Entry Capacity Substitution Workshop 2 7 th May 2008 Substitution Example.

Slides:



Advertisements
Similar presentations
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Advertisements

Long Term Entry Capacity & User Commitment Transmission Workstream 7 th August 2008.
Entry Capacity Substitution Transmission Workstream – 6 th August 2009.
The Treatment of “Spare / Sterilised” Capacity – follow up Draft for discussion purposes only.
Capacity trade and transfer mechanism and the next AMSEC auction Nienke Hendriks Head of Gas Transmission Policy, Enforcement and Compliance 9 May 2007.
Long Term Entry Capacity & User Commitment Review Group th September 2008.
GRI NW Investment Workshop Chris Logue, European Policy Manager, 4 th June 2010 The Hague.
Entry Capacity Substitution Workshop 5 – 5 th December 2008 Review and Options for Development.
Further consultation on NTS entry baselines Nienke Hendriks Head of Gas Transmission Policy, Compliance and Enforcement 14 August 2007.
The Entry Capacity Transfer & Trade Methodology Statement Transmission Workstream
Capacity Release Processes and Investment Planning Transmission Planning Code Workshop 2 1 st May 2008.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Entry Capacity Substitution Workshop 8 – 7 th April 2009.
Entry Capacity Substitution Workshop 7 – 10 th February 2009.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Entry Capacity Substitution Workshop 9 – 7 th July 2009 DRAFT PRESENTATION.
Transfers and Trades Transmission Workstream
Discretionary Release of Non Obligated NTS System Entry Capacity Transmission Workstream 1st May 2008.
Third Workstream meeting re Baseline Re-consultation and Substitution 12 September 2007.
1 Allocation of Baseline Reduction in the Substitution Methodology Draft Presentation aimed for 11 th June Substitution Workstream John Baldwin Gas Strategies.
Update on Entry Capacity Substitution Transmission Workstream 6 th March 2008 Summary of consultation responses.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Review Group 221: Option 3 – security provided after allocation.
Exit Capacity Substitution and Revision Transmission Workstream meeting, 3 rd December 2009.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Review of Entry Capacity and the Appropriate Allocation of Financial Risk Review Group th Sept 2008.
Capacity Methodology Statements Transmission Workstream 5 th July 2007.
Optimisation of Entry Capacity Strawman Transmission Workstream 4 th May 2006.
Entry Capacity Substitution Workshop 3 11 th June 2008 Substitution Example.
Implementation of Trades and Transfers National Grid NTS 5 th June 2008.
September 2008 QSEC auction - Allocations Transmission Workstream
Entry Capacity Substitution Workshop 6 – 7 th January 2009.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Entry Capacity Substitution Workshop 4 9 th July 2008 Entry Capacity Substitution Methodology Statement: Discussion Paper.
Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th March 2009.
Entry Capacity Substitution: Discussion Document Transmission Workstream 7 th August 2008 Initial Analysis of Responses.
Proposal to adjust investment lead times Transmission Workstream 4 th May 2006.
Trades and Transfers Workshop, 6 th November 2007.
Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009.
Initial Thoughts on Timeline for Entry Capacity Substitution Draft for discussion purposes only.
Transfers and Trades Special Transmission Workstream
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
The Entry Capacity Substitution Regime Transmission Workstream 7 th February 2008 Thoughts for discussion.
Interactions with the implementation of RIIO-T1
Exit Capacity Release Methodology Statement
Transmission Planning Code – Draft Document
Non-approved draft Transmission Workstream, 6th December 2007
Transmission Planning Code
Transmission Workstream, 2nd March 06
Capacity Methodology Statements: Impact of Mod 452
Action from Workshop 3 – SUB010
Capacity Methodology Statements
Exit Capacity Substitution and Revision
Background to National Grid’s Baseline analysis
Update on Exit Capacity Substitution and Revision
Development of Entry Capacity Substitution
Entry Capacity Substitution
Modification 501 slides for Workgroup
Long Term Non Firm Capacity Update
Review of Trade and Transfer Winter 09/10
Transmission Workstream – 6th July 2005
Richard Fairholme E.ON UK
Modification Proposal 0133 – “Introduction of AMTSEC auction”
Optimisation of Entry Capacity Modification Proposal
IECR Incremental Step Size
Review Group 221: Review of Questions from Session 2
Incremental Entry Capacity Release Methodology Statement
Modification 0043 – Limitation on offering for sale unsold capacity
Entry Capacity Transfers - Constrained Period
Presentation transcript:

Entry Capacity Substitution Workshop 2 7 th May 2008 Substitution Example

2 Introduction  2007 TPCR introduced an obligation on National Grid to introduce “Entry Capacity Substitution”.  At Entry Capacity Substitution workshop 1 National Grid agreed to consider providing a worked example to illustrate the impact of Entry Capacity Substitution.

3 Introduction  The example is illustrative only and should not be taken as guaranteeing specific outcomes when the substitution processes are implemented.  Example  Consider the scenario where incremental entry capacity is requested at Easington ASEP in a future QSEC auction.  Intended to show processes involved without referring to actual projects.  All values used are indicative whilst being a reasonable approximation to actual capacity levels.

