LST Upgrade LST Upgrade Readiness Review William Sands, Princeton University, 5-5-2004.

Slides:



Advertisements
Similar presentations
CRIMPING Introduction
Advertisements

LST Mechanical Design Review Utility Routing, Cableways & Crate Locations Peter Kim October 21, 2003.
Module Assembly Update Ohio State University and Princeton University are presently preparing facilities for module assembly. Both universities are fabricating.
Muon EDR: Chamber design M2/3 R1/2 16/04/20031T.Schneider/LHCb Muon EDR 1.General description - AW read out -Cathode pad read out -HV supply 2.Details.
Installation. Indoor Unit Installation Typical Installation.
Click on this image to open the full PDF document.
Assembly Instructions Additional documents needed for Assembly: GA Drawings on all Units Header Platform GA Drawings Motor Deck Platform GA Drawing Packing.
TPC Proposal for the 35 Ton Liquid Argon Test Abstract We propose to equip the 35 ton cryostat with one APA and two CPA’s, and all the necessary equipment.
CMS ZDC Crane Emergency Payload Removal Procedures This document proposes the viability of using a portable hydraulic actuator Hand crane (Davit crane)
MINI BOX. STANDARD BOX MAGNUM BOX SPINDLE ASSEMBLY.
Observations and next works from the recent tests of the insertion tools of Mini-Drawers at CERN Roméo Bonnefoy and François Vazeille Tilecal Operation.
G.Barber Tracker Planning & Mechanical Preparation June Tracker Planning & Mechanical Preparation An outline of (known) outstanding work to be carried.
IFR-LST status report G. Cibinetto INFN Ferrara Babar Collaboration Meeting, Feb. 21, 2004 Milestones LST production status 1 st module assembled Princeton.
V. Carassiti - Princeton (USA) 9-13/01/ BABAR IFR UPGRADE DETECTOR ASSEMBLING AND MOUNTING.
RACKS AND CABLES Peter Kim SLAC LST Install Readiness Review May 5, 2004.
October 22, 2003H.J. Krebs1 LST Mechanical Design Review 2005 IR-2 Installation Discussion H.J. Krebs October 22, 2003.
BaBar: The Detector Richard F Boyce 21 October 2003.
2004 BRASS INSTALLATION HARDWARE. BRASS INSTALLATION FOR 2004 TOP AND BOTTOM SEXTANTS ONLY PROCEEDURE AND FIXTURES FOR TOP AND BOTTOM ARE SIMULAR.
May 5, 2004H.J. Krebs LST Installation Readiness Review 2004 IR-2 Installation Schedule H.J. Krebs May 5, 2004.
Daya Bay Muon Subsystem Review, 7/28-29/2007, IHEP, Beijing RPC Assembly Changguo Lu, Kirk McDonald, Bill Sands Princeton University (July 28, 2007)
October 22, 2003H.J. Krebs1 LST Mechanical Design Review Mechanical Installation Preparation H. James Krebs October 21, 2003.
October 22, 2003H.J. Krebs1 LST Mechanical Design Review 2004 IR-2 Installation Schedule H.J. Krebs October 22, 2003.
Installation. Indoor Unit Installation Typical Installation.
BaBar/LST Meeting Dec 8, 2003K. Honscheid, Ohio State University Module Assembly Quality Control High Voltage Ohio State Status Report.
Don Lynch 9/15/05 HBD Safety Review 1 Mechanical Design And Installation Hadron Blind Detector (HBD) Don Lynch.
7/28/03P. Kroon AEROGEL Assembly of Cells into 80-cell Array: –8 cells wide by 10 cells high mm high (Y) by 2077 mm wide (Z) by about 335 mm deep.
Purpose Power lines Equipment Assured Grounding GFCI Conclusion.
IFR End Door Enhancement Mechanical Engineering Status & Installation Issues H. James Krebs June 23, 2001.
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008.
C. Bromberg 1 Michigan State University Feb. 8, 2004 RPC Monolithic Detector l Most absorber shipped direct to the site äShipping minimized äHeavy (~20.
Installation. Indoor Unit Installation Typical Installation.
