Mu2e WGM R. Ray Mu2e Project Manager Sept. 14, 2012.

Slides:



Advertisements
Similar presentations
PAINLESS PERIODIC REVIEW Cynthia Steinhoff Anne Arundel Community College Arnold, Maryland.
Advertisements

Preparation of the Self-Study and Documentation
Mu2e WGM 2/22/2011 R. Ray Mu2e Project manager. CD-1 Our sole focus is on CD-1 and in particular, the Director’s Review scheduled for April 3-5. To be.
Mu2e WGM 6/15/2011 R. Ray Mu2e Project manager. Reviews We were on Lehman’s schedule for early August. We gave up that slot 2 weeks ago when it became.
Financial Systems Needs Assessment Project Update Monthly Research Administrators Meeting March 11, 2010.
FAC, 4/16/07 D. Schultz 1 e-Beams Systems Update People ARR Linac Installation Undulator Production MMF Operations David Schultz.
Iterative development and The Unified process
Process Engineer’s Role in Project Management Dr Abdullah Malik.
LSU 07/07/2004Communication1 Communication & Documentation Project Management Unit – Lecture 8.
MAC Committee Update Robert Kondziolka, MAC Chair.
Project X RD&D Plan Conventional Facilities (Civil Construction) Russ Alber AAC Meeting February 3, 2009.
Mu2e WGM 7/27/2011 R. Ray Mu2e Project manager. Director’s Review We have settled on date for the Director’s CD-1 Review; Oct Focus of review will.
Software Engineering Chapter 15 Construction Leads to Initial Operational Capability Fall 2001.
Mu2e WGM 9/15/2010 R. Ray Mu2e Project manager. L2 Systems and Managers R. Ray - Mu2e WGM2 1.2 Accelerator S. Werkema FNAL 1.3 Conventional Construction.
Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.
Mu2e Mu2e Status Andy Hocker, Technical Division All-Experimenters Meeting 8-JUN-2015.
1 BROOKHAVEN SCIENCE ASSOCIATES Plans for LOBs and Site Master Plan Martin Fallier, Conventional Facilities Division Director CFAC Review March 10-11,
 Coordinating construction related training  Following and gathering info for construction related performance measures  Follow Contract Modifications.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck Deputy Director (Project Management)
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Martin Fallier Director, Conventional Facilities Conventional Facilities Value and Risk Management May 8, 2008.
Delaware Health Benefit Exchange (HBE) Project Update Delaware Health Care Commission Meeting: March 28, 2013.
Lab-Wide Earned Value Management System Project Core Team Meeting October 01, 2008 Dean A. Hoffer/Elaine McCluskey.
NOvA Project Status April 3, 2007 John Cooper Ron Ray Nancy Grossman.
OFFICE OF SCIENCE 1 3. Cost Estimate Gines, Fisher 2.Are the estimated cost and proposed schedule ranges realistic, consistent with the technical and budgetary.
Copyright 2008 Introduction to Project Management, Second Edition 2  Many people have heard the following sayings: ◦ If you fail to plan, you plan to.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
12 GeV Upgrade Project Status Allison Lung Hall C Users Meeting Jefferson Lab January 18, 2008.
P5 and the HEP Program A. Seiden Fermilab June 2, 2003.
Executive Session Director’s CD-1 Review of the Mu2e Project April 3, 2012 Elaine McCluskey.
LBNE Working Group Meeting December 20, :00– 5:00 PM Snake Pit.
Mu2e Cost and Schedule Ron Ray Mu2e Project manager Fermilab PAC Meeting November 3-4, 2008.
