Stefano Redaelli Beam Department - Operations Group Operational Aspects of the Phase II Crab Cavity System LHC-CC09 3 rd LHC Crab Cavity Workshop European.

Slides:



Advertisements
Similar presentations
Jan Uythoven, AB/BTLHCCWG, 3 May 2006 Page GeV Commissioning Machine Protection Needs to be commissioned to: Prevent damage with the used, higher.
Advertisements

DS Quench TEST 2  MOTIVATION and METHOD: 1. Achieve 500kW on beam 1 – TCP7 collimators.(so far 500kW with beam 2 and 235kW over 1s with beam 1 were reached.
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
RF de-bunching problem  The Beam Phase module measures the phase of each individual bunch and makes an average that is passed to the Low Level for updating.
Lot’s of time lost due to cryo problem in IR8. Major impact, therefore review of MD program… Start discussion here, please let us know your input. Will.
The ATS MD part III (Achromatic Telescopic Squeezing scheme) Participants: Any (active) volunteers Goal: 1)MD1 (S. Fartoukh & R. Assmann  10h): “Pre-squeeze’’
Beam Commissioning Workshop, 19th January Luminosity Optimization S. White, H. Burkhardt.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
1 Luminosity monitor and LHC operation H. Burkhardt AB/ABP, TAN integration workshop, 10/3/2006 Thanks for discussions and input from Enrico Bravin, Ralph.
LHC Technical Committee, 23/05/20071 LHC Commissioning Phases Squeeze presented by Massimo Giovannozzi on behalf of the LHCCWG Particular thanks to S.
CONTENT: Beam characteristics and parameters Filling schemes Operational settings OP procedure and COLL setting Planning Shift breakdown To define the.
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
1 Tunnel implementations (laser straight) Central Injector complex.
Friday to Saturday 02:00: Machine closed. 09:00: Cryogenics all OK. Preparing pre-cycle. 10:00: Pre-cycle started. 11:30: Pre-cycle finished. 14:00: Beam.
R. Assmann - LHCCWG Two Beam Operation R.W. Aßmann LHCCWG Acknowledgements to W. Herr, V. Previtali, A. Butterworth, P. Baudrenghien, J. Uythoven,
Global Design Effort ILC Crab Cavity Overview and requirements Andrei Seryi SLAC on behalf of ILC Beam Delivery and Crab-Cavity design teams Joint BNL/US-LARP/CARE-HHH.
R. Assmann - LTC Two Beam Operation R.W. Aßmann with W. Venturini and V. Kain LTC Acknowledgements to W. Herr, V. Previtali, A. Butterworth, P.
Machine development - results and plans – critical results, what’s to be done? R. Assmann 15/07/2011 R. Assmann for the LHC MD coordination team (R. Assmann,
Mariusz Sapinski BI/BL Acknowledgements: 1 Planning of quench tests - LMC158 Draft planning of beam induced quench tests at the end of 2013 run LHC Machine.
Injection Energy Review D. Schulte. Introduction Will review the injection energy So could answer the following questions: Which injection energy can.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
MD Wed – Sat DayTimeMD Wed06:00UPS repair, ATS optics checks w/o beam 12:00Cycle, test ATS optics w/o beam 16: TeV: BPM offset determination for.
M. Gilchriese LHC Startup Luminosity Planning July 29, 2005.
1 Commissioning and Operation of the machine protection system L. Ponce Acknowledgements: M. Zerlauth, J. Wenninger, D. Wollmann, V. Chetvertkova, G. Valentino,
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
LHC Machine Operational Status and Plans LHCC, 22nd September 2010 Steve Myers (On behalf of the LHC team and international collaborators)
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
RHIC Status April 8, 2011 RSC Meeting Haixin Huang.
Plan for 500 GeV Development Vadim, Mei. Goals 1.Explore polarization transmission to the 500 Gev CM energy. 2. Inspect the luminosity aspects (with 2.
Collimation Aspects for Crab Cavities? R. Assmann, CERN Thanks to Daniel Wollmann for presenting this talk on my behalf (criticism and complaints please.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Turnaround time in modern hadron colliders & store-length optimization
Fabio Follin Delphine Jacquet For the LHC operation team
Luminosity monitor and LHC operation
Operating IP8 at high luminosity in the HL-LHC era
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
M.Fitterer, A.Patapenka, A.Valishev (FNAL)
LHC Commissioning with Beam
Minimum Hardware Commissioning – Disclaimer
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
LHC schedule.
The LHC - Status Is COLD Is almost fully commissioned
Potential failure scenarios that can lead to very fast orbit changes and machine protection requirements for HL-LHC operation Daniel Wollmann with input.
-9:00: Test IP transverse adjustment (CMS) and optics verification.
MD2036: UFO dynamics studies and UFO fast detection
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Status of the BLHC ….work in progress! Mike Lamont CERN/AB 18/01/2008
Status of LHC Operations
Machine plans - Alignment workshop
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Intensity Evolution Estimate for LHC
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
LHCCWG Meeting R. Alemany, M. Lamont, S. Page
Week 35 – Technical Stop and Restart
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Friday morning 10:30 Optics measurements and corrections.
450 GeV Initial Commissioning with Pilot Beam - Beam Instrumentation
Overall commissioning strategy for protons (estd. 2005)
LHC Beam Operations Past, Present and Future
Summary Thursday h21: Stable beams fill #1303.
Machine plans - CMS startup workshop
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Collimators: Operations - Baseline Assumptions
Summary for LPC (March 7th, Ralph Assmann)
Monday :15 fill 3523 dumped by BPMs IP6
LHC Morning Meeting - G. Arduini
Another Immortal Fill….
Beam commissioning plans, 2007 and 2008
Presentation transcript:

