Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

Slides:



Advertisements
Similar presentations
Chapter 17 Project Management McGraw-Hill/Irwin
Advertisements

Chapter 13 Project Scheduling: PERT/CPM
F O U R T H E D I T I O N Project Management © The McGraw-Hill Companies, Inc., 2003 supplement 3 DAVIS AQUILANO CHASE PowerPoint Presentation by Charlie.
1 1 Slide © 2001 South-Western College Publishing/Thomson Learning Anderson Sweeney Williams Anderson Sweeney Williams Slides Prepared by JOHN LOUCKS QUANTITATIVE.
Operations Management Session 27: Project Management.
1 Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept WBS: Lowest level OBS: Lowest level.
Project Scheduling: Gantt/Pert Charts
1 Topics to cover in 2 nd part ( to p2). 2 Chapter 8 - Project Management Chapter Topics ( to p3)
PROJECT MANAGEMENT. Outline What is a “project”? Project Management Objectives and tradeoffs Planning and Control in Projects Scheduling Methods Constant-Time.
Gantt Chart Graph or bar chart with a bar for each project activity that shows passage of time Provides visual display of project schedule Slack amount.
Project Scheduling Prof. Jiang Zhibin Dept. of IE, SJTU.
إدارة المشروعات Projects Management
1 1 Slide © 2000 South-Western College Publishing/ITP Slides Prepared by JOHN LOUCKS.
MGMT 483 Week 8 Scheduling.
Chapter 9 Project Management.
Operations and Supply Chain Management, 8th Edition
Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.
Importance of Project Schedules
Project Management An interrelated set of activities with definite starting and ending points, which results in a unique outcome for a specific allocation.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Project Management OPIM 310-Lecture.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 6 Project Management To Accompany.
© 2000 by Prentice-Hall Inc Russell/Taylor Oper Mgt 3/e Chapter 6 Project Management.
Roberta Russell & Bernard W. Taylor, III
Copyright 2009 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Where We Are Now. Where We Are Now Developing the Project Plan The Project Network A flow chart that graphically depicts the sequence, interdependencies,
Software Project Management Task Sequencing Activity Sequencing Concepts PERT charts Critical Path Analysis.
Time Management Week 7 - Learning Objectives You should be able to: n List and describe the processes, activities, inputs, and outputs in time management.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Developing a Project Plan Chapter 6.
MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. W6 6.2 Operation Management Operation Management Managing Projects Techniques.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Copyright 2006 John Wiley & Sons, Inc. Project Management OPIM 310.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
1 Project Management Chapter Lecture outline Project planning Project scheduling Project control CPM/PERT Project crashing and time-cost trade-off.
Project Management: A Managerial Approach
Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Copyright 2009 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 6 th Edition Chapter.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 17 Project Management Part.
Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 6 Project Management To Accompany.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Project Planning and Budgeting Recall the four stages Project Definition and Conceptualization Project Planning and Budgeting Project Execution and Control.
Irwin/McGraw-Hill  The McGraw-Hill Companies, Inc Project Scheduling IENG 321 IENG 321.
Chapter 7 – PERT, CPM and Critical Chain Operations Management by R. Dan Reid & Nada R. Sanders 4th Edition © Wiley 2010.
© 2006 John Wiley and Sons, Inc. Project Management: A Managerial Approach Chapter 8 – Scheduling.
(M) Chapter 12 MANGT 662 (A): Procurement, Logistics and Supply Chain Design Purchasing and Supply Chain Analysis (1/2)
Project Planning & Scheduling What is a “project”? Objectives and tradeoffs Planning and Control in Projects Scheduling Methods Constant-Time Networks.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Project Planning, Scheduling and Control Planning: –defines objectives, tasks and preceeding relationships; estimates time and resources Scheduling: –identifies.
Beni Asllani University of Tennessee at Chattanooga
Scheduling Scheduling : is the process of converting a project action plan into an operating time table. Why scheduling ? To answer the following questions:
Project Management Chapter 8.
Project Management: PERT/CPM
Project Planning & Scheduling
Project Scheduling
Project Management (PERT/CPM) PREPARED BY CH. AVINASH
Project Planning & Scheduling
Project Scheduling Chapter 14.
Projects: Critical Paths
Project Planning and Budgeting
Probabilistic Time Estimates
Project Scheduling: networks, duration estimation, and critical path
Stevenson 17 Project Management.
Slides Prepared by JOHN LOUCKS
Project Management CPM/PERT Professor Ahmadi.
Presentation transcript:

Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling

A Gantt Chart |||||||||| Activity Design house and obtain financing Lay foundation Order and receive materials Build house Select paint Select carpet Finish work MonthMonth

8-3 Standard Abbreviations CPM – Critical Path Method PERT - Program Evaluation and Review Technique

8-4 Background Schedule is the conversion of a project action plan into an operating timetable Basis for monitoring a project One of the major project management tools Work changes daily, so a detailed plan is essential Not all project activities need to be scheduled at the same level of detail

8-5 Background Continued Most of the scheduling is at the WBS level, not the work package level Only the most critical work packages may be shown on the schedule Most of the scheduling is based on network drawings

8-6 Network Scheduling Advantage Consistent framework Shows interdependences Shows when resources are needed Ensures proper communication Determines expected completion date Identifies critical activities

8-7 Network Scheduling Advantage Continued Shows which of the activities can be delayed Determines start dates Shows which task must be coordinated Shows which task can be run parallel Relieves some conflict Allows probabilistic estimates

8-8 Network Scheduling Techniques: PERT (ADM) and CPM (PDM) PERT was developed for the Polaris missile/submarine project in 1958 CPM developed by DuPont during the same time Initially, CPM and PERT were two different approaches – CPM used deterministic time estimates and allowed project crunching – PERT used probabilistic time estimates Microsoft Project (and others) have blended CPM and PERT into one approach

8-9 Terminology Activity - A specific task or set of tasks that are required by the project, use up resources, and take time to complete Event - The result of completing one or more activities Network - The combination of all activities and events that define a project – Drawn left-to-right – Connections represent predecessors

8-10 Terminology Continued Path - A series of connected activities Critical - An activity, event, or path which, if delayed, will delay the completion of the project Critical Path - The path through the project where, if any activity is delayed, the project is delayed – There is always a critical path – There can be more than one critical path

8-11 Terminology Continued Sequential Activities - One activity must be completed before the next one can begin Parallel Activities - The activities can take place at the same time Immediate Predecessor - That activity that must be completed just before a particular activity can begin

8-12 Terminology Continued Activity on Arrow - Arrows represent activities while nodes stand for events Activity on Node - Nodes stand for events and arrows show precedence

8-13 AON and AOA Format Figure 8-3 Figure 8-2

8-14 Constructing the Network Begin with START activity Add activities without precedences as nodes – There will always be one – May be more Add activities that have those activities as precedences Continue

8-15 Solving the Network Table 8-1

8-16 The AON Network from the previous table Figure 8-13

Project Network for a House Lay foundation Design house and obtain financing Order and receive materials Dummy Finish work Select carpet Select paint Build house

Critical Path A path is a sequence of connected activities running from start to end node in network A path is a sequence of connected activities running from start to end node in network The critical path is the path with the longest duration in the network The critical path is the path with the longest duration in the network Project cannot be completed in less than the time of the critical path Project cannot be completed in less than the time of the critical path

The Critical Path A: = 9 months B: = 8 months C: = 8 months D: = 7 months Lay foundation Design house and obtain financing Order and receive materials Dummy Finish work Select carpet Select paint Build house

The Critical Path A: = 9 months B: = 8 months C: = 8 months D: = 7 months Lay foundation Design house and obtain financing Order and receive materials Dummy Finish work Select carpet Select paint Build house The Critical Path

Lay foundation Design house and obtain financing Order and receive materials Dummy Finish work Select carpet Select paint Build house Start at 3 months Start at 5 months 1 Finish at 9 months Start at 8 months Activity Start Times

