1 GLD and GLDc Sep. 12, 2007 Y. Sugimoto KEK. 2 Compact GLD Option Motivation –GLD and LDC will write a common LoI –The detector design should have common.

Slides:



Advertisements
Similar presentations
SiD Surface assembly Marco Oriunno (SLAC) MDI-CFS Meeting Sep. 4-6, 2014, Ichinoseki (Japan)
Advertisements

Assembly Hall in Hybrid-A’ and ILD 2014/9/6 Yasuhiro Sugimoto 1.
Global Design Effort Goals and Introduction Andrei Seryi, SLAC, September 17, 2007.
1 IR Hall for GLD Oct Y. Sugimoto KEK. 2 Underground hall HybridPure CMS IR hall area (WxL)25x55 Beam height8.6 Crane max hook height20.5 Largest.
Global Design Effort Detector concept # Plenary introductory talk IRENG07 Name September 17, 2007.
Tagger and Vacuum Chamber Design. Outline. Design considerations. Stresses and deformations. Mechanical assembly.
“GLD” Detector Concept Study 21. Mar. Y. Sugimoto KEK.
DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1.
Experimental hall in Japanese mountain site Y. Sugimoto ILD MDI/Integration 1.
Global Design Effort Detector concept Plenary introductory talk IRENG07 Kurt Krempetz September 17, 2007.
1 FD Support and Pacman for GLDc 27 Aug Yasuhiro Sugimoto KEK.
1 Design of Solenoid and iron yoke for GLD KEK Hiroshi Yamaoka Ken-ichi Tanaka July 13, ‘05.
Tracking Integration Challenges Y. meeting 2013/9/25.
1 GLD Surface Assembly Y. Sugimoto KEK
1 ILD/CMS Engineering Meeting M. Joré – ILD integration philosophy Integration philosophy of ILD Matthieu Joré – January 21st Integration of the subdetectors.
LCWS14 Benoit CURE - CERN/PH Dept.1 International Workshop on Future Linear Colliders October 2014 Organized by the Vinca Institute of Nuclear.
1 Alternative assembly option of ILD Y.Sugimoto 2010/10/18 ILD Integration
Experimental hall in Japanese mountain site Y. Sugimoto 1.
111 ILD LOI Part-II: Detector Y. Sugimoto KEK for ILD concept group.
October 13, 2006 Global Design Effort 1 International Linear Collider Machine Detector Interface Materials for discussion at Engineering Forum: experiences.
Philip Burrows SiD Meeting, Paris 11/02/081 Machine Detector Interface Issues Philip Burrows John Adams Institute Oxford University Thanks to: Tom Markiewicz.
September 18, 2007H. J. Krebs1 SiD Collaboration One Piece End Door Design Concept plus Forward Equipment Interfaces H. James Krebs SLAC September 18,
KEK Hiroshi Yamaoka Task list for Magnet/Iron yoke Solenoid magnet Iron yoke Experimental hall and other facilities May 11, ’05.
MEA Machine and Experiment Assembly 1 Norbert Meyners, MEA Engineering Forum at CERN 12.Okt Thoughts about LDC Hall and Assembly (Work is not finished.
Si D in 14mrad/14mrad/z=0 ILC T. Markiewicz/SLAC SiD Advisory Group 14 August 2006.
Zian Zhu Magnet parameters Coil/Cryostat/Support design Magnetic field analysis Cryogenics Iron yoke structure Mechanical Integration Superconducting Magnet.
4366-ILD-T-Platform-and-environment.ppt A. Hervé Seoul workshop 17 February 2009 Concept of Platform and Environment A. Hervé / ILD-Webex meeting.
Global Design Effort Critical Interaction Region Issues, Report from the IR engineering workshop Andrei Seryi, SLAC October 24, 2007.
18/11/04DELPHI visits, PhC1 Visits to DELPHI/LHCb Ph.Charpentier.
Cost Issues Y.Sugimoto, A.Maki Estimation Procedure Get unit cost from the cost estimation for GLD(DOD) Estimate (relative) amount of return-yoke.
ILD requirement for assembly space and time 2015/11/3 Yasuhiro 1.
MEA Machine and Experiment Assembly Norbert Meyners, MEA 17. Sept. 2007ILC IRENG07; SLAC1 LDC Engineering Design (Status)