Stefano Redaelli Beam Department - Operations Group Operational Aspects of the Phase II Crab Cavity System LHC-CC09 3 rd LHC Crab Cavity Workshop European Organization for Nuclear Research, CERN, Geneva, CH 16 th -18 th September 2009 Acknowledgments: R. Bailey, J. Tückmantel R. Calaga, R. Tomás, F. Zimmermann

S. Redaelli, LHC-CC /09/ Outline Introduction Commissioning baseline Strategy Procedures Crab cavity operation aspects Integration into LHC procedures Safe beam tests Conclusions

S. Redaelli, LHC-CC /09/ Scope - Introduction Scope of this presentation in the context of CC Phase II system: - Introduce/review beam commissioning procedures - Show the framework that the CC commissioning has to comply with - Identify main working areas - if possible - to establish safe commissioning procedures for the nominal operation - This talk does NOT provide detailed procedures The procedures for the LHC beam commissioning were established in preparation for the 7 TeV operation. Collective effort of OP team and system experts; first version by mid-2008 Since then, two things have changed: - HWC → MANY quenches are needed to train the dipoles (“training problem”) - Sep. 19 th event → Issue with the interconnections (“splice problem”) ⇒ New commissioning baseline for : 3.5 TeV → ~5 TeV. Nevertheless, for the Phase II system, the 7 TeV baseline is appropriate: - By ~2018 the high energy goal will be achieved. - The operating energy has actually a minor impact on the procedures

S. Redaelli, LHC-CC /09/ Overall commissioning strategy Hardware comm. Machine checkout Sector tests Global machine checkout Circulating beam commissioning 43 / 156 bunch operation 75ns, 50ns, 25ns operation Install Phase II collimation 25ns ops II LHC beam commissioning strategy: Staged approach to address efficiently machine complexity Physics runs at energy below 7 TeV, imposed by hardware (start with 2x3.5 TeV) Co-existence of HWC, checkout and sector tests before circulating beam commissioning Full machine checkout and machine protection commissioning AFTER first beam OP Stage A Stage B Stage C Three beam commissioning stages: ๏ Stage A→Simplest machine configuration (no crossing, moderate squeeze) ๏ Stage B→Up to intensity limit (fill pattern depends on experiment requests) ๏ Stage C→Towards nominal and ultimate performance 3.5 TeV 5 TeV 5+ TeV Phase II Crab: well into high performance goal of Stage C

S. Redaelli, LHC-CC /09/ Stage A - “early” physics runs Procedures for Stage A elaborated within the LHC Commissioning Working Group Put together operation team, commissioning team and “owners” of accelerator systems LHC Engineers in Charge and Commissioners responsible for the preparation Details worked out at the LHCCWG, then approval at the LTC Web-based documentation, strict approval of EDMS documents

S. Redaelli, LHC-CC /09/ Geography of Stage A phases 450 GeV 7 TeV A.1: First turn A.2: Circulating pilot A.3: Beam Instr. comm. A.4: Inj. optics checks A.5: Increase intensity A.6: Two beam operation A.7: 450 GeV collisions A.8: Energy Ramp A.9: 7 TeV optics A.10: Un-squeezed collisions A.11: β squeeze A.12: Detector magnets Addressed during 2008 beam commissioning