Early Times ES - earliest time activity can start ES - earliest time activity can start Forward pass starts at beginning of CPM/PERT network to determine ES times Forward pass starts at beginning of CPM/PERT network to determine ES times EF = ES + activity time EF = ES + activity time ES ij = maximum (EF i ) ES ij = maximum (EF i ) EF ij = ES ij - t ij EF ij = ES ij - t ij ES 12 = 0 ES 12 = 0 EF 12 = ES 12 - t 12 = = 3 months EF 12 = ES 12 - t 12 = = 3 months Lay foundation Design house and obtain financing Order and receive materials Dummy Finish work Select carpet Select paint Build house

Computing Early Times ES 23 = max EF 2 = 3 months ES 23 = max EF 2 = 3 months ES 46 = max EF 4 = max 5,4 = 5 months ES 46 = max EF 4 = max 5,4 = 5 months EF 46 = ES 46 - t 46 = = 8 months EF 46 = ES 46 - t 46 = = 8 months EF 67 = 9 months, the project duration EF 67 = 9 months, the project duration Lay foundation Design house and obtain financing Order and receive materials Dummy Finish work Select carpet Select paint Build house

Computing Early Times Lay foundation Design house and obtain financing Order and receive materials Dummy Finish work Select carpet Select paint Build house (ES = 0, EF = 3) (ES = 5, EF = 8) (ES = 3, EF = 5) (ES = 3, EF = 4) (ES = 5, EF = 6)(ES = 6, EF = 7) (ES = 8, EF = 9) (ES = 5, EF = 5) Early Start and Finish Times

Late Times LS - latest time activity can start & not delay project LS - latest time activity can start & not delay project Backward pass starts at end of CPM/PERT network to determine LS times Backward pass starts at end of CPM/PERT network to determine LS times LF = LS + activity time LF = LS + activity time LS ij = LF ij - t ij LS ij = LF ij - t ij LF ij = minimum (LS j ) LF ij = minimum (LS j )

Computing Late Times LF 67 = 9 months LF 67 = 9 months LS 67 = LF 67 - t 67 = = 8 months LS 67 = LF 67 - t 67 = = 8 months LF 56 = minimum (LS 6 ) = 8 months LF 56 = minimum (LS 6 ) = 8 months LS 56 = LF 56 - t 56 = = 7 months LS 56 = LF 56 - t 56 = = 7 months LF 24 = minimum (LS 4 ) = min(5, 6) = 5 months LF 24 = minimum (LS 4 ) = min(5, 6) = 5 months LS 24 = LF 24 - t 24 = = 4 months LS 24 = LF 24 - t 24 = = 4 months Lay foundation Design house and obtain financing Order and receive materials Dummy Finish work Select carpet Select paint Build house

Computing Late Times LF 67 = 9 months LF 67 = 9 months LS 67 = LF 67 - t 67 = = 8 months LS 67 = LF 67 - t 67 = = 8 months LF 56 = minimum (LS 6 ) = 8 months LF 56 = minimum (LS 6 ) = 8 months LS 56 = LF 56 - t 56 = = 7 months LS 56 = LF 56 - t 56 = = 7 months LF 24 = minimum (LS 4 ) = min(5, 6) = 5 months LF 24 = minimum (LS 4 ) = min(5, 6) = 5 months LS 24 = LF 24 - t 24 = = 4 months LS 24 = LF 24 - t 24 = = 4 months Lay foundation Design house and obtain financing Order and receive materials Dummy Finish work Select carpet Select paint Build house ES = 3, EF = 5 LS = 3, LF = 5 ( ) ES = 5, EF = 8 LS = 5, LF = 8 ( ) ES = 3, EF = 4 LS = 4, LF = 5 ( ) ES = 0, EF = 3 LS = 0, LF = 3 ( ) ES = 5, EF = 5 LS = 5, LF = 5 ( ) ES = 5, EF = 6 LS = 6, LF = 7 ( ) ES = 8, EF = 9 LS = 8, LF = 9 ( ) ES = 6, EF = 7 LS =7, LF = 8 ( ) Early and Late Start and Finish Times

Activity Slack Activities on critical path have ES = LS & EF = LF Activities on critical path have ES = LS & EF = LF Activities not on critical path have slack Activities not on critical path have slack S ij = LS ij - ES ij S ij = LS ij - ES ij S ij = LF ij - EF ij S ij = LF ij - EF ij S 24 = LS 24 - ES 24 = = 1 month S 24 = LS 24 - ES 24 = = 1 month

Activity Slack Data Lay foundation Design house and obtain financing Order and receive materials Dummy Finish work Select carpet Select paint Build house ActivityLSESLFEFSlacks * * * * * * Critical path

Activity Slack Data Lay foundation Design house and obtain financing Order and receive materials Dummy Finish work Select carpet Select paint Build house ActivityLSESLFEFSlacks * * * * * * Critical path Activity Slack S = 0 S = 1 S = 0

8-31 Total Slack vs. Free Slack Slack calculations shown up to this point are for “Total Slack” Total Slack is the most a task can be delayed with changing the plan for project completion. – May cause delay on a successor, eating into its slack time. Free Slack is the amount a task can be delayed with no affect on any other task.

Probabilistic Time Estimates Reflect uncertainty of activity times Reflect uncertainty of activity times Beta distribution is used in PERT Beta distribution is used in PERT

Probabilistic Time Estimates Reflect uncertainty of activity times Reflect uncertainty of activity times Beta distribution is used in PERT Beta distribution is used in PERT a = optimistic estimate m = most likely time estimate b = pessimistic time estimate where Mean (expected time): t = a + 4 m + b 6 Variance:  2 = b - a 6 2

Example Beta Distributions P(time) Time amtbamtb m = t Time Time ba Figure 6.11

Southern Textile Company System changeover Manual Testing Dummy System Training Dummy System Testing Orientation Position recruiting System development Equipment installation Equipment testing and modification Final debugging Job training A B CED F G H I JK L M

Activity Estimates 1 - 2A B C D E F G H I J K L M11013 TIME ESTIMATES (WKS) ACTIVITY amb

Activity Estimates TIME ESTIMATES (WKS)MEAN TIMEVARIANCE ACTIVITY ambt 

Early and Late Times For Activity 1-2 a = 6, m = 8, b = 10 t = = = 8 weeks a + 4 m + b (8)  2 = = = week b - a

Early and Late Times ACTIVITY t   ESEFLSLFS

Southern Textile Company ES = 9, EF = 16 LS = 9, LF = 16 ES = 0, EF = 8 LS = 1, LF = 9 ES = 0, EF = 6 LS = 0, LF = 6 ES = 6, EF = 9 LS = 6, LF = 9 ES = 0, EF = 3 LS = 2, LF = 5 ES = 3, EF = 7 LS = 5, LF = 9 ES = 9, EF = 13 LS = 12, LF = 16 ES = 8, EF = 8 LS = 9, LF = 9 ES = 13, EF = 13 LS = 16, LF = 16 ES = 3, EF = 5 LS = 14, LF = 16 ES = 16, EF = 25 LS = 16, LF = 25 ES = 13, EF = 17 LS = 21, LF = 25 ES = 8, EF = 13 LS = 16, LF =

Southern Textile Company ES = 9, EF = 16 LS = 9, LF = 16 ES = 0, EF = 8 LS = 1, LF = 9 ES = 0, EF = 6 LS = 0, LF = 6 ES = 6, EF = 9 LS = 6, LF = 9 ES = 0, EF = 3 LS = 2, LF = 5 ES = 3, EF = 7 LS = 5, LF = 9 ES = 9, EF = 13 LS = 12, LF = 16 ES = 8, EF = 8 LS = 9, LF = 9 ES = 13, EF = 13 LS = 16, LF = 16 ES = 3, EF = 5 LS = 14, LF = 16 ES = 16, EF = 25 LS = 21, LF = 25 ES = 13, EF = 17 LS = 21, LF = 25 ES = 8, EF = 13 LS = 16, LF =  2 =  2 +  2 +  2 +  2 = = 6.89 weeks^ Total project variance

Probabilistic Network Analysis Determine probability that project is completed within specified time where  = t p = project mean time  =project standard deviation x =proposed project time Z =number of standard deviations x is from mean Z =Z =Z =Z = x -  

Normal Distribution Of Project Time  = t p Timex ZZProbability

Southern Textile Example What is the probability that the project is completed within 30 weeks?

Southern Textile Example What is the probability that the project is completed within 30 weeks?  = 25 Time (weeks) x = 30 P( x  25 weeks)

Southern Textile Example What is the probability that the project is completed within 30 weeks?  = 25 Time (weeks) x = 30 P( x  25 weeks)  2 = 6.89 weeks  = 6.89  = 2.62 weeks Z = = = 1.91 x -  

Southern Textile Example What is the probability that the project is completed within 30 weeks?  = 25 Time (weeks) x = 30 P( x  25 weeks)  2 = 6.89 weeks  = 6.89  = 2.62 weeks Z = = = 1.91 x -   From Excel, a Z score of 1.91 corresponds to a probability = normsdist(1.91) =

Southern Textile Example What is the probability that the project is completed within 22 weeks?  = 25 Time (weeks) x = 22 P( x  22 weeks)

Southern Textile Example What is the probability that the project is completed within 22 weeks?  2 = 6.89 weeks  = 6.89  = 2.62 weeks Z = = = x -    = 25 Time (weeks) x = 22 P( x  22 weeks)

Southern Textile Example What is the probability that the project is completed within 22 weeks?  2 = 6.89 weeks  = 6.89  = 2.62 weeks Z = = = x -   From Excel, a Z score of corresponds to a probability = normsdist(-1.14) =  = 25 Time (weeks) x = 22 P( x  22 weeks)

Normal Distribution Of Project Time When doing these problems in Excel use: norm.dist() to find a probability norm.inv() to find a date.

8-52 Calculating Activity Times

8-53 Uncertainty of Project Completion Time Assume activities are statistically independent Variance of a set of activities is the sum of the individual variances Interested in variances along the critical path

8-54 Toward Realistic Time Estimates Calculations are based on 1% chance of beating estimates Calculations can also be based on 5% or 10% Changing the percentage requires changing the formulae for variance When using 5%, the divisor changes to 3.29 When using 10%, the divisor changes to 2.56

8-55 Precedence Diagramming Finish to start Start to start Finish to finish Start to finish

Four Types of Dependencies – FS (Finish-to-Start) When A Finishes, B can Start Example: Foundation must be finished before framing starts PDM AON

Four Types of Dependencies – FF (Finish-to-Finish) When A Finishes, B can Finish Example: testing of an application cannot finish until coding is finished PDM AON

Four Types of Dependencies – SS (Start-to-Start) When A Starts, B can Start Example: Data entry can start as soon as data collection starts PDM AON

Four Types of Dependencies – SF (Start-to-Finish) When A Starts, B can Finish Example: legacy system cannot be shut down (finished) until new system has gone online (started) PDM AON

Three categories of dependencies – Mandatory Inherent (physical limitations) – Discretionary Preferred (defined by team) – External Legal (government) Contractual Other Dependency Determination

Lead – Successor can start before activity finishes – Example: Landscaping can begin before the completion of the building Shown on the diagram as a finish-to-start relationship with a lead Lead = (-1)Lag in MSP Applying Leads and Lags

Lag – Delay between activities Example: Concrete must cure before next activity can begin Shown on the diagram as a start-to-start relationship with a lag Applying Leads and Lags 15 d

Work (or Effort) is the number of workdays or work hours required to complete a task Duration includes the actual amount of time worked on an activity and the elapsed time Work = Duration x Units Estimating Activity Durations

Effort Driven = Constant Work 8-64 Task TypeEffort Driven ONEffort Driven OFF Fixed UnitsAdding Resources shortens duration Adding Resources increases total work, but not units and duration Fixed DurationAdding Resources decreases units for each resource Adding Resources increases total work, but not units and duration Fixed WorkAdding Resources shortens duration (N/A)