Objectives: Develop a solution to either enhance or replace the FasTrak tool Scope/Why is this important?: Increase the transparency for issues that are.
7/26/2006 Wyatt Merritt 1 DECam CD1 Documentation DOE Critical Decision Process Documentation Requirements.
Commodity Node Procurement Process Task Force: Status Stephen Wolbers Run 2 Computing Review September 13, 2005.
Fermilab Presentation Greg Bock, Pepin Carolan, Mike Lindgren, Elaine McCluskey 2014 SC PM Workshop July 2014.
Chapter II: 9-Step Proposal Process: An Overview.
Fall 2015 ECEn 490 Lecture #8 1 Effective Presentations How to communicate effectively with your audience.
Activities and news Last meeting: 2015 CERN budget allocations as expected, now distributed on accounts Annual report done, and MTP (Medium Term Plan)
Plan of work is the general scheduling of program according to major activities (or phases) such as planning, implementation and evaluation.
DOE Stanford Site Office Office of Science U.S. Department of Energy 1 U.S. Department of Energy’s Office of Science Office of Science Review of the LCLS.
DUSEL Beamline Working Group Meeting March 09, :00 AM – Snake Pit (WH2NE) By Dean Hoffer - OPMO.
1 Integration and Milestones Elton Smith Hall D Detector Review October 20-22, 2004.
OFFICE OF SCIENCE 1 Closeout Report on the DOE/SC CD-3b Review of the Utilities Upgrade Project (UUP) Fermi National Accelerator Laboratory August 11-12,
HNSciCloud Pre-Commercial Procurement Project Procurement Framework and Schedule Dante Gregorio CERN 26 January
NOvA Project Status February 6, 2007 John Cooper Ron Ray Nancy Grossman.
Project X Working Group Meeting January 15, :00 PM Snake Pit.
Closeout Report on the Review Committee (CD-1) for the Long Baseline Neutrino Experiment (LBNE) Project at Fermi National Accelerator Laboratory October.
Lead from the front Texas Nodal 1 Early Delivery System Testing Environments & Planning – Involving Market Participants TPTF May.
DOE Review of LARP – Feb 17-18, 2014 DOE Critical Decision Process Ruben Carcagno February 17,
CONDUCTING BUSINESS WITH THE TOWN OF MIAMI LAKES Construction Services October 28, 2013.
Executive Session Director’s Conceptual Design Review of Mu2e Project May 3-5, 2011 Jim Yeck.
EMIS Chapter 5 Much of Chap 5 and 6 varies depending on the contract type. Two major types are important so we’ll digress to Contracting 101 for.
OFFICE OF SCIENCE DOE/SC CD-3c Review of the Muon to Electron Conversion Experiment (Mu2e) Project Fermi National Accelerator Laboratory June 14-16, 2016.
Director’s Progress Review Closeout Meeting
Preparation of the Self-Study and Documentation
Head, Office of Project Management Oversight (OPMO)
Project Management W. J. Foyt
Reconstruction site Investigation, Planning, Scheduling, Estimating and Design Eng. Fahmi Tarazi.
Contracting Officer Podcast Slides
Support Structure Fabrication
LCLS Linac Technical Design Review Charge
Director’s Progress Review Closeout Meeting
Linking assurance and enhancement
[Project Name] Post-Mortem Presentation Template
NSS Instrument Project Tollgate Coordinator
CONVENTIONAL FACILITIES LCLS Office Space Procurement
CMGC Overview SLAC Site Plan Systems Description Construction Schedule
East Hall under construction
PLAN OF WORK Plan of work is the general scheduling of program according to major activities (or phases) such as planning, implementation and evaluation.
Presentation transcript:

Mu2e WGM R. Ray Mu2e Project Manager Sept. 14, 2012

DOE Mini-Review Currently scheduled for afternoon of Oct 16.  Schedule is tight to be ready by then. Will decide by 9/24 to go with this date or move back by a week or two. To be ready for the review we have to  Update RLS  Respond to Recommendations from Review targeted at mini Review. 7/3/12R. Ray - Mu2e WGM2

Recommendations Prepare at least one of the initial solenoid specification packages by the next mini review.  We will have 4 specification packages for the solenoid conductor by the review. Two are complete now and are on the street for bids. By the time of the review the bids will be back for 1 and the other 3 will be on the street. Prepare an initial plan for contract/procurement oversight of vendors by the next mini review.  Joe Collins working on this. Draft expected in a week. Explore the possibility of early procurement of superconductor by the next mini review.  This is now our baseline plan that is already being executed. Consider the possibility of initiating practice PS and DS coil winding by additional vendors and the lab by the next mini review.  Our plan has always been to qualify a second vendor. 7/3/12R. Ray - Mu2e WGM3

Recommendations Consider reducing the duration between preliminary design completion and final design start to support AE team continuity (evaluate within 3 months after CD-1 approval).  Done. Currently evaluating A&E firms. Consider accelerating the start of civil construction to take advantage of the recent aggressive construction market conditions (evaluate within 3 months after CD-1 approval).  Still working on this. Concern is how quickly we can be ready for CD-2, which will be required before we can break ground on the detector hall. Evaluate procuring the solenoids earlier. A draft procurement plan should be presented at a mini-review in 3 months for early procurement of the superconducting cable.  Solenoid schedule has been accelerated. Draft of the procurement plan exists. Needs a bit more work and is being put forward as a template for the lab. More importantly, the first phase of the plan is already being executed. 7/3/12R. Ray - Mu2e WGM4

Recommendations Prepare a detailed make/buy analysis for the solenoids before the next mini review.  Work being done on this front (see Mike’s talk). Will have a draft document by the time of the mini review. 7/3/12R. Ray - Mu2e WGM5

Recommendations To summarize: to satisfy the recommendations we still need  Contract/procurement oversight plan.  Understand potential for acceleration of civil construction  Finish solenoid conductor procurement plan  Finish make/buy draft document 7/3/12R. Ray - Mu2e WGM6

RLS Updates Many changes to the RLS are underway Changes to tailoring strategy  CD-3a prior to CD-2 for conductor  CD-2/3b for project baseline/civil construction o Still don’t completely understand this one o Requires site prep work, currently in a GPP scheduled for FY15, to be advanced.  CD-3c for solenoid construction and everything else that is ready o Will base this one off of the solenoids and will not wait for anything else  Possibly a CD-3d for everything that’s not ready for CD-3c Incorporated a standard set of procurement activities for all procurements over $100k.  Currently going through each procurement and validating the schedule logic RLS updates always take longer than expected. 7/3/12R. Ray - Mu2e WGM7

Schedule – New CD-3a 7/3/12R. Ray - Mu2e WGM8

Schedule – Accelerate Civil 7/3/12R. Ray - Mu2e WGM9 Detector hall can be ready. Not convinced we can be ready for CD-2. Need CD-2 to get CD-3 for building.

Solenoid Acquisition Oversight Committee It was suggested that we form a committee to advise the Project Manager about issues related to the acquisition of the solenoids. Idea endorsed by DOE. Should speed up approvals down the lone. We have a draft charge and a list of names for potential membership. Will forward charge and list of names to DOE (Bruce Strauss,Ted, Pepin, Paul) for comment and for suggestions of additional names. Will then proceed to form the Committee. Hope to have this in place by the mini review, though it is not required. 7/3/12R. Ray - Mu2e WGM10

Procurement Review As follow up to last month’s Procurement Review, Carl has formed a steering committee to address the recommendations. Doug is representing Mu2e on this committee One suggestion is to have a common format for Advanced Procurement Plans (APPs). We have written a draft APP for the solenoid conductor as a starting point. We have examples from other labs that vary considerably in form and content I think the audience for these are:  Procurement Department  Lab  DOE (FSO and in some cases Chicago Operations) 7/3/12R. Ray - Mu2e WGM11

Action Items Ted will work with Lehman’s Office to schedule the mini review sometime after October 1.  Done Ted to get clarification from Lehman’s office on what was meant by the recommendation of accelerating the start of civil construction.  Not sure we addressed this explicitly but we believe we understand the ground rules at this point. Ron/Doug to talk with similar type project outside of Fermilab on Procurement Support (FTEs) needs and how they estimated those needs.  Still to be done. 7/3/12R. Ray - Mu2e WGM12