350MHz RF Waveguide Air Personnel Safety System Dave Bromberek March 3, 2008.

Slides:



Advertisements
Similar presentations
1. Four LLs were published in February Transmission Relaying – Undesired Blocking 2.Lack of Separation for Critical Control Power Supply Leads.
Advertisements

Submitted by: Name:Rajendra Kumar Choudhury Branch:Electrical Engg.
Setup/Installation/Operation of an Environmental Control Unit (ECU)
Freezer Alarm &Backup Systems Preventing Sample Losses * * * * * * * * * * * * * * * * * * * * * * * * Joe DeFrancesco, Gina Koskela, Peter Sturman Oregon.
Anesthesia Apparatus Checkout Recommendations
Full Authority Digital Engine Control
NERC Lessons Learned Summary December NERC lessons learned published in December 2014 Three NERC lessons learned (LL) were published in December.
Model 754 Portable Ventilator
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Shielding Workshop S. Buda Personnel Protective Systems March 27, 2007.
RF Safety Discussion Derun Li/Bob Rimmer Center for Beam Physics Lawrence Berkeley National Laboratory SRF Institute, JLab.
BEPCII RF POWER SYSTEM RF group, IHEP Sep ~ April 1.The 1 st transmitter had finished installing,commissioning and SAT (Site Acceptance Test).
GO ORDNANCE !!! ORDNANCECORPS 1 Antenna Mast Group We will now trace the electrical circuits of the antenna mast mast group. Be fore we get started you.
SYMAP-BC SYMAP-BC.
Using a Multimeter.
Integration of Cavities and Coupling Coil Modules Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting March 28 – April 1, 2004.
Safety Review: RF Issues Derun Li Absorber Safety Review December 9-10, 2003 Lawrence Berkeley National Laboratory Berkeley, CA
EPICS on TPS RF System Yu-Hang Lin Radio Frequency Group NSRRC.
CBC AUTOJH SYSTEM CONTROLS CHAPTER 10. CBC AUTOJH OBJECTIVES Discuss Operation and Function of controls for Manual and Automatic Climate Control System.
Possible Assembly and Test of the Crab cryomodule in SM18 at CERN P. Maesen LHC Crab Cav meeting, 17 Sep’ 09 LHC-CC09Cryomodule Assembly & Test Stand.
Pressure Switches. New modulating and multi-stage furnaces are more complex and require that installation instructions and procedures be followed so that.
Engineer Training UV Electrical Cabinet (16 and above) TJ8300 / TJ8500 UV Electrical Cabinet (Machines 16 and above)
Low Pressure, Continuous Flow Breathing Air System.
THE ELECTRIC SUB STATION
ATF2 Q-BPM System 19 Dec Fifth ATF2 Project Meeting J. May, D. McCormick, T. Smith (SLAC) S. Boogert (RH) B. Meller (Cornell) Y. Honda (KEK)
Thomas Jefferson National Accelerator Facility Page 1 Hall B Drift Chambers Review, March 2007 George Jacobs Jefferson Lab Hall B 12 GeV Upgrade Drift.
SPX High Level RF and RF Interlock Systems WBS U Doug Horan RF Systems Engineer Accelerator Systems Division/RF Group DOE Lehman CD-2 Review.
Single Loop Analogue addressable fire control Panel
RF power & FPC status Eric Montesinos, CERN BE-RF on behalf of all people involved, great thanks to all of them !