October 21, 2003H.J. Krebs1 LST Mechanical Design Review Handling & Installation Fixtures Design and Fabrication Status H.J. Krebs October 10, 2003.
26 April 2013 Immanuel Gfall (HEPHY Vienna) Belle II SVD Overview.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
Tariq J. Solaija, NCP Forward RPC EDR, Tariq Solaija Forward RPC EDR The Standard RPC for low  regions Tariq J. Solaija National Centre for.
The LST High Voltage System LST Readiness Review May 5, 2004 Klaus Honscheid Ohio State University.
11 SSD Power and Cooling on the Cone STAR Integration Workshop Howard Matis May 16, 2008 STAR Integration Workshop Howard Matis May 16, 2008.
11/15/02H.J. Krebs IFR Improvement Phase II (Barrel) Mechanical Engineering Issues H. James Krebs November 15, 2002.
16/04/20031PNPI / LHCb Muon EDR Wire Pad Chambers PNPI design for regions R4 in Stations M2,M3,M4  4 gas gaps of 5mm±70µm;  Active area: 1224x252.8 mm².
Test Tube Activities at Ohio State (8/5/03) Two (very useful) sub-group meetings after last weekly meeting –Mechanics (Bill, Lu, Mark, Jim, Charlie, Klaus)
VVS Prototype Construction at Fermilab Erik Ramberg 26 February,2002 Design issues for VVS Details of VVS prototype design Schedule and Budget Testing.
Long Bo for LAPD Hans Jostlein10/20/2011 December 15, 2015 Long Bo for LAPD 1.
Front End Board (16 channels) Superlayer Cross Section Frontend Enclosure HV cap board HV cap Board Signals from chamber wires go to HV cap board to be.
1 Jim Thomas - LBL A proposal to close the Grid Leak “it will never die” Yuri Fysiak, Jim Thomas & Gene VanBuren Eric Anderssen, Howard Wieman & Jon Wirth.
PHENIX WEEKLY PLANNING 3/23/06 Don Lynch. MPC Electronics MPC rack installed without cards. Cards to be installed As available and as access time is available.
Proposal for LST-based IFR barrel upgrade Roberto Calabrese Ferrara University Workshop on IFR replacement, SLAC, 11/14/2002.
CLAS12 Drift Chamber Prototyping
Assumptions: Cockcroft-Walton photomultiplier bases are the same for all ECAL sections Digital to analog converters are installed on the distribution boards.
LARP Collaboration Meeting Racetrack Coil Fabrication
MQXFB design, assembly plans & tooling at CERN J.C Perez On behalf of MQXF collaboration team MQXF Workshop on Structure, Alignment and Electrical QA.
LSTs in the IFR gaps Workshop on IFR replacement SLAC November 14, 2002 L. Piemontese INFN Ferrara.
FGT Magnet C Assembly metric tons (59 US tons) -100mm thick steel plates -6.6m high x 3.1m wide x 1m deep (outer dimensions) -5m high x 2.25m wide.
June 2, 2008 Bill Wisniewski1 BaBar Disassembly and Disposal Overview.
Comments on Services Elba Comments on Services & … Bill Wisniewski SLAC.
Test Tube Activities at Ohio State (7/29/03) Amphenol/Spectra Strip will send two 10 m long samples of signal cable –With a (round) jacket, shielding –20.
K.Long/G.Barber Mice Tracker Mechanical Status CM20 Feb 08 1 Mice Tracker Mechanical Status Contents:- Tracker 1 Status Tracker 2 Status Further Hardware.
Scorpion is a remote tester specifically designed for testing ASD systems. Scorpion is compatible with the FAAST aspirating smoke detector. It is particularly.
No Solder Battery Interrupter
Introduction BaBar Components The Problem IFR Upgrade: 2004 & 2005
Service channels between Tracker and PP1
BaBar LST Upgrade Mark Convery SLAC 13 Jun 07.
- STT LAYOUT - SECTOR F SECTOR A SECTOR B SECTOR E SECTOR D SECTOR C
BaBar IFR Upgrade Mark Convery SLAC 7 Jun 06.
LST Module Installation
Limited Streamer Tubes
RPC and LST at High Luminosity
Limited Streamer Tube Project Summary
Bunker Wall Design Wall ESS
Single Detector Design
Presentation transcript:

