Minimalist Mars Mission Establishing a Human Toehold on the Red Planet Executive Summary DevelopSpace MinMars Team.

Slides:



Advertisements
Similar presentations
Concept Overview for 2 mt Case “2 mt case”: integrated payloads of no more than 2 mt can be landed on the surface of Mars; extension of current Mars EDL.
Advertisements

Presented by Marco Christov at the 11th Mars Society Annual Convention, 14 – 17 August 2008, Boulder Colorado. A Mars Heavy Transport.
National Aeronautics and Space Administration Presentation to the NASA Goddard Academy 2. Constellation Overview Ken Davidian Lead, Commercial.
 Falcon 9 Heavy › To carry crew capsule and propellant required to rendezvous with transit vehicle Image Credit:
“Mars To Go” Based Missions Donovan Chipman David Allred, Ph.D.
IAC 2008, GlasgowDevelopSpace Minimalist Human Mars Mission IAC-08-A5.1 OPEN INNOVATION FOR SPACE SYSTEMS – USING THE DEVELOPSPACE PLATFORM FOR DESIGNING.
Larry Bell, Sasakawa International Center for Space Architecture (SICSA) Gerald D. Hines College of Architecture, University of Houston, Houston TX RUTGERS.
Minimalist Mars Mission Establishing a Human Toehold on the Red Planet January 2011 Review DevelopSpace MinMars Team.
Minimalist Human Mars Mission Surface infrastructure discussion July 26 th, 2008.
MinMars Project Surface Infrastructure Update A DevelopSpace Project June 15 th, 2008.
Project X pedition Spacecraft Senior Design – Spring 2009
Earth-Moon Transport Doroteo Garcia Kazuya Suzuki Patrick Zeitouni.
Strategic Plan Elements: ISRU, Analog Outpost Mike Duke November 10, 2008.
TMS logo THE MARS SOCIETY Life on Mars? ALH84001 Could There Be Life On Mars?
Human Exploration And Development of Space NASA and North Carolina: Building Stronger Partnerships April 24, 2002.
Jet Propulsion Laboratory California Institute of Technology National Aeronautics and Space Administration National Aeronautics and Space Administration.
Near-Term Mars Colonization - DevelopSpace Project - April 20, 2008.
Near-Term Mars Colonization -A DevelopSpace Project- May 25 th, 2008.
Background The Apollo program sent 12 Americans to the lunar surface between 1969 and 1972, but humans have not set foot on the moon since then. In January.
The Return to Space Exploration Constellation. NASA Authorization Act of 2005 The Administrator shall establish a program to develop a sustained human.
. Mr. K. NASA/GRC/LTP Part 3 The Future. Preliminary Activities Imagine that you are part of a team planning for an eventual human landing on Mars. You.
Near-Term Mars Colonization -A DevelopSpace Project- June 28 th, 2008.
Oh, Thank Heaven for 7-Eleven: Fueling Up in Space with In-Situ Resource Utilization ASTE-527 Final Presentation Riley Garrett.
Constellation Program Overview Mark Geyer Constellation Program Office October 2006.
The ISECG Global Exploration Roadmap Status update at Target NEO2 Workshop July 9, 2013 NASA/Kathy Laurini Human Exploration & Ops Mission Directorate.
Jet Propulsion Laboratory California Institute of Technology August 4, 2015 Austin Nicholas Landing Site Considerations Related to the Potential Sample.
Advanced Space Exploration LEO Propellant Depot: Space Transportation Impedance Matching Space Access 2010 April 8-10, 2010 Dallas Bienhoff Manager, In-Space.
Mars Orbit Rendezvous Robert Dyck. Only land what you need Mars Direct ERV contains stuff not needed on Mars Food & life support for transit to Earth.
STRATEGIES FOR MARS NETWORK MISSIONS VIA AN ALTERNATIVE ENTRY, DESCENT, AND LANDING ARCHITECTURE 10 TH INTERNATIONAL PLANETARY PROBE WORKSHOP June,
MIT : NED : Mission to Mars Presentation of proposed mission plan