1 ILD meeting LAL M. Joré – Integration status Matthieu Joré – 25 th of May ILD integration status and open issues.
1 Design Activity of Large Detector for ILC July 18, 2007 Yasuhiro Sugimoto KEK.
GLD experimental hall and detector assembly Y.Sugimoto KEK 27 Sep
An Hybrid QD0 for SID ? Marco Oriunno (SLAC), Nov. 14, 2013 LCWS13, TOKYO.
1. Introduction 2. Magnetic field design Optimization of yoke configuration in several conf. Boundary conditions -
Assembly scenario of ILD Si trackers 2015/4/21 Yasuhiro 1.
Philip Burrows MDI Panel Meeting 15/08/06 Philip Burrows John Adams Institute Oxford University SiD and IR/MDI Issues.
Reducing the Iron in the Endcap Yoke of CLIC_SiD Benoit Curé, Konrad Elsener, Hubert Gerwig, CERN CERN, June 2014 Linear Collider Detector Magnet Meeting.
ILD and SiD in Japanese site (from discussions in SiD/ILD E/D Interface Working Meeting) Yasuhiro Sugimoto, Marco Oriunno 2011/12/15 SiD
SiD MDI Issues Tom Markiewicz/SLAC Beijing ACFA/GDE Meeting 05 February 2007.
Experimental hall in Japanese mountain site 2011/11/30 Yasuhiro CFS Webex meeting 1.
MEA Machine and Experiment Assembly Norbert Meyners, MEA 12. July 2007ILC IRENG07 WG-A1 LDC Engineering Design (Status) Introduction General Design Detector.
12 July 2007IRENG07 WG-A M. Breidenbach1 SiD Concept SiD is relatively modest in scale compared to the LHC detectors, and comparable to SLD: Tracker Radius.
Implication of gamma-gamma on 14mr tunnels discussion (questions for discussion with WG-C and WG-A) Valery Telnov Budker INP IRENG07, Sept.19, 2007, SLAC.
F. Kircher CLIC concept meeting 12/15/08 1 Some points about the superconducting magnet for a CLIC detector F. Kircher (CEA Saclay/DSM/Irfu/SACM) December.
Octobre LAL Orsay Report from the IRENG07 workshop at SLAC W. Lohmann, DESY from Septembre 17 – 21, ~ 100 participants - plenary and parallel sessions.
An idea of ILD general assembly plan 2015/10/8 Yasuhiro Integration Meeting 1.
1 MDI/Integration issues of GLD(c) Yasuhiro Sugimoto KEK Jan. 15,
M.Oriunno, SLAC 1 SiD installation with horizontal access shafts Marco Oriunno, SLAC SiD/ILD Engineering Meeting SLAC, December 2011.
1 Update of detector hall in mountain regions Y.Sugimoto in Granada.
Experimental Hall in Mountain Regions
2016/9/30 Yasuhiro Infra/CFS mini-ws
Detector Utility/Service Cavern
Yasuhiro Sugimoto 2012/2/1 ILD integration meeting
Magnetic System Overview Solenoid and Anti-DID
Experimental hall design in Japanese site
Present status of the flux return yoke design
SiD Muon Yoke Structure - Deformation Studies -
Update of experimental hall in Japanese mountain site
Detector Service Cavern for ILC
Magnetic System Overview Solenoid and DID
Detector hall in mountain regions
Changes to SiD since the DBD
Sub-Detector Assembly Area Summary of discussion at ALCW2015
ILD-0 overall dimensions C.Clerc ILD meeting, Seoul 17/02/09
Radiation Physics requirements for the IR
Detector hall in mountain regions
Extract from today’s talk given to DCB
Presentation transcript:

1 GLD and GLDc Sep. 12, 2007 Y. Sugimoto KEK

2 Compact GLD Option Motivation –GLD and LDC will write a common LoI –The detector design should have common parameters –Common parameters should be determined based on detailed simulation study, but it will take a time ~0.5y(?) –As a working assumption for the moment, a modified design of GLD with the central values for B and R CAL between original GLD and LDC is made B=(3+4)/2=3.5 T R CAL =( )/2=1.85 m

