31.08.2005LHCOP / SPS Cycling for LHC1 SPS cycling for LHC injection J. Wenninger AB/OP Introduction to the timing system. Timing and settings constraints.

Slides:



Advertisements
Similar presentations
Accelerator Complex Status P. Collier. Linac2, Booster and PS Startup on-time, according to the schedule. Only minor problems Rapidly set-up the major.
Advertisements

8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
PIP and the Booster Notch Bob Zwaska October 12, 2011 PIP Meeting.
Day ● 09:00-14:00: Collimation setup 3.5 TeV – Slowed down by losses induced by tune hump. – 48 collimators set up. – Beam dumped by ATLAS during.
Preliminary results and ideas for the SPS upgrade MDs on LHC beams in 2011 G. Rumolo on behalf of all the MD team (Elena, Thomas, Karel, Christina, Holger,
BEAM PREPARATION IN INJECTORS AND BEAM CHARACTERISTICS K.Cornelis BE-OP-SPS.
January 2006Beam dump and injection inhibits / J.Wenninger1 Beam Dump and Injection Inhibits J. Wenninger AB-OP & D. Macina TS-LEA LHC experiments signals.
Production of a Safe Drive Beam The Drive Beam pulse Which bunch goes where How to get rid of undesired bunches General Principle Operational Scenarios.
V. Kain, G.H. Hemelsoet AB/OP1Nov 08, 2007 LHC Injection System V.Kain, G.H. Hemelsoet, AB/OP Input from: E. Carlier, B. Goddard, J. Wenninger What do.
LHC beams in the SPS in 2014 H. Bartosik, G. Rumolo, G. Iadarola With the help from K. Kornelis, V. Kain and SPS OP crew.
Timing upgrades after LS1 Jean-Claude BAU BE-CO-HT1.
07-JUL-2003LEADE / JW1 Satellite bunches in the LHC Satellite “definition” Satellite luminosity Satellite detection & tolerances J. Wenninger AB/OP.
CONTENT: Beam characteristics and parameters Filling schemes Operational settings OP procedure and COLL setting Planning Shift breakdown To define the.
23/08/20081 RBI.816 Operation First aid on RBI.816 converter control J. Wenninger.
Friday to Saturday 02:00: Machine closed. 09:00: Cryogenics all OK. Preparing pre-cycle. 10:00: Pre-cycle started. 11:30: Pre-cycle finished. 14:00: Beam.
1 Interlock logic for LHC injection: intensity limitations Jörg Wenninger AB-OP-SPS Outcome of the join Machine-Experiments Workshop on Machine Protection.
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
0 1 Alternative Options in the Injectors – Preliminary Summary H. Damerau LIU-TM#8 18 October 2013 Many thanks for discussions and input to T. Argyropoulos,
SPS Timing. Outline Timing table Modes of operation Mode switch mechanism External events Creating a timing table Timing event cleaning.
FGC Upgrades in the SPS V. Kain, S. Cettour Cave, S. Page, J.C. Bau, OP/SPS April
1 LTC Timing AB/CO/HT Central timing hardware layout Telegrams and events Postmortem, XPOC LHC Central Timing API Fill the LHC Use Case Julian Lewis.
R. Assmann - LHCCWG Two Beam Operation R.W. Aßmann LHCCWG Acknowledgements to W. Herr, V. Previtali, A. Butterworth, P. Baudrenghien, J. Uythoven,
Nominal intensity bunches ● First ramp with nominal intensity bunches suffered from an instability appearing around 1.8 TeV. ● Nominal intensity bunches.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
00:15: Stable beams fill 1883, 1.1E33 cm-2s-1.  Seems the 144 bunches beam 1 doe not fit properly on the injection kicker waveform. Systematically the.
NA61 11 October 2010Light Ion for NA61/ S. Maury1 Light Ion in SPS Foreseen to have primary Ar beam physics in 2012 Nothing runs in 2012 NA61 duty cycle.
‘Review’ of the machine protection system in the SPS 1 J. Wenninger BE-OP SPS MPS - ATOP 09.
Content  The LHC beams produced  LINAC2 & PSB  The PS  The SPS  Super Cycles and N0n-LHC physics  Conclusions IEFC Workshop, 8 March 2012 Rende.
