Brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Inner Triplet Review Q1, Q2, and Q3 Mechanics T. Nicol April 24-25, 2007.

Slides:



Advertisements
Similar presentations
MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
Advertisements

MICE- AFC Unit Mechanical Design of the Cold Mass Support System Oxford University Rohan Senanayake.
Vacuum Vessel Production Readiness Review
ITER VV supports Cadarache 6 September 2007 A. Capriccioli.
Liquefied Natural Gas Fuel tank
MICE Collaboration Meeting at Frascati, Jun 26~29, 2005 Iron Shield Mounting Design Stephanie Yang.
October, 2003 P. Fabbricatore and S. Farinon Spectrometer magnets – Possible layout of cryostat in the end region In order to define the cryostat layout.
Module Vessel Connection Concept Steve Virostek Lawrence Berkeley National Laboratory AFC Module Meeting April 23, 2004.
1 Update on Focus Coil Design and Configuration M. A. Green, G. Barr, W. Lau, R. S. Senanayake, and S. Q. Yang University of Oxford Department of Physics.
Progress on the MICE 201 MHz Cavity Design Steve Virostek Lawrence Berkeley National Lab RF Working Group Fermilab August 22, 2007  automatic.
Felix Wamers, Technical Coordination Meeting, 12 th -13 th of May CERN-GSI Technical Coordination Meeting Felix Wamers, Yu Xiang,
Strength of Material Shear Strain Dr. Attaullah Shah.
1 RF-Structures Mock-Up FEA Assembly Tooling V. Soldatov, F. Rossi, R. Raatikainen
Cryomodule Concept for the ODU RF Dipole Crab Cavity Tom Nicol* - Fermilab December 10, 2013 * With lots of help from HyeKyoung, Tom J, Shrikant, Ofelia,
Superconducting Large Bore Sextupole for ILC
LARP QXF 150mm Structure Mike Anerella / John Cozzolino / Jesse Schmalzle November 15, nd Joint HiLumi LHC-LARP Annual Meeting.
Brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Production Readiness Review January 23, 2002 T. Nicol – Fermilab
Aluminum bellows for experiments
DFBX Thermo-Mechanical Review
LBNL Test Cryostat Preliminary Design Review Tuning – Field Correction Soren Prestemon, Diego Arbelaez, Heng Pan, Scott Myers, Taekyung Ki.
R&D Status and Plan on The Cryostat N. Ohuchi, K. Tsuchiya, A. Terashima, H. Hisamatsu, M. Masuzawa, T. Okamura, H. Hayano 1.STF-Cryostat Design 2.Construction.
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
RFCC Module Design Update  automatic tuners  cavity suspension  cavity installation Steve Virostek Lawrence Berkeley National Lab MICE Collaboration.
1 LHC-DFBX Shipping Specification Steve Virostek LBNL Presented at the DFBX RFP Review October 2002, LBNL Brookhaven - Fermilab - Berkeley US LHC.
Work toward Stainless Steel SRF Helium Vessels at Fermilab Tom Peterson (presenter), Information from Jeff Brandt, Serena Barbanotti, Harry Carter, Sergei.
Key Design Issues and Recent Reviews Tom Peterson, Fermilab DFBX PRR, October 23, 2002 US LHC ACCELERATOR PROJECT brookhaven - fermilab - berkeley.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
Magnets and Supports Bob Wands October 20, 2006 PPD/MD/Engineering Analysis Group Fermilab 4 th Concept Detector at Fermilab October, 2006.
R. Ostojic CERN, AT Department. 2 LHC Insertions Experimental insertions in points 1, 2, 5, 8 contain low-beta triplets. In total, eight triplets are.
56 MHz SRF Cavity Cryostat support system and Shielding C. Pai
56 MHz SRF Cavity Thermal Analysis and Vacuum Chamber Strength C. Pai
C.Hauviller/TS-IC 27 avril April 2007 Summary C. Hauviller Review of the inner triplet.
SCH Controls Readiness Review- Cryostat Nov 4-5, 2015 Kurt Cantrell.
56 MHz SRF Cavity and Helium vessel Design
C. Garion Presentation Outline  Overview of the inner triplet interconnections  Q1/Q2, Q2/Q3 interconnections  General view  Working conditions  Compensation.
LMQXFA Cold Mass Assembly Antonios Vouris Fermilab February 3, 2016.
ILC IR FINAL FOCUS & EXTRACTION MAGNETS Prepared by Andy Marone ILC Workshop, Sept
4/27/06 1 US LHC ACCELERATOR RESEARCH PROGRAM brookhaven - fermilab – berkeley - slac US LARP Inner Triplet Cryogenics and Heat Transfer LARP Collaboration.
Cavity support scheme options Thomas Jones 25/06/15 1.
LHC Inner Triplet Status J. Kerby For…Ranko Ostojic, Cedric Garion, Tom Page, Thierry Renaglia, Herve Prin, Bob Wands, Frederic Gicquel, Ingrid Fang, Juan.
The integration of 420 m detectors into the LHC
Mike Struik / LHC-CRI INSTRUMENTATION FEEDTHROUGH SYSTEM FOR LHC MACHINE ARC QUADRUPOLE MAGNETS. 123rd LHC Vacuum Design Meeting 19 April 1999.
MICE RFCC Module Update Steve Virostek Allan DeMello Lawrence Berkeley National Laboratory MICE CM27 at RAL, UK July 8, 2010.
Adam Carreon July 19, 2012 Technical Division SRF Department Dressed SSR1 Cavities.
Magnet R&D for Large Volume Magnetization A.V. Zlobin Fermilab Fifth IDS-NF Plenary Meeting 8-10 April 2010 at Fermilab.
CW Cryomodules for Project X Yuriy Orlov, Tom Nicol, and Tom Peterson Cryomodules for Project X, 14 June 2013Page 1.
Fixes J. Kerby For my many colleagues who have contributed to this effort (Ranko Ostojic, Cedric Garion, Tom Page, Thierry Renaglia, Herve Prin, Bob Wands,
14-Jun-161 Status of Horizontal Test Stand (HTS-2) Development Efforts Pradeep Kush, Prashant Khare, RRCAT, India Team Members: S.Gilankar, Rupul Ghosh,
Thermal screen of the cryostat Presented by Evgeny Koshurnikov, GSI, Darmstadt September 8, 2015 Joint Institute for Nuclear Research (Dubna)
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
QXF magnet integration Paolo Ferracin Joint LARP/CM20 HiLumi meeting Napa Valley, CA, USA 8-10 April, 2013.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
F LESEIGNEUR / G OLIVIER LUND January 9th, ESS HIGH BETA CRYOMODULE ESS CRYOMODULE STATUS MEETING HIGH BETA CRYOMODULE LUND JANUARY 9TH, 2013 Unité.
Teleconf ACS – FREIA 28th March 2017
Status of the low-β triplets
MQXC Nb-Ti 120mm 120T/m 2m models
Roadmap for triplet cryostats
HFM Test Station Main Cryostat
Status of design and production of LEP connection cryostat
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
Challenges of vacuum chambers with adjustable gap for SC undulators
LARP Vertical Test Facility
Cedric Garion, TE-VSC-DLM, WP12
LHC IRQ Tie Bar Redesign Using Sleeves – Preliminary
The 11T cryo-assembly: summary of design and integration aspects
Cooling aspects for Nb3Sn Inner Triplet quadrupoles and D1
SNS PPU Cryomodule Space Frame
SNS PPU Cryomodule Space Frame
Status of QQXF cryostat
Presentation transcript:

