 3) Operation with pilot bunches (phase 3.D) Feedback loop setting up: Setting up of a fine 1-turn delay and phase shifts for each pickup Beam: at least 6, ideally 12 bunches circulating. Single bunches or a reasonably spaced train (not 25ns). Destructive test, need occasional refill Time: ~ 2 hours per beam per plane LBOC, ADT re-commissioning after LS111

ADT re-commissioning with beam (phase 3) White noise excitation for loss maps (phase 3.E): Prerequisite: Blow-up application updated to new HW/SW (BE/OP) Commissioning phase 3.c completed Beam: Something circulating, ideally in bucket 1. Destructive test, need occasional refill Time: ~ 2 hours per beam per plane If needed could be conducted just after 3.c LBOC, ADT re-commissioning after LS112

ADT re-commissioning with beam (phase 3) Operation with a single nominal bunches (phase 3.F) Beam Position module setting up: Dedicated setting up with orbit bumps (phase rotation, intensity related settings) Beam: single nominal bunch circulating Time: provided our Matlab tools work with FESA 3 and we can still access the FBCT and the BPM (orbit feedback) classes: ~4 hours per beam per plane Time: in case our Matlab tools do not work: ~2 days per beam per plane LBOC, ADT re-commissioning after LS113

ADT re-commissioning with beam (phase 3) Operation with trains, low number (phase 3.G): No special setting-up, check of the beam transfer function, eventually fine adjustment of the 1-turn delay Beam: train of nominal bunches circulating Time: ~1 hour per beam per plane LBOC, ADT re-commissioning after LS114

ADT re-commissioning with beam (phase 3) Operation with trains, large number (phase 3.H): No need for dedicated setting-up, only few checks in a shadow of other activities Beam: train of nominal bunches circulating Time: n/a LBOC, ADT re-commissioning after LS115

ADT re-commissioning with beam (phase 3) Operation with trains, 25ns bunch spacing (phase 3.I): Check of the beam transfer function, fine adjustment of the 1-turn delay Other checks/setting up (e.g. digital filters) Beam: train of nominal bunches circulating. Destructive test, need occasional refill Time: xx hours per beam per plane Operational observation system critical (Observation box vs. Expert buffers) LBOC, ADT re-commissioning after LS116

ADT re-commissioning with beam (phase 3) Operation with doublet beam (phase 3.J): Check of the analogue signals Setting up of the Beam Position Modules Other checks/setting up Beam: doublet beam in some form Time: xx hours per beam per plane Operational observation system critical LBOC, ADT re-commissioning after LS117

ADT re-commissioning with beam (phase 3) 3.J and 3.K is new territory, difficult to make a realistic estimate of the time required LBOC, ADT re-commissioning after LS118

ADT re-commissioning with beam (phase 3) Injection gap cleaning (phase 3.K): Prerequisite: Sequencers updated to new HW/SW (BE/OP) Commissioning phase 3.c completed Beam: Something circulating, ideally in bucket 1. Destructive test, need occasional refill Time: xx hours If needed could be conducted just after 3.c LBOC, ADT re-commissioning after LS119

ADT re-commissioning with beam (phase 3) Abort gap cleaning (phase 3.L): Prerequisite: Sequencers updated to new HW/SW (BE/OP) Prerequisite: AGC application ready and updated to new HW/SW (BE/OP) Commissioning phase 3.c completed Beam: Something circulating, ideally in bucket 1. Destructive test, need occasional refill Time: ~ 2 hours per beam per plane If needed could be conducted just after 3.c LBOC, ADT re-commissioning after LS120

Open questions Automatic intensity settings and protection (BE/OP+BE/RF) Current scheme with the SIS checking the circulating intensity in the SPS is already quite good Using this information and having a state machine programming the front-end gain settings is a logical extension Some ideas on the algorithm already there Where should it run, who is responsible tbd. Observation system (BE/RF/CS) Will The Observation Box be ready? Do we still need to use the expert buffers? All CCC applications need to be updated to the new source of data LBOC, ADT re-commissioning after LS121

Overall ADT re-commissioning time-line LBOC, ADT re-commissioning after LS122 Total: min. 72 hours (9 shifts, preferably not in a row)

Summary LBOC, ADT re-commissioning after LS123 Number of significant changes is large  we consider ADT to be a new system All procedures well established, lot of experience from the Run I

Summary LBOC, ADT re-commissioning after LS124 ADT is a very complex system, the re-commissioning will be quite demanding involving many people Provided enough coffee is available… …and enough food is served… …we should make it!

Thank you for your attention LBOC, ADT re-commissioning after LS125