LHC Injection Sequencing MD 16/23/2009 Injection sequencing / BCM R, Giachino, B. Goddard, (D. Jacquet), V. Kain, M. Meddahi, J. Wenninger.
SPS proton beam for AWAKE E. Shaposhnikova 13 th AWAKE PEB Meeting With contributions from T. Argyropoulos, T. Bohl, H. Bartosik, S. Cettour.
CERN Timing Overview CERN timing overview and our future plans with White Rabbit Jean-Claude BAU – CERN – 22 March
1 Machine considerations and constraints for the Safe Injection Flag and Safe Beam Flag Jörg Wenninger AB-OP-SPS Introduction to ‘injection flags’ Machine.
Filling Schemes for the 2010 Heavy Ion Run Updated (3 rd iteration) version of BCWG presentation initially on 28 September, updated after discussions with.
ELENA: Commissioning & operation ELENA beam commissioning Operation 12/11/2015T.Eriksson CERN BE/OP/AD1.
Injection and protection W.Bartmann, C.Bracco, B.Goddard, V.Kain, M.Meddahi, V.Mertens, A.Nord, J.Uythoven, J.Wenninger, OP, BI, CO, ABP, collimation,
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
LHC 8 & 9 May :10: Injection kicker B1 faulty on oil level –Check in UA and RA. Leaks fixed, to be further checked in TS1 10:30: Pre-cycle started.
CO Timing Review: The OP Requirements R. Steerenberg on behalf of AB/OP Prepared with the help of: M. Albert, R. Alemany-Fernandez, T. Eriksson, G. Metral,
Guy Crockford, BE/OP/LHC, CERN WAO 2012 Automation in the SPS and LHC and its effect on operator skills The past 20 years have seen great advances in the.
Thursday 20 th April 01:53 RCBV17.R7B2 tripped as happened few days ago: SIS intercepted. 05:54 Stable beams, 1380b, still RF problems B1, abort gap cleaning.
© 2001 By Default! A Free sample background from Slide 1 Controls for LEIR AB/CO Technical Committee - 18 th March 2004.
ELENA RF Manipulations S. Hancock. Apart from debunching before and rebunching after cooling, the principal role of the rf is to decelerate the beam and.
Summary of ions measurements in 2015 and priorities for 2016 studies E. Shaposhnikova 3/02/2016 Based on input from H. Bartosik, T. Bohl, B. Goddard, V.
HP-PS beam acceleration and machine circumference A.LachaizeLAGUNA-LBNO General meeting Paris 18/09/13 On behalf of HP-PS design team.
SPS availability K. Cornelis Acknowledgments : A. Rey and J. Fleuret.
1 Synchronization and Sequencing for high level applications Julian Lewis AB/CO/HT.
SPS Applications Software issues - startup in 2006 and legacy problems
DRY RUNS 2015 Status and program of the Dry Runs in 2015
About Interlocks, Timing Systems and how to send SPS beams to the LHC
Alternative/complementary Possibilities
SLS Timing Master Timo Korhonen, PSI.
Machine Coordinators: G. Arduini, J. Wenninger
SPS extraction, transfer lines, injection
Saturday 21st April 00:33 Interlock during ramp on BLM HV
High Radiation to Materials 16th Project Team Meeting – May 20, 2010
Summary Friday h38: Ramp down and pre-cycle.
New AD Production Beam in the PSB
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
LHC Morning Meeting - G. Arduini
LHCCWG Meeting R. Alemany, M. Lamont, S. Page
Interlocking of CNGS (and other high intensity beams) at the SPS
Dry Run 0 Week 13: BI test of...everything circulating beam: all fixed displays and BI applications OP directories for 2009, concentrators running Need.
Beam Interlocks for Detectors and Movable Devices
Interlocking strategy
New page for summary of test status
Thu :00 Dumped beams, refill for Pb-Pb physics. No more protons in 2011… Some changes: Increase of flat top total voltage to 14 MV. Feed-forward.
Feedbacks & Stabilization Getting them going
LHC An LHC OP guide… under construction J. Wenninger
Presentation transcript:

LHCOP / SPS Cycling for LHC1 SPS cycling for LHC injection J. Wenninger AB/OP Introduction to the timing system. Timing and settings constraints at the SPS. 2-cycle filling scheme. 1-cycle filling scheme. From discussions with J. Lewis, M. Jonker, L. Jensen, M. Lamont and others…

LHCOP / SPS Cycling for LHC2 Timing system / 1  The machine timing is orchestrated by the CBCM (Central Beam and Cycle Manager) which consists of a group of MTGs (1 / machine).  The CBCM is working with ‘Beams’ :  A beam (timing system definition) is a a group of cycles in the various machines that have to be executed in sequence to produce a meaningful output, i.e. a ‘real beam’.  Not all beams involve all machines, some only involve the booster (ISOLDE) or booster and PS (East Hall, AD, nTof). SPS PS Booster 1.2s 3.6s 21.6s (or more) the LHC beam as defined by the timing system involves booster, PS and SPS cycles

LHCOP / SPS Cycling for LHC3 Timing system / 2  Normal / Spare :  A spare beam is associated to every (main) beam.  Before executing the (main) beam (i.e. cycle sequence) the CBCM verifies that the beam can be produced (no external interlock conditions). If there is no problem we are in the ‘Normal’ situation and the beam is executed.  If the beam cannot be executed, then a set of spare beams are tested. If the tests are OK, the ‘Spare’ beam is executed.  If the tests fail on the ‘Spare beam’, the ‘Spare beam’ is executed, but with the beam cutoff in the Linac.  For the SPS the Spare beam is used for the economy mode !

LHCOP / SPS Cycling for LHC4 Timing sequences / 1  The BCD (Beam Coordination Diagram) encapsulates all the beam information.  Includes one or more SPS beams (FT, CNGS, LHC) as well as booster / PS beams that are run while the SPS is accelerating, extracting….  A BCD Sequence (Timing Sequence) is a collection of BCDs organized to perform certain tasks. If the SPS is involved, the BCD sequence is always composed of : Lead-in BCD that executes the pulse start (once). Repetitive BCD that executes the SPS beam / super-cycle. For coast-able cycles : repetitive BCD that runs the coast. Lead-out BCD that executes the pulse stop (once).  The transition from one BCD to the next can be automatic (sequence change, EDF interlocks…) or manual (pulse stop command for SPS, coast start & end…).

LHCOP / SPS Cycling for LHC5 Timing sequences / 2  A number of sequences can be loaded into the CBCM at the same time.  Switching from one sequence to the next is fast (if they are ready).  For the SPS the timing system will automatically execute a Lead-out / pulse stop and Lead-in / pulse start. Note that EVERYTIME we change timing sequence, the SPS will execute a pulse-stop and a pulse-start (since cycles may start at 14 or 26 GeV).  The pulse-stop / -start takes ~ 30 seconds, and is not a significant overhead.  Our 2004 experience with this timing system :  A significant delay (sometimes it was the dominant delay) during SPS super- cycle changes is due to the lengthy editing of the BCDs, because the CPS crews have to copy lot’s of beams back and forth.  OP (CPS & SPS sides) is requesting some changes to the BCD editor to simplify life.

LHCOP / SPS Cycling for LHC6 Users  The timing system associates to each cycle a USER  the cycle identifier.  The user information is sent out over telegrams every BP (Basic Period = 1.2 s).  In addition to the PRESENT user, the telegrams also indicate the NEXT user.  For the CPS this concept is reasonable given the short cycle lengths (up to 3 BPs).  At the SPS this has drastic consequences since the timing system decides one cycle ahead what cycle to play NEXT !!  Since at the SPS no system is using the NEXT information (the old SPS timing system did not have this concept) a way out is to decide that at the SPS the next info becomes available only a few seconds (tbd) before the NEXT cycle starts.  In 2006 the user information will also be included in each timing event, because the system is ambiguous at the SPS – clients may not be able to decide if they should use the PRESENT or NEXT user tag of the telegram :  Some events arrive before the start of the (magnetic) cycle. For example : the injection kickers use events that arrive 1000 ms before each injection.  for the first injection they must take the NEXT user, for the others the PRESENT user !  Within a super-cycle, the SPS cycles are not aligned to the BPs.

LHCOP / SPS Cycling for LHC7 Destinations  Each beam is associated to a DESTINATION, an information that is also distributed by the timing system.  Possible LHC beam destinations : SPS dump  no extraction. LHC ring 1. TI2 TED(s). LHC ring 2. TI8 TED(s).  The destination can be set DURING the cycle (but asap of course) : At cycle start it will be ‘SPS dump’ or ‘unknow’.  The information on the destination can be used to generate selected timing events, either centrally by the MTG or locally in the CTRs (Timing Receivers).  selective generation of extraction events.  The SW interlock system can send information (external conditions) to the CBCM to inhibit a given destination. Example : if the TEDs are not IN, TED destinations are not allowed !

8 Cycle timings : booster to SPS Timing of booster, PS and SPS cycles for the nominal LHC cycle (BP = 1.2s)  The beam for the NEXT cycle is already injected into the booster before the PRESENT beam is extracted from the SPS.  If we decide that we do not want the NEXT beam in the LHC or do not decide on time, we have to get rid of it somewhere (D3, SPS dump…) as reliably as possible.  The (PS) RF system must know the ring & bucket number ~ ten’s of ms before extraction from the PS.