Thomas Jefferson National Accelerator Facility Page 1 Hall B Drift Chambers Review, March 2007 George Jacobs Jefferson Lab Hall B 12 GeV Upgrade Drift.
The APS 350-MHz CW RF Test Stand Dave Bromberek Advanced Photon Source Argonne National Laboratory.
Linac R&D Update May 15, L-Band Source Consists of a LLRF system (VME/Epics based), a SNS High Voltage Converter Modulator (on loan), a Thales 2104C.
Codan 5700 Series C-Band Transceiver Technical Overview.
Anders Sunesson RF Group ESS Accelerator Division
© Belimo University 2012, All Rights Reserved Pressure Independent Control Valves PICCV ePIV Energy Valve Belimo’s Family of PI Control Valves Flow Verification/Commissioning.
Ding Sun and David Wildman Fermilab Accelerator Advisory Committee
Test plan for SPL short cryomodule O. Brunner, W. Weingarten WW 1SPL cryo-module meeting 19 October 2010.
Invensys Controls Europe An Invensys Company EWCM 41x0 family New 32x74.
Hydro Multi-B – (2) or (3) CME Pumps in Parallel
1 Al Moretti, APC, Fermilab MAP- Winter Meeting February 28 - March 4, 2011 TJNAF Newport News, VA.
Neptune Power Versions compared 1 All rights reserved © 2003, Neptune Power sub-system Versions 1 and 2 Key features V2 is functionally equivalent to V1.
D. Valuch, N. Schwerg, O. Brunner (CERN)
1 © 2015 Eaton. All Rights Reserved.. Suggestion on How to Use Industry Trainers are encouraged to use this material in their sessions Download the presentation.
Cryostat & LHC Tunnel Slava Yakovlev on behalf of the FNAL team: Nikolay Solyak, Tom Peterson, Ivan Gonin, and Timergali Khabibouline The 6 th LHC-CC webex.
Summary of Relative RF Distribution Costs with Gradient Considerations (Work in Progress) Chris Adolphsen SLAC.
COOLING & VENTILATION PLANTS M. Nonis – CERN EN Department / CV Group Annual Meeting of the FCC study – Rome 14 th April 2016.
Technical Panel Session. Sunday January 11, DC System Failure Modes IEEE PES SBC Winter Meeting. January 11 – 15, New Orleans, LA Part 3.
ILCTA-MDB RF Power Status 4/27/06 Reid 1 ILCTA-MDB Status 1.3 GHz RF Power 3.9 GHz RF Power Meson Detector Building April 27, 2006 [John Reid]
Common Problems with Performance/Testing of Batteries
Using a Multimeter.
RF Systems and Controls for the LERF CM Tests
Completion of the MICE-US construction project
Doug Horan RF Group Accelerator Systems Division CWRF08 Workshop
ARAC/H/F Air-cooled water chillers, free-cooling chillers and heat pumps Range: kW.
System Network Structure
NERC Published Lessons Learned Summary
RF interlocks for higher intensities (LMC 15 June)
SPS cryogenic proximity equipment and SM18 validation
Tracker cooling loop “check out” draft for discussion
LV Safe Powering from UPS to Clients
12 GHz High Power RF components requirements for CEA activities
BEPCII RF POWER SOURCE AND INPUT COUPLER
The D.C. Scout Battery Distribution System Ground Locator
TS2 PSS Architecture, Concepts of Operations and Interfaces
Accelerator PSS Radiation Monitoring
Series 5300 Lithium Cell Formation System
Operation of Target Safety System (TSS)
Hardware integration and interfaces
Door Heat Exchanger: Specification
Injector/Linac RF Status
Presentation transcript:

350MHz RF Waveguide Air Personnel Safety System Dave Bromberek March 3, 2008

2 Outline System Operation and Layout Failure Modes 3 Year Calibration

3 System Operation Pressurization of the 350MHz waveguide system in Bldg. 420 is used as THE means of providing rf radiation personnel protection in the event of a breach of the waveguide system (see also technical note “Measurements of RF Power Radiated From Open WR2300 Waveguide Flanges” – D.Horan 7/3/05). Blowers on the rf cavities provide cooling air to the input couplers and also slightly pressurize the waveguides to ≈ 3-4”H2O (≈ psi.). The pressure is monitored and interlocked by eight waveguide photohelic pressure gauges, one or more of which is capable of detecting a waveguide flange gap of.185”, in all available waveguide switching modes. A trip of any waveguide photohelic will shutdown all five 350MHz klystron stations. Orphan photohelics are installed at RF1 and RF3 to provide protection in these areas when the stations are switched off-line. Additional photohelics monitor cavity blower pressure (Not Interlocked).

4 System Layout Two blowers supply cooling air to the input coupler and slightly pressurize the waveguide. Each cavity’s blower manifold is monitored by a photohelic. Cavity blower pressure is alarm only Each sector’s waveguide is monitored by a photohelic. Waveguide air pressure is a PSS interlock and will trip all 5, 350MHz rf stations.

5 System Layout

6 There are two blowers on each rf cavity, one being redundant. The cavity photohelics are on a scale on 0” – 10”H2O and read 10” or better with both blowers at full speed. Blowers are fed from two 120VAC power circuits/sector. Each cavity blower pair is fed from a separate circuit.

7 System Layout Waveguide photohelics are on a scale of 0” – 5”H20 and normally read between 3” - 4.5”H2O. Pressure sampling port is located on a section of waveguide in Bldg. 420 (see drawing)

8 System Layout Photohelic gauges are individually fused. A 24VDC power supply feeds the setpoint contacts from the cavity gauges to Allen/Bradley Fuse 24VDC Power Supply

9 System Layout

10 Blower Control Screen From RF Panel – Select Sector Cavity Photohelic Setpoint Contacts Blower AC Power Circuits

11 RF6 Waveguide Air PSS Screen From RF Panel - Misc/Tools

12 OAGapps Data From x-term type OAGapps

13 OAGapps Data

14 OAGapps Data

15 OAGapps Data

16 OAGapps Data

17 Failure Modes Cavity Blower AlarmCheck locallyDead or dying blower 8” H2OCheck OAGapps SymptomsStepsProblem

18 Failure Modes Cavity Blower AlarmCheck locally2 dead blowers 0”H2OCheck RF6Hose disconnected Check OAGappsBad Gauge SymptomsStepsProblem

19 Failure Modes Cavity photohelic hoses CAN be disconnected and connected to an adjacent gauge to eliminate the photohelic as the culprit. NEVER disconnect the waveguide photohelic hose unless the rf stations are already down due to a WG Air PSS trip. If it is determined that a waveguide photohelic is the problem, or the system is tripped on waveguide air, a work request and CCWP must be submitted and approved. C1C2 C3C4WG

20 Failure Modes 4 Cavity Blowers in AlarmCheck 24VDC P.S.Power supply 10”H2O SymptomsStepsProblem

21 Failure Modes 4 Cavity Blowers in AlarmCheck OAGappsAC Power 0” or Low “H2OCheck AC Power breakers Waveguide Air Trip SymptomsStepsProblem

22 Failure Modes Waveguide Air TripCheck waveguide integrityAny of these 0” or Low ‘H2OCheck for hose disconnection Gauge SymptomsStepsProblem

23 3-Year Calibration & Testing See “Technical Note on the Testing of the 350MHz Waveguide Air Personnel Safety System” – D. Bromberek 10/21/05 Test and adjust setpoints –Requires the opening/closing of five waveguide flanges (one at each station), in twelve waveguide switching modes – 60 iterations –Data is recorded and setpoints chosen.185” uniform gap in a waveguide flange trips RF6 PSS System.185” gap is detected by at least one photohelic in every waveguide configuration Loss of one cavity blower does not trip the PSS Loss of two cavity blowers does trip the PSS (Not always possible) –Validation and sign-off of CCWP requires tripping each of the eight waveguide photohelics one at a time, and verifying that it trips ALL FIVE STATIONS.

24 3-Year Calibration & Testing.185” Spacers.185” spacers in use

25 3-Year Calibration & Testing Data RF3 – May 2005

26 3-Year Calibration & Testing Simplified Data From RF3 – May 2005

27 3-Year Calibration & Testing Calibration due spring shutdown ’08.