S. Redaelli, LHC-CC /09/ Flow chart Circulating beam Injection First turn 450GeV initia l 450GeV optics 450GeV Increase I Circulating beam Injection First turn 450GeV initial 450GeV optics 450GeV Increase I Top energy Collisions Pilot physics Ramp both beams Squeeze both beams 450GeV Collisions 450GeV 2 beams Beam 2 Beam 1 2 beams Experiment magnets OFF Dipoles OFF Snapback Ramp Top energy checks Snapback Ramp Top energy checks Squeeze

S. Redaelli, LHC-CC /09/ Flow chart - nominal operation Injection B1 450GeV optics 450GeV Increase I Injection B2 Physics Ramp both beams Squeeze both beams Clearly, we must go back to the commissioning flaw in case of major machine changes: - Intensity / energy steps - Changes of crossing schemes - Early re-commissioning -... Both CC Phase I and Phase II have to be considered “major machine changes” and therefore require: - full integration into existing procedures - dedicated commissioning time

S. Redaelli, LHC-CC /09/ Details: steps of commissioning phases

S. Redaelli, LHC-CC /09/ Ion commissioning procedures Commissioning plan elaborated by ion team. Specific aspects tackled separately: RF, BI, Collimation, protection, BLM quench thresholds Web documentation addresses specific ion aspects for each step: A similar approach is recommended for the crab-cavity commissioning procedures: You should prepare one document that presents consistently for each phase the specific aspects related to the commissioning with CC. A lot of detailed work is required - a few aspects will be mentioned in the following.

S. Redaelli, LHC-CC /09/ Outline Introduction Commissioning baseline Strategy Procedures Crab cavity operation aspects Integration into LHC procedures Safe beam tests Conclusions

S. Redaelli, LHC-CC /09/ Steps affected by CCs 450 GeV 7 TeV A.1: First turn A.2: Circulating pilot A.3: Beam Instr. comm. A.4: Inj. optics checks A.5: Increase intensity A.6: Two beam operation A.7: 450 GeV collisions A.8: Energy Ramp A.9: 7 TeV optics A.10: Un-squeezed collisions A.11: β squeeze A.12: Detector magnets Clearly, main tests done at top energy. But: we will have to profit from phases with SAFE beams to speed-up the commissioning. Cavities have to stay ON all the time with beam → All phase are affected. Here, focus on the main aspects...

S. Redaelli, LHC-CC /09/ Basic assumptions Assumed status of beam commissioning during CC Phase II: - We will master the all commissioning phases (inj→ramp→squeeze→collisions) - One or both beams available on request, multi-bunch operation fully under control. - Variety of commissioning beams available: pilot, intermediate, nominal; single/multi bunches Assumptions on SAFE beams: - ~ p at injection energy (updated after a few years of operation) - No beam is safe at 7 TeV - Will have experience on machine protection and collimators, but will still need to be very careful! Pre-requisites before starting for crab-cavity system: - Hardware commissioning without beam completed - Cavity conditioning completed - Basic controls verified (RF levels but also active mechanical alignment) - Detailed tests of RF loops and synchronization without beam - Crab cavities must be super-conducting before putting beam ! (see Joachim’s talk) - Established settings for first injection!!

S. Redaelli, LHC-CC /09/ First beam commissioning (A.3) Reference beam conditions at injection energy: - Both beams captured, optimized lifetime - Single bunches of a few x p, 450 GeV Requires commissioning steps for CC - Verification with beam of the basic controls - Status displays - Settings for RF levels, gain and phase adjustments - Pick-ups? - Initial beam commissioning of “standard” RF loops and tuning - Initial tests for de-tuning the cavities Needed as soon as possible!! - First tests of voltage ramp up over tens of turns - First scans of crab phase to find the zero field offset - Find minimum load position with local orbit bumps - Test the active remote mechanical alignment with beam, compare with orbit bump measurements Mountain range of first LHC captured beam