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Inner Triplet Review Q1, Q2, and Q3 Mechanics T. Nicol April 24-25, 2007

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Complete magnet assembly (Q3)

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Q1 supports at IP 5L

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Brief history of notable design features External heat exchanger (including the corrugated copper tube) –Driven by different Q1/Q3 and Q2 cold mass diameters from Fermilab and KEK. At the time of the initial design both labs were planning to build cold masses of each type. The external design allowed a magnet-independent heat exchanger design. Spider support –Driven by the external heat exchanger which required a lot of radial space and precluded a suspension more like support posts used in the arc dipoles. –We sought to make a suspension system that was laterally stiff to preclude small oscillations due to ground motion and other influences. –Wanted to minimize warm to cold deviations. –Constant pressure to minimize static heat load lead to reduced thickness supports. Welded cold mass bellows –Driven by the desire to make quick connections to the Fermilab Magnet Test Facility feedbox without welding and subsequent cutting. –Performance history at Fermilab has been good albeit with smaller diameters and lower operating pressures. –We learned later that allowed pressures from manufacturers only apply when the bellows are compressed flat and restrained.

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Documentation Engineering Notes Technical Memos and Papers Specifications QA Documents Drawings Design Reviews Meetings and Workshops Are all available at:

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Materials 304 stainless steel – Piping, flanges, etc. –Allowable stress: 138 MPa (20000 psi) 304L stainless steel – Cold mass skins –Allowable stress: 115 MPa (16700 psi) 6061-T6 aluminum – Shield shells and extrusions, pipe supports –Allowable stress: 59 MPa (8600 psi) Carbon steel - Vacuum vessel –248 MPa (36000 psi) min yield, Charpy toughness 21 J/cm2 min, 28 J/cm2 average over 3 tests (equivalent to L485MB) G-11 CR – Supports –Allowable stress: 69 MPa (10000 psi) based on 139 MPa (20000 psi) ultimate C932 bearing bronze – Support rods, cold mass adjusting screws

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Loads considered Shipping and handling loads. Vertical and lateral loads were thought to be the dominant loads driving the design of the suspension system. Axial shipping loads were always thought to be handled by external restraints. Cooldown loads associated with change in diameter and length of the cold mass, piping, and thermal shield. Pressure loading on the piping support system. Early design efforts focused more on individual magnet and cryostat elements rather than the system as a whole. Forces due to pressure asymmetries were underestimated and underappreciated. Vacuum loading on the external support system. Cold mass weight.