RASC-AL 2010 Topics. TECHNOLOGY-ENABLED HUMAN MARS MISSION NASA is interested in eventual human mission to the Martian surface. Current Mars design reference.
Mars Today 1 An immediate and inexpensive program for manned Mars visitation.
TYLER PATTERSON MARS ONE:.  Mars One is an international private sector initiative to start a small colony on the surface of mars.  Founded in 2011.
HIAD Mission Infusion: Technology Development & Potential Utilization
Introduction to the Altair Project
America will send a new generation of explorers to the moon aboard NASA’s Orion crew exploration vehicle. After that, on to MARS!!!
The Augustine Committee Review of Human Spaceflight Plans Committee Briefing to COMSTAC October 29, 2009 Review of US Human Space Flight Plans Committee.
Unit 6 Lesson 1 Explanation. In 2004, President Bush set the following goal for the NASA constellation program, “this vision… is a sustainable and affordable.
MinMars Update Telecon October, 25 th Mars Design Reference Architecture 5.0 New reference document as of July 2009 – NASA-SP – Uploaded.
Human Exploration of Mars Design Reference Architecture 5
Near-Term Mars Colonization -A DevelopSpace Project- May 4 th, 2008.
Crew Mobility for Lunar Surface Exploration Dr. Rob Ambrose NASA-JSC May 2008.
LEO Propellant Depot: A Commercial Opportunity? LEAG Private Sector Involvement October 1 - 5, 2007 Houston, Texas LEAG Private Sector Involvement October.
Review of Past and Proposed Mars EDL Systems. Past and Proposed Mars EDL Systems MinMars Mars entry body design is derived from JPL Austere Mars entry.
National Aeronautics and Space Administration February 27, 2013 Defining Potential HEOMD Instruments for Mars 2020 A Work in Progress... NOTE ADDED BY.
Near-Term Mars Colonization -A DevelopSpace Project- June 15 th, 2008.
Recommendation to Cease NASA Crew Return Vehicle Development April 29, 2004 Amanda KellyBlake HajovskyAnthony Pittman Engineering Technical Communications.
October, 2005 NASA’s Exploration Architecture. 2 A Bold Vision for Space Exploration  Complete the International Space Station  Safely fly the Space.
Orbital Aggregation & Space Infrastructure Systems (OASIS) Background Develop robust and cost effective concepts in support of future space commercialization.
An Earth – Moon Transportation System Patrick Zeitouni Space Technology.
National Aeronautics and Space Administration The Evolvable Mars Campaign in support of a Sustainable Journey to Mars The Evolvable Mars Campaign in support.
Affording Mars II: October, 2014 Turning Vision into Reality Humans to Mars Summit May, 2016 George Washington University Washington,
NASA Collaboration with SpaceX’s Red Dragon Mission FISO Telecon September 21, 2016 Phil McAlister, NASA Headquarters.
The Future of Human Spaceflight *** A Journey to Mars
Callisto Mission LaRC Option
LunarCOTS.com CisLunarOne.com
The ISECG Global Exploration Roadmap Status update at Target NEO2 Workshop July 9, 2013 NASA/Kathy Laurini Human Exploration & Ops Mission Directorate.
NASA Hypersonic Research
h t t p : / / w w w . u s c . e d u / g o / t t c
Return to The Moon: An International Perspective
Mars Sustainability Workshop Kennedy Space Center February 8, 2018
  Robert Zubrin Pioneer Astronautics W. 8th Ave. unit A
Sustainable Space Development
Introduction to the Altair Project
Mars as Seen from Phobos
  Robert Zubrin Pioneer Astronautics W. 8th Ave. unit A
Humans to the Red Planet within a Decade
Humans to the Red Planet within a Decade
Where do we go from here? Goals of human exploration of Mars: Science, Outpost, Settlement NASA’s Plan: Earth Reliant è Proving Ground è Independence.
Deep Space Exploration Requires the best from all of us
Presentation transcript:

Minimalist Mars Mission Establishing a Human Toehold on the Red Planet Executive Summary DevelopSpace MinMars Team

MinMars: Motivation and Concept Ultimate goal: sustainable human expansion into space – making humanity a multi-planetary species Logical first step towards this goal: establishing a human settlement on Mars and expanding it into a mostly self-sustaining colony –Why Mars? Mars is the best choice for an initial settlement (resources, atmosphere, gravity, accessibility / transportation requirements) MinMars is concerned with establishing an initial human toehold: 4 humans get to Mars and remain there for the rest of their lives –Functionally corresponds to Bob Zubrin’s exploration and base phases –The initial crew proves long-term habitability and tests the technologies necessary to establish a more expansive human settlement and colony The DevelopSpace MinMars study is intended to establish toehold near-term feasibility and identify important topics for detailed work –Somewhat similar in function to NASA’s Mars design reference missions

MinMars Toehold Outpost Architecture Habitat: assembled out of several modules (hard- shell as well as inflatable); number of modules dependent on Mars lander payload (2 mt assumed) Power: thin-film solar arrays & li-ion batteries Location: around 30 deg northern latitude due to solar power generation concerns Life support & ISRU: high-closure life support with water distillation and filtering; in-situ oxygen and buffer gas production; initially no in-situ water production, water required for loop closure is imported Resupply: very conservative estimate of ~24 mt of resupply per opportunity (for 4 crew); would require 12 launches with performance 30 mt to LEO (old SpaceX Falcon 9 Heavy performance class) Surface mobility: unpressurized rovers (exploration radius of km); would be similar to NASA’s lunar mobility chassis Image credit: NASA

Cargo Transportation Earth Mars Low Mars Orbit Highly Elliptic Earth Orbit (e.g. GTO) 1-13 months of loitering Direct Mars entry (lifting) using an extension of Viking EDL technology Commercial Earth launch (e.g. on a Falcon 9 Heavy) Trans-Mars coast (~ 6-8 months) 2 mt of useful payload on the surface of Mars; 1 km landing accuracy Pre-deployed beacon Note: concept based on old SpaceX Falcon 9 Heavy performance numbers – needs to be revised

Mars EDL Concept Analyses indicate that existing Mars EDL technology can be extended to a payload mass of 2000 kg –See NASA Mars Design Reference Architecture 5.0 –Existing Mars EDL technology was developed for Viking => Extension of the MSL EDL system (however, no skycrane, lander stage instead): –MSL ballistic coefficient: 115 kg/m 2 –MSL reference area (4.6 m diameter): m 2 –Payload mass fraction on entry: 775 kg / 2800 kg = 0.28 –MSL hypersonic drag coefficient: 2800 kg / (115 kg/m 2 x m 2 ) = 1.46 –MSL propellant mass estimate: 8 x 50 kg = 400 kg MinMars EDL system characteristics: –Entry mass: 2000 kg / 0.28 = 7143 kg –Reference area: 7143 kg / (1.46 x 115 kg / m 2 ) = m 2 –Aeroshell diameter: 7.36 m –Lander propellant mass: 2000 kg / 775 kg x 400 kg = 1032 kg –EDL system dry mass (including the cruise stage): 8000 kg – 2000 kg – 1032 kg = 4968 kg Ballistic coefficient: MSL scaled up 7.36 m MinMars aeroshell Payload envelope (cylinder): 1.5 m diameter, 2.5 m height Note: concept based on old SpaceX Falcon 9 Heavy performance numbers – needs to be revised

Crew Transportation (for 2 Crew) Earth Mars Low Mars Orbit Low Earth Orbit (e.g. GTO) 1-5 months of loitering for Earth departure stages Direct Mars entry (lifting) using an extension of Viking EDL technology Commercial cargo launch (e.g. on a Falcon 9 Heavy) Trans-Mars coast (~ 6 months) 2 crew members on the surface of Mars; 1 km landing accuracy Pre-deployed beacon Mars lander ITH Earth departure stage 2 Earth departure stage 1 Commercial crew launch (e.g. Falcon 9 / Dragon) Earth departure stages discarded ITH discarded Note: concept based on old SpaceX Falcon 9 Heavy performance numbers – needs to be revised

Net-Present-Cost (NPC) Analysis Assumptions Cost estimates for spacecraft, surface infrastructure, and propulsion systems carried out with mass-based CERs –All estimates in FY04 $ Mn Launch cost for a Falcon 9 Heavy class launch vehicle assumed to be FY04 $ 150 Mn Learning rates (and associated reduction of unit costs) not included in the analysis presented here Non-discounted as well as discounted analyses (sensitivity analysis to discount rate) Time horizon for DDT&E: 5 opportunities (~ 10 years) Please note: this is a notional analysis intended only to assess orders of magnitude and relative importance of cost contributions

NPC by Category Non-discounted5% discount rate10% discount rate Note: concept based on old SpaceX Falcon 9 Heavy performance numbers – needs to be revised

Technology Investment Options In-situ food production –Could significantly improve resupply cost and risk (dependence on Earth-based supply) In-situ water production –Could significantly improve resupply cost and risk (dependence on Earth-based supply) In-situ production of spare parts –Could significantly improve resupply cost and risk (dependence on Earth-based supply) Higher-payload-mass EDL systems + HLLV –Reduces the number of landings, assembly operations –Makes most sense when combined with a higher-payload Earth launch capability (50 – 70 – 100 mt to LEO) Advanced EVA suits for Mars surface environment –Could significantly improve resupply cost (no metal oxide)