S. Redaelli, LHC-CC /09/ Detailed optics meas. at 450 GeV (A.4) CC → - Final commissioning of RF loops and synchronization with main RF - Detailed local measurements of aperture, orbit and optics - Commissioning of local orbit bumps and orbit feedback (200 μm!) - Commissioning with safe beams of the protection interlocks (local orbit, RF power,...) - Establishment of ramp settings to keep de-tuning! - Preliminary measurements of phase advance / closure of local crab-bump. Assess perturbations outside the local bump - Impedance measurements - Beam-based alignment of each cavity, establish reference with respect to the orbit measurements - Stability of crab performance! This is the phase we establish the reference beam conditions for ramp and physics: - Measurements/corrections of aperture, orbit, tunes, optics,... - Collimator settings - Preparation for energy ramp - Final RF commissioning with detailed optics knowledge

S. Redaelli, LHC-CC /09/ Increasing intensities (A.5) “Standard” RF check for multi-bunch operation: - Check synchronization with main RF. Re-commissioning loops and controls for multi-bunch operation. Review orbit stability with higher intensities. Check HOM loads for large number of bunches. Compare beam-based alignment from CC signal to multi-bunch orbit. Re-check the crab-bumps with multi-bunch operation. Detailed commissioning of protection mechanisms: - Establish interlock references (software); - Set-up collimation and protection systems. Clearly, detailed procedures must be established in preparation for un-safe beams! MP issues for Phase I discussed by Joerg!

S. Redaelli, LHC-CC /09/ Ramp and Squeeze (A.8-11) Crab-cavities must stay de-tuned all the time with beam in the machine, with RF power ON. ⇒ A “full” commissioning of the system must be completed before attempting the first ramp! - Even a pilot beam is un-safe at high energy!! - Special care has to be taken during squeeze: reduce aperture at highest energy! - Active control of phase, feedback with V=0 constrain all the time! Require detailed measurements during optics changes and corresponding corrections of - Local bumps - Betatron functions and phases at the cavity locations - Closure of crab bumps - Aperture,... Establish a procedure to ensure protection / collimation during squeeze. - Need to find optimized collimator settings during ramp and squeeze How to check in detail the de-tuning in all stages (change of En or of optics)?

S. Redaelli, LHC-CC /09/ Luminosity tuning and leveling Detailed procedure to be established, largely based on the Phase I experience. Define an optimum set of parameters for initial commissioning (number of bunches, I b, crossing angles, beta*,...) Assume that: - Luminosity optimization without crabbing is well established! - Reliable luminosity measurements available BUT: High risk: Need to define a set of SAFE conditions for tests. Little aperture margin available with squeezed beams + crossing. Already commented on the required beam tests even before CC installation... I see two additional possible options: 1. Collisions at lower energies 2. Anti-crab to REDUCE luminosity at top-energy WITHOUT crossing

S. Redaelli, LHC-CC /09/ Possible SAFER beam tests 1. Luminosity tuning at reduced beam energies. Establish a trade off between - Bunch length - Aperture: larger beam sizes vs crossing vs β * - Accuracy of absolute luminosity measurements L ~ cm -2 s -1 at 3.5 TeV, β* = 1 m, p x 156 bunches, no crossing 2. Use crab schemes to reduce luminosity at top energy - Squeezed beams with no crossing, head-on collisions. Nominal emittance. Larger aperture margin at the triplet without crossing - Up to 156 bunches per beam give enough luminosity for tests: L ~ 6 x cm -2 s -1 at 7 TeV, β* = 55cm, no crossing - What to do: - Scan crab bump an tune it to an “optimum” minimum/reduced luminosity value - Assess machine performance with (supposedly) closed local bumps in both IPs, in nominal top-energy conditions - Machine perturbations - Collimation - Operability, stability -... Clearly, the final validation must come from the proof that a POSITIVE luminosity gain can be achieved!

S. Redaelli, LHC-CC /09/ Conclusions The operation of crab cavities will be challenging - See also previous talks on MP aspects and safe beam tests The Crab Cavity system commissioning must be fully integrated into the LHC beam commissioning - General framework for the proton beam commissioning was presented - First - preliminary - attempt to integrate into existing procedure was started - Detailed procedures must be provided as a part of system approval! - Experience of beam operation will have to be taken into account From day-1, we will need a complete commissioning - Obvious for Phase II, but also for Phase I - To a large extent, what was presented applies to Phase I as well! We must prepare early on safe procedures - Phase I experience will be essential - Need to do as much as possible at low energies - Should start the luminosity “tuning” with safe beams: work out programs for meaningful tests at lower energies and/or with adequate aperture margins