9 SPS timing events  The first SPS timing event of a cycle arrives 3000 ms before beam is injected (which coincides with start cycle). This event is used by BDI (wire scanners). Other event groups arrive ~ 1000 ms before beam injection (kickers & BDI).  In this example, we must have already taken the decision what cycle to play before the beam is even extracted to the LHC (unless we pad the beam out with 2-3 BP where we just wait… - see later).

LHCOP / SPS Cycling for LHC10 SPS settings for LHC beams / 1  Up to now we always used the SAME super-cycles for all LHC beams (pilot, intermediate, nominal…).  But the settings for those beams are not identical. Differences are due to :  Injector (PS) :  Steering of TT2/TT10  extraction from PS  injection oscillations.  Momentum at injection  RF / extraction from PS  RF capture.  RF – 3 very critical parameters :  Injection phase.  Injection bucket.  Phase loop sampling.  SPS ring :  Momentum at injection (see ‘injector’).  Tune (corrective trims for high intensity – mostly injection FB).  Chromaticity (~ +10 higher for nominal).  Reference points in the trim history (SPS ring) & manual changes (RF & TT2/10 steering) are used so far to handle beam changes.

LHCOP / SPS Cycling for LHC11 SPS settings for LHC beams / 2  For 2006 we are considering (G. Arduini, L Normann & JW) the following changes:  A dedicated cycle for each beam:  No need to go back and forth in the trim history, which is not compatible with ‘faster’ cycling.  More cycles to maintain – but the SPS is very stable (even over years) ! Only the orbit maintenance will be a bit more tricky.  Faster ramp  reduce cycle lengths:  Might increase the ramp rate in the central part of the ramp by a factor 2. If the RF ‘allows’ it !  Maintain a slow ramp start  Q and Q’ control and measurement.

LHCOP / SPS Cycling for LHC12 LHC filling – general issues  Master of the ship :  LHC is master whenever beam is send to the LHC.  SPS is master for MDs, TL setup (up to the dumps), machine checkout…  Must foresee a (simple) mechanism of ‘mastership transfer’ and destination change’.  Beam destination & delays :  To use the beam of a given cycle, the beam destination must be known in time.  The CBCM delay depends on cycling details – see later.  PS RF system must be informed (bucket & ring) ~ 10 ms before extraction (re-phasing).  If the CBCM is not informed in time – i.e. does not know what to do - it should help us prepare a ‘graceful abort’ of whatever beam that may be in the SPS :  Hold back extraction events (extraction permit generation & PC pulsing).  Send out automatic SPS dump timing events.

LHCOP / SPS Cycling for LHC13 LHC filling / 1 Possible LHC filling ‘sequence’ : 1.The LHC injection sequencer requests a beam from the CBCM. Either the sequence of batches/buckets/rings is pre-loaded, and the injection sequencer requests the NEXT shot and the CBCM knows what it has to do… Or the injection sequencer has to send the batch/bucket/ring ring info to the CBCM. In addition the RF must be informed about bucket # and ring. It must be informed some 10’s of milliseconds BEFORE extraction from the PS for re-phasing. 2.The required batches are injected into the SPS, and accelerated to 450 GeV. An interlock on the DC beam intensity in the SPS ring can ensure that the intensity does not exceed the requested intensity range. The interlock is activated just after the start of the ramp, and the beam is dumped in the SPS if limits are exceeded. 3.At 450 GeV the bunch length is shortened to fit into LHC buckets. The tails will probably be scraped in the SPS. The beam will be at 450 GeV between 0.5 to 1 second (EDF $).

LHCOP / SPS Cycling for LHC14 LHC filling / 2 5.Quality interlocks will be applied (some time) : Beam structure (number of bunches, bunch population spread…) (BDI/fast BCT). Bucket number (RF). Bunch length (RF) and transverse emittance (BDI) – provided we ever get fast measurements…. Since available time is very short, CRITICAL quality interlocks should be generated in the front-ends and connected to the SPS ring beam dump. A CRITICAL quality interlock condition will lead to a beam dump in the SPS before extraction. 6.If there is no hardware interlock from the transfer lines, the LHC injection and the LHC itself (BIC systems), the beam is extracted to the LHC. Only the extraction (and possibly transfer line) corresponding to the destination ring must be pulsing. 7.A ‘task’ must verify that the beam arrived in the LHC. Tests are time-critical if we do not want to miss the next cycle – maximum acceptable delay ~1 second… In the early days this delay may be much longer : manual checks by the OP crew !!! 7.Depending on the outcome of the test: Request next beam. Retry (beam did not leave the SPS…). Pause ? Abort ? If no decision is made