3 Original GLD

4 Compact GLD - GLDc

5 Parameters (1) GLDGLDc Iron YokeBarrelRout7.2 m6.9 m Rin4.5 m4.1 m Weight6090 t5080 t E.C.Zin4.2/4.5 m3.7/3.95 m Zout7.5 m6.9 m Weight3260 t / side3050 t / side SolenoidB3 T3.5 T R4 m3.6 m Z4 m3.6 m Weight~330 t~300 t E1.6 GJ1.7 GJ Stray G120 G

6 Parameters (2) GLDGLDc TPCRin0.45 m Rout2.0 m1.75 m Zmax2.3 m2.0 m Barrel CALECALRin2.1 m1.85 m Rout2.3 m2.05 m BRin Tm Tm 2 HCALRout3.5 m3.15 m Thickness1.2 m1.1 m Weight1750 t1130 t BRin 2 =10.2 for LDC and 8.1 for SiD

7 Parameters (3) GLDGLDc EC CALECALZmin2.8 m2.4 m Zmax3.0 m2.6 m HCALZmax4.2 m3.7 m Thickness1.2 m1.1 m Weight270 t / side CALTotal weight2290 t1670 t Detector weight Barrel yoke + solenoid6.4 kt5.4 kt Barrel total8.2 kt6.5 kt Endcap total3.5 kt/side3.3 kt/side Total weight15 kt13 kt

8 Assembly GLD –Barrel part (Yoke+Sol.) > 6000 ton –For CMS style assembly (using 2000 ton crane to descend), it should be split into 5 rings and there will be many gaps Large stray field Difficulty in alignment of rings –In present design, GLD barrel yoke is split in R- and  -direction into 24 pieces –400-t cranes in the underground exp hall and surface assembly hall GLDc –Barrel part (Yoke+Sol.) < 6000 ton –Pure CMS style assembly can be done by splitting the barrel part into 3 rings and splitting each end cap part into two halves –50~100-t crane underground, 2000-t crane for the shaft, and 80-t crane in the surface assembly hall

9 Design of GLDc Endcap GLD/GLDc endcap yoke is vertically split Installation and maintenance of Muon detectors are done from the splitting plane (X=0 plane) like Belle detector Support rings can be put between iron slabs to increase the rigidity of the endcap yoke Usually two halves may be connected tightly and split only for installation and maintenance of sub-detectors Endcap calorimeters can be arranged without dead space Because hadrons make shower in the endcap iron, small gap of muon detectors does not make inefficiency of muon identification

10 Endcap Deformation Calculation by FEA method –Endcap is treated as a whole and surface force is calculated –The surface force at the front surface of the endcap is obtained as a function of R, and parameterized by a simple function –This simple function is used for the calculation of the deformation –Z-constraint only at R=4.1m (Inner radius of barrel yoke) –3D model calculation 25cm iron plates 5cm muon gaps Z-constraint Z R

11 Endcap Deformation Z R Magnetic Force

12 Endcap Deformation Results AngleSupport ring ZZ r=0.4 mr=6.9 m 3D180No -21 mm+11 mm  =0 -23 mm-13 mm  =90 3D360No-12 mm-3.9 mm 3D1801 (r=4.1m) -5.7 mm-0.6 mm  = mm-0.5 mm  =90 3D mm-0.2 mm 3D1802 (r=2.3, 4.1m) -2.6 mm+0.5 mm  = mm-0.7 mm  =90 3D mm-0.4 mm 3D1803 (r=2.3, 3.2, 4.1m) -1.7 mm+0.3 mm  = mm-0.7 mm  =90 3D mm-0.4 mm 2D360No-90 mm0 mm - FixSiD-like: 23x(10cm Fe + 5cm gap) 3D: 3-dimensional model 2D: Axial symmetric 2-dimensional model 180: Splitting endcap 360: Non-splitting endcsp

13 Endcap Deformation No support ringOne support ring/gap Splitting plane Symmetry plane 3D-180 degree model

14 Gap in sub-detectors Endcap calorimeters –Split along a plane which does not cross the IP (x=30cm plane, for example) Endcap muon detector –Split along the x=0 plane (same as iron yoke) –Tracks entering the muon-detector gap can be detected by TPC and calorimeters –If the particle is a pion, it creates hadronic shower in iron yoke, and would be detected by muon detector even if there is small gap