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Internal piping nomenclature

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Piping parameters

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Magnet and cold mass weights

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Q1 and Q3

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Q1 internal piping assembly F Q1-Q2

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Q3 internal piping assembly F Q1-DFBX F Q1-Q2

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Path of forces Forces originate at the magnet interconnect from bellows spring forces and pressure induced axial forces… …they act on the internal piping and are transmitted to the cold mass through the pipe anchors… …then are transferred to the support structure through the anchor and slide mechanisms… …then to the vacuum vessel through the external support lugs… …and finally to the floor through the external jacks.

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Q1 and Q3 forces Bellows forces, Fb, are due to pressure and mechanical compression and extension

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Magnet to magnet interconnect

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Bellows forces at design pressure

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Bellows forces at test pressure

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Bellows forces due to cooldown

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Q1 pipe support weldment (Q3 similar)

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Q1 pipe support weldment proposed modification As designed pipe anchor stresses Bracket to cold mass weld stress: psi (288 MPa) Elbow to end dome weld stress: psi (120 MPa) Modified pipe anchor stresses Bracket to cold mass weld stress: 9121 psi (63 MPa) Elbow to end dome weld stress: 9430 psi (65 MPa) See Q1 Pipe Anchor Stress Analysis – T. Page, April 19, 2007

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Spider and cold mass attachment

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Spider and cold mass attachment

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Spider and tie bar assembly

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Vacuum vessel attachment

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Vacuum vessel attachment

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Completed cold mass and piping on spider supports

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Completed cold mass and piping on spider supports

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, External jack stands in warm fit-up

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Q2

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Q2 internal piping assembly F Q2-Q3 F Q1-Q2

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Path of forces Forces originate at the magnet interconnect from bellows spring forces and pressure induced axial forces… …they act on the internal piping and are transmitted to the cold mass through the pipe anchors… …then are transferred to the support structure through the anchor and slide mechanisms… …then to the vacuum vessel through the external support lugs… …and finally to the floor through the external jacks.

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Q2 forces Bellows forces, Fb, are due to pressure and mechanical compression and extension

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Magnet to magnet interconnect

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Bellows forces at design pressure

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Bellows forces at test pressure

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Bellows forces due to cooldown

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Q2 pipe support

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Q2 pipe support shear stresses (Forces due to bellows installation forces at one end only.)

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Spider and cold mass attachment

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Spider and cold mass attachment

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Spider and tie bar assembly

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Vacuum vessel attachment

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Vacuum vessel attachment

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Completed cold mass and piping on spider supports

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Completed cold mass and piping on spider supports

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, External jack stands in warm fit-up

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Combined systems

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Summary of items tested Heat exchanger performance extensively tested in full-scale prototype Corrugated tube test. Two supports tested to simulate lateral, vertical, and cooldown loads Slide material tests Shipping and handling test Bellows tests –Cooldown and shield line bellows tested to 25 bar – result lead to redesign of all bellows except for cold mass bellows –Cold mass bellows tested to 25 bar – result lead to supplemental squirm protection incorporated into bellows restraints Warm fit-up at CERN in building 181

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Heat exchanger test

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Heat exchanger test

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Spider support test Two tests to failure in the horizontal direction. Failure at: lb (81847 N) and lb ( N) S.F. on lateral load of 1.75 for Q1/Q3 and 2.25 for Q2 based on minimum test result

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Warm fit-up assembly

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Interconnect at warm fit-up

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Interconnect at warm fit-up

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Cold mass bellows test

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Pressure tested items at Fermilab 25 bar test –Completed cold mass –Cold mass pipes and bellows (M1, M2, M4) –Heat exchanger outer shell (L) –Cooldown line (LD) in Q1 –EE, and FF only one article –XBt and collection volume tested to 5 bar after addition of the collection volume Pressurized leak test –Competed Q1 and Q3 cold masses and all internal piping pressurized to 2 bar with cryostat evacuated Vacuum leak tested –All internal components and completed system piping prior to cryostating

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Shipping

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Typical magnet shipping configuration

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Analysis results - 2g vertical + 1g lateral load Shipping and handling loads: Lateral: 1g Vertical: 2g (1g + weight) Axial: 0.1g w/ restraint  max = psi (76 MPa)

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Tie rod assembly at warm fit-up

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Tie bar analysis load cases and results Load case 1 – All vacuum vessels are allowed to slide on their vertical supports in Z without resistance. The system is constrained against Z-motion only at the end of the DFBX-to-V3 connecting rods. Loading is 25 bar warm pressure test loading. Load case 2 – Vacuum vessels constrained as in load case 1. Loading is the 25 bar warm pressure testing loading, plus the vacuum load. Load case 3 – Jacks with a Z compliance of lbs/in are placed at each vessel at the support location nearest the IP. Loading is the same as load case 1. Load case 4 – Vacuum vessels constrained as in load case 3. Loading is the same as load case.

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Vacuum vessel ear deflection – Case 1 (worst case)

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Vacuum vessel ear deflection – Vacuum only Ear deflection = (0.156 – 0.133) in = in (0.6 mm)

brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Cryostat Review April 24-25, Other areas of concern Interconnect “H” piece should be tested to 25 bar with ends configured comparable to actual installation. Q1 and Q3 internal piping anchors. Column buckling of the cryostat pipes, particularly the LD line. Should be mechanically tested.