Presentation is loading. Please wait.

Presentation is loading. Please wait.

Completion of the MICE-US construction project

Similar presentations


Presentation on theme: "Completion of the MICE-US construction project"— Presentation transcript:

1 Completion of the MICE-US construction project

2 MICE-US construction project
Scope well known Detector systems Scintillating fiber trackers Beam profile monitor (decommissioned) CKOVs LiH absorber Spectrometer solenoids Magnet systems QPS system Including extensive upgrades to original configuration Partial Return Yoke Step IV Step V’ (now will not be used) 2 201 MHz RF modules Everything complete except for delivery of the 2 RF modules MICE Project Board March 7, RAL Alan Bross

3 MICE Project Board March 7, 2017 RAL Alan Bross
RF Modules Complete stand-alone system MICE Project Board March 7, RAL Alan Bross

4 Body and Be window selection Frequency “tuning”
Cavity body (MHz) Be Window In (MHz) Be Window Out (MHz) Final Frequency (MHz) -0.517 Well within tuning capabilities of the MICE RF power system MICE Project Board March 7, RAL Alan Bross

5 MICE Project Board March 7, 2017 RAL Alan Bross
Status Module 2 “complete” Leak tight RF couplers Cavity water feedthroughs Actuators and gas lines Beryllium windows RF pickups Turbo-pump and NEG Vacuum gauges Bypass line and pressure box MICE Project Board March 7, RAL Alan Bross

6 RF Module 2 details Actuator with gas lines RF Coupler
Cooling Water Line Differential Pressure Box MICE Project Board March 7, RAL Alan Bross

7 MICE Project Board March 7, 2017 RAL Alan Bross
Vacuum tests Module 2 Vessel 4X10-7 torr Cavity 5X10-8 torr This vacuum fine for operation But expect ~ 5X lower in cavity when in operation in MICE Pumping System NEG Pump Turbo Pump Conductance to Cavity MICE Project Board March 7, RAL Alan Bross

8 Note on background rates
We completed a very successful program testing the MICE pre-production prototype cavity in the MTA at Fermilab Maximum gradient field on ~ 14 MV/m Very low background x-ray rates at MICE gradient of 8 MV/m (actually will be lower given RF power source available for MICE). At 8 MV/m with MTA 4T: Measured 2.2 mS/hr on 1.8m from high-gradient window Scaling to MICE with 1ms RF flattop at 1 Hz rep. rate yields ~ 6.5mS/hr (0.65 mR/hr). This corresponds to ~ 1 background hit/real muon hit MICE Project Board March 7, RAL Alan Bross

9 MICE Project Board March 7, 2017 RAL Alan Bross
Module 1 Final assembly work Install Be windows – initial pressure box tests were done with aluminum windows in case of failure Reconnect vacuum system + RGA Pump-down and leak check Module #1 RF testing follows MICE Project Board March 7, RAL Alan Bross

10 Be careful of things in “ ” Module 2 vacuum event
Power lost to roughing pumps, turbo-pump shut down Another group in the LBNL main shops disconnected the power to the RF mod 2 vacuum system, reconnected, but never contacted MICE team Vacuum went to 10-3 Torr level, Beryllium windows protected By-pass system worked NEG pump failed and oxidized, causing particulate contamination in lower vacuum system and bottom of cavity No contamination in the outer vacuum Vacuum level recovered – no vacuum contamination MICE Project Board March 7, RAL Alan Bross

11 MICE Project Board March 7, 2017 RAL Alan Bross
Module 2 vacuum event II Cleaning procedure with Isopropyl alcohol on cavity surface and beryllium windows Required opening module and gaining access to cavity interior Rinsed inner surface with IPA and wiped with lint-free cleanroom wipes - process repeated until wipes came back clean Successful -> removed particulate residues in lower vacuum components and cavity surface Re-installed beryllium window and module end flange System is currently under vacuum again and will be leak checked Recovery appears to be successful and complete Now pumping Vacuum good, but RGA shows H2O and alcohol Leak check tomorrow MICE Project Board March 7, RAL Alan Bross

12 Module #2 Low Level RF test ready to start
FNAL control system installed Actuator testing and cavity tuning frequency measurements ready to begin Scheduled for the week of March 13th, 2017 1-2 days required for testing LLRF test includes: Cavity frequency and Q0 measurement RF tuning system test RF coupling measurement Mark coupler orientation -> critical coupling MICE Project Board March 7, RAL Alan Bross

13 RF modules – final steps
Complete LLRF tests on module 2 next week Then begin crating Following week leak check and LLRF on module 1 Then crate To shipper by end of March This will then complete the MICE-US construction project. Note: normally installation and commissioning is part of the construction project, but will not be possible for RF modules at this time Would require new agreement MICE Project Board March 7, RAL Alan Bross

14 MICE Project Board March 7, 2017 RAL Alan Bross
Shipping RF modules Ship by end of March Modules will ship together Be windows installed RF couplers not installed, crated separately Clear acrylic inspection windows installed on RF coupler spool pieces Vacuum pumps and gauges installed Modules we be backfilled with N2 Modules mounted on isolation pallet & then crated. Provisions for Fork lift Exterior windows on crate for inspection Air shipment – arrival at Heathrow Airport ~ 2 week door-to-door MICE Project Board March 7, RAL Alan Bross

15 END


Download ppt "Completion of the MICE-US construction project"

Similar presentations


Ads by Google