15 Gap in sub-detectors Endcap CAL

16 Pacman design and FD support A: slide sideway using air pad B: supported from the floor of platform QD0 cryostat is supported by the support tube and the support tube is supported from B We can put additional support for the support tube at the entrance of endcap yoke to damp the vibration, if necessary Upper part of B (~10 ton) must be removable by crane for installation and removal of the support tube C: slide along the wall (D) (common to both experiments) ~50 tonx2 D: part of the wall Wall distance can be as small as 11.5 m from IP, if the crane can access to 2.65m from the wall Construction of C is done by a mobile crane (CMS style) Inner radius of pacman should be determined after design of gate valve etc. between QD0 and QF1 is fixed Platform Wall

17 Pacman design and FD support Plan view 3D view B C The other experiment should make “nose” in their pacman to fill this gap Push-pull operation: Step-1: Open C-part Step-2: Disconnect beam pipe Step-3: Slide the platform

18 Pacman design and FD support Endcap open on the beam position TPC extraction for inner tracker maintenance at garage position

19 Still smaller cavern option Forget about crane access Forget about safety issues Design with cavern floor width as small as 21m can be drawn with the support- tube scheme –Pacman “C” moves upwards (using a small gantry crane fixed to the wall?) in push-pull operation –There is no way for a person to run away from one side of the detector to the other side (escape tunnel ?) C moves upwards in push-pull

20 B field of GLDc 500 G50 G B 0 =3.5 T B(10.5m<Z<20m) <50 G B(R>8m) <500 G Same calculation but different color mapping

21 L* for GLDc ComponentStartLength End cap yoke3.7 m BCAL3.8 m (note-1) 0.2 m BPM4.0 m0.2 m QD0 cryostat4.2 m0.264 m QD0 coil (L*)4.464 m L* of ~4.5 m seems adequate note-1: By putting BCAL at Z>Z endcap, strength of anti-DID can be reduced because R-component of solenoid B-field near the hole of end cap yoke can help guiding low energy pair-background into the beam exit hole

22 GLDc requirements for CFS Surface assembly hall –Same as CMS (?) Main shaft –16 m in diameter or larger Underground cavern –21 m floor (platform) width –Crane access to Z~9m –Cavern size is site-dependent Power consumption –Detector: xx kW –E-hut, sol. power supply, etc.: yy kW –Final doublet:  Ask WG-B –Platform movement: ?? –Light, air-conditioning:  Ask WG-C Guess of power consumption of detector DetectorE-hut, etc. VTX300 W3 kW SIT TPC CAL9 kW70 kW Solenoid-200kW/20kW Total

23 Other Issues Issues not studied yet –Detector cooling –Detector alignment –Luminosity (run period) needed for track-based alignment –Support scheme of beam pipe –Vibration analysis –Seismic issues –Services for detector solenoid including push-pull –Tolerable stray field from the viewpoint of safety and interference with near-by electric apparatus –Fire safety How to proceed these studies? –Should GLD and LDC do it independently? –Or, shall we study for the unified large detector?

24 Summary Thanks to intense discussion in WG-A, a self-consistent design of compact version of GLD – GLDc has been developed –Barrel yoke is divided into 3 parts in Z and pure CMS-like assembly is adopted –Requirement for capacity of the crane underground is much less than 400 ton –Endcap is vertically split and reinforced by support rings between iron slabs –Installation and maintenance of endcap muon detectors are done from the splitting plane (Belle-like) –Endcap calorimeters are split with an offset in x-direction not to make inefficient gap for neutral particles from IP –QD0 is supported from the floor through a support tube –The support tube is additionally supported from the endcap yoke to reduce the low-frequency vibration, if necessary –In the push-pull operation, beam line is cut between QD0 and QF1, pacman attached on the wall is open, and then, the detector and the QD0 support system move together sitting on a big (21mx23m) platform A lot of issues are still to be studied –Collaboration with LDC for a unified detector design seems reasonable