LST Upgrade LST Upgrade Readiness Review William Sands, Princeton University,

William R. Sands III,Princeton University, Installation Procedure Outline 1) Present Module Production A) Modules Completed B) Production Rate C) Projected Completion Date 2) Layer 18 Special Case A) Z Plane Installation B) Module Installation C) Utility Routing 3) Z Plane Installation A) Lower Sextant a) fixturing b) procedure B) Upper Sextant a) fixturing b) procedure C) Readout 5) Quality Control A) Overview B) Shift Time 6) Manpower A) One Shift B) Two Shifts 8) Safety 7) Conclusion 4) Module Installation A) Fixturing B) Procedure a) module insertion 1) lower sextant 2) upper sextant C) Utility Connections a) gas lines b) HV lines c) ground connections d) Phi readout

William R. Sands III,Princeton University, Present Module Production Modules are produced in 4 types an 8 cell 2 tube module (standard), an 8 cell 3 tube module, a 7 cell 2 tube module and a shorter 8 cell 2 tube for layer 18. Modules needed plus 15% for the top and bottom sextants are 138 standard modules, 14 8 cell 3 tube, 42 7 cell 2 tube and 24 layer 18 modules. Princeton University and Ohio State University share responsibility for module production. Princeton will provide 42 standard,14 3 tube, 24 layer 18 and 34 7 cell modules. OSU will provide 96 standard, and 32 7 cell modules. As of Princeton will have completed 42 standard tubes and 14 3 tube modules and move on to layer 18 modules these should take 6 days to produce. As of OSU will have produced 32 standard modules. At present Princeton is averaging 20 modules per week and OSU 16 per week. The smaller output by OSU is strictly due to space constraints.

William R. Sands III,Princeton University, Module Configuration Per Layer

William R. Sands III,Princeton University, Reference to Detector Areas

William R. Sands III,Princeton University, Layer 18 Special Case Layer 18 is a special case due to flux bars that capture the modules, because of this constraint layer 18 will be installed prior to the brass absorbers so that there is the longest available time for QC prior to it being trapped by the installation of the remaining layers. Layer 18 has a 200mm thick flux bar on the forward and backward end but only the forward flux bar can be removed which makes it necessary to rout all layer 18 utilities through the forward end. There are 4 slots in the flux bar for utility routing and although not designed for LST’s there is sufficient space for the utilities. Aside from the all the utilities being routed out the forward end, the Z plane and module installation will be done as explained in the general installation plan.

William R. Sands III,Princeton University, The cross section of the utility grooves in layer 18 is 15 mm by 100 mm as shown below.

William R. Sands III,Princeton University, Layer 18 Layer 18 resides behind the flux bar shown below in red and we are forced to run utilities thru existing grooves in the bar.

William R. Sands III,Princeton University, Layer 18 Without Flux Bars

William R. Sands III,Princeton University, Flux Bar

William R. Sands III,Princeton University, Internal conduit to place utilities for layer 18, conduits held in place with blind rivets.

William R. Sands III,Princeton University, Conduit is covered with second plate prior to flux bar installation.

William R. Sands III,Princeton University, Second plate extends up from flux bar to facilitate placement.

William R. Sands III,Princeton University, General Installation Z Planes Installation Z plane installation varies from the top sextant to the bottom sextant as does the Z plane itself. All module and Z plane insertion takes place at the forward end and in the bottom sextant there are obstructions making it impossible to install the Z planes as a single large sheet. The people at SLAC responsible for the Z plane fabrication have come up with a clever way of folding the plane on the bottom sextant to make installation possible.

William R. Sands III,Princeton University, Z Strip Configuration for Top and Bottom Sextant The Z-Strips are placed in each layer prior to the modules. The readout connectors straddle the center gap plate on the top and bottom sextants in the backward end.

William R. Sands III,Princeton University, Forward End Facing North The forward end where the Z-strips and modules are installed will have the corner plates and center gap plates removed. Full access to the layers in the forward end will allow for a much more controlled installation and is necessary to fit the Z-strips which are full width.

William R. Sands III,Princeton University, Forward End Facing East For installation of the bottom sextant we have some obstructions with the concrete pier and structural apparatus shown below. The pier is approximately 161” from the steel and points on the structure come as close as 60”. Installation of the Z planes is accomplished by folding the plane in 3 sections.

William R. Sands III,Princeton University, In the bottom sextant the Z planes can be installed by hand or using the RPC removal platform designed by Les Dittert, plan view shown below. The top sextant must use the LST adjustable removal apparatus along with another platform,shown on page 19, to allow the overhead crane to hoist the planes to the removal platform.

William R. Sands III,Princeton University, The tray is constructed from aluminum box tubing and plywood covered with mylar to reduce sliding friction.

William R. Sands III,Princeton University, Backward End Facing South From the backward end the Z-Strip readout and will exit the layers between the center gap plate and corner plates.

William R. Sands III,Princeton University, Angelo Cotta Ramusino,our electrical engineer from Ferrara, has come up with a scheme to attach the Z plane transition boards on to the center gap plate via a circuit board and copper strip in addition to some spade connectors for grounding other utilities. Z Readout

William R. Sands III,Princeton University, The copper ground bar and circuit extend the length of the gap plate picking up Z plane readouts from layer to layer.