4 Assumptions  How capacity substitution is ultimately developed will define the precise processes to be followed and may add a level of complexity.  Hence to illustrate the end-to-end process it is necessary to make a number of assumptions.  A single NPV test applies irrespective of how incremental capacity is made available.  Substitution applies from 42 months after the auction.  Capacity available for substitution as defined in Licence.  Existing capacity allocations and QSEC bids are consistent through the QSEC timeframe.

5 Overview of QSEC Auction with respect to Substitution InvitationAuction Allocation Analysis Available Capacity “Permits” P 0 to P 20 prices Signal Incremental (and obligated) capacity needs Quantity & date Identify substitution opportunities. Recipient / Donor Revised allocations IECR / ECS Capacity release rules Subsequent auctions Revised Obligated Level Available Capacity Prices Incremental Obligated Entry Capacity Proposal to Ofgem

6 Substitution Example - Invitation Assumptions National Grid can meet all expected incremental capacity requests in the 42 month default lead-time; i.e. no “permits” played. Donor ASEPs will be those with available capacity and greatest interactivity with the Recipient ASEP. For example, in respect of Easington, the Donor ASEPs could be those identified in the table below. No surrender facility. ASEPObligated level mscmd Baseline mscmd Unsold Easington Hornsea21161 Theddlethorpe56 49 Bacton “Unsold” capacity is 90% baseline minus the highest sold quantity for any quarter after month 42. For other quarters more capacity will be available for sale at the ASEP but not for substitution. All unsold capacity is available for Users at the relevant ASEP or, if remaining unsold, for substitution.

7 Substitution Example – Assumed Auction Bids Easington auction bids received for incremental entry capacity. Passes NPV test for quantity 10 mscmd from 42 months. AN Other ASEP auction bids received for incremental entry capacity. Passes NPV test for quantity 5 mscmd from 42 months. Not shown in table below. Potential Donor ASEPs: total bids received (plus existing allocations) are less than 90% baseline. ASEPQuantity bidQuantity of baseline sold Available for sub i.e. 90% baseline minus max sold level Easington10 incremental880 Hornsea Bids no higher than existing levels 141 Theddlethorpe249 Bacton5296

8 Capacity Substitution Process Previously Consulted Upon.

9 Substitution Example – Recipient ASEP Incremental capacity triggered for Easington and AN Other Revenue driver at Easington is lower than AN Other so consider this as Recipient ASEP for substitution first. Lower revenue driver implies that the ASEP will benefit most from substitution. Hence more likely to minimise need for investment. AN Other not considered further in this example.

10 Substitution Example – Analysis as per Illustrated Process Diagram Donor ASEP identified as nearest ASEP (by pipeline distance) with available capacity Hence ranking of Donor ASEPs in example is Hornsea Theddlethorpe Bacton Substitutions will be verified by network analysis. Substitutions will not be permitted where analysis shows failure to maintain pressure and other network commitments or increases risk of constraint management actions being required.

11 Substitution Example - Allocations Revised allocations (based on peak quarter) Users at Easington:10 mscmd incremental Users at Donor ASEPs:No change from pre-auction Revised obligated levels Easington: Previous obligated level plus 10 = 140 mscmd Donor ASEPs:As determined according to methodology Revised obligated levels apply from the first date of substitution, i.e. 42 months, and will be available in the next QSEC and relevant MSEC auctions in due course.

12 Substitution Example - Allocations Role of Ofgem (C8D 9 l) National Grid will submit to Ofgem its Incremental Obligated Entry Capacity Proposal Specifies quantity of incremental entry capacity and whether it should be treated as: non-incremental obligated entry capacity (i.e. substitution); or funded incremental obligated entry capacity. Ofgem have 7 days to suspend implementation If suspended, Ofgem have 28 days to: Veto; or direct to modify (subject to agreement with National Grid). Volume at the recipient ASEP to be treated as substituted capacity First month of substitution This could require analysis to be repeated and investment plans revised. Allocations to be made within 2 months auction closing (UNC B2.6.7).

13 Substitution Example Incremental Obligated Entry Capacity Proposal. National Grid will submit to Ofgem its Incremental Obligated Entry Capacity Proposal. In respect of Easington: Quantity of incremental entry capacity = 10 mscmd; of which X mscmd will be met from substitution; and Y mscmd will be funded. National Grid receives no additional revenue in respect of incremental capacity met by substitution.

14 Substitution Example – Prices Reserve Prices (and step prices for incremental entry capacity) are a function of the obligated capacity level Hence, substitution will generally decrease the P 0 price at Donor ASEPs; and Release of incremental capacity will generally increase the P 0 price at Recipient ASEPs Revised obligated levels / prices apply from the applicable quarter/month, i.e. from month 42.

15 Substitution Example – Prices (to be completed) ASEP Initial Prices p/kWh/day Change in obligated level mscmd New Prices p/kWh/day P0P0 P1P1 P5P5 P0P0 P1P1 P5P5 Easington Hornsea Subject to results of analysis Theddlethorpe Bacton

16 Potential Timeline for Development of Entry Capacity Substitution 7 th May 2008 Late July Deadline for comments Q3 Formal consultation on ECS (and IECR if required) Potential Timeline Industry comments to NG Late June Draft ECS for comment. 7 th May Workshop 2 11 th June Workshop 3 Ofgem approval / Impact Assessment 28 plus 14 days

17 Next Steps  Next workshops  11 th June  National Grid to walk through draft methodology for determining Entry Capacity Substitution quantities / locations.