William R. Sands III,Princeton University, General Installation Module Installation As with the Z planes the procedure for module installation is different for the top and bottom sextants. Again the RPC removal platform will be necessary for the top sextant installation. The bottom sextant in some areas can utilize a platform for holding multiple modules but due to the obstructions some have to be inserted individually. Utilities exit through the forward end and backward end with gas and phi readout exiting in the forward end and Z readout and high voltage exiting through the backward end. The utilities exit between the center gap plate and corner plate on the left and right. The modules are grouped in two halves in every layer where up to 5 modules will be feed from one gas input and output. Each module has one high voltage cable and two phi readout cables with the exception of the 3 tube modules which have 3 phi readout cables. Utilities are routed to the outer perimeter of the detector through “incremental conduits”. Conduits are sectioned to only take up space in already installed layers.

William R. Sands III,Princeton University, Installation Platform The installation platform can hold up to half the modules per layer. In the top sextant where there are no obstructions it can be loaded to capacity.

William R. Sands III,Princeton University, Example of incremental conduit installed on detector after modules are installed in individual layers have been installed. Weld studs are inserted into steel plates to hold conduit and cross pieces inside channels are for strain relief using cable ties. Yellow in layer slots represent brass absorber layers.

William R. Sands III,Princeton University, Pictured below is a phi transition board on a 3 tube module. The phi readouts exit through the forward end. The phi cable is connected to the transition board and routed to the conduit where it leaves the sextant.

William R. Sands III,Princeton University, Below is a 2 tube module with HV boxes and connecting strain relief. HV wires are stranded out of the bulk Kerpen cable and soldered to pc boards inside the HV boxes. The bulk cable is then attached to the stain relief with cable ties. strain relief HV box

William R. Sands III,Princeton University, High Voltage Cable Connector The high voltage connector was introduced so that during installation the entire HV cable didn’t have to be handled. Dave Warner, at Colorado State, was brought on to work on the HV connector design. The main criteria for the design is that they be as small in cross section as possible and sustain the required voltages with a reasonable margin of safety. Dave presented a design of two connectors one 11 pin and one 16 pin. The 11 pin connector is used for the 2 tube modules and the 16 pin connector is used for the 3 tube modules. The connectors reside outside the detector in an area where the HV cables leave the conduit. This area offers the required space needed, Peter Kim acknowledged that the space was available.

William R. Sands III,Princeton University, High voltage lines and boxes are connected to the modules at the forward end and the HV connector end of the cable is tethered and pulled through the layer gap. The HV lines must be guided as the modules are being pushed through the gap, once the modules are in place the HV line can be routed into the conduit.

William R. Sands III,Princeton University, Pin Connector Cross Section Female Connector Male Connecter

William R. Sands III,Princeton University, Grounding Scheme Horizontal spade connector Ground wires are run from individual utilities to vertical spade connectors riveted to a Cu clad board that connects all grounds on the board. Horizontal connecters can be accessed in the gap and will daisy chain modules together, up to 5 modules, and also connect to ground on the center gap plate. Vertical spade connector

William R. Sands III,Princeton University, Quality Control Quality control begins with handling of modules and they will be handled as carefully and as little as reasonable. As soon as possible after module installation they will be tested for High Voltage and gas integrity. An overnight test on readouts will be done with cosmics. If any problems are detected, replacement or if possible a fix will be the first priority on the next installation shift. Testing will continue as long as possible without interfering with installation.

William R. Sands III,Princeton University, Manpower Ohio State, Princeton, Colorado State and the Italian collaborators are presently in the queue for supplying personnel for installation along with SLAC crews for rigging and staging. There will be several people versed in all aspects of the installation that will act as shift managers as well as being part of the installation crew in all there should be upward of 20 people available. It is still to be determined if 2 installation shifts will be possible. Two shifts are only feasible if a layer on the top and subsequently a layer on the bottom can be done. It is unadvisable to do 2 consecutive layers prior to QC so the area will not be obstructed by the next layer’s cabling if there is a problem.

William R. Sands III,Princeton University, Daily Plan Each day in two shifts the plan is to install one layer or more if possible. A third quality control shift then comes on tests the modules each day. If a problem is found the first task the next day is to replace the faulty module and then move on to the next installations. It has been found that tube can sometimes be repaired, if this is the case the module will be used as a spare or installed in another sextant at a later date.

William R. Sands III,Princeton University, Safety Safety is a major concern for all involved. There are many aspects to this issue including overhead, electrical and fall protection. It is important that there are enough people for every operation and not too many to encumber the movements or egress of others. Along with SLAC safety personnel the shift managers and individual workers will pay considerable attention to safety issues.

William R. Sands III,Princeton University, Conclusion The module and Z plane installation will proceed in mid August. This is a huge undertaking and has been thoroughly thought out by many experienced people. Jim Krebs and his group are constructing a mock layer with all obstructions replicating a layer in the bottom sextant where the difficulty is highest. During the week of June 7 th an installation will be done in this mockup and plans will be tweaked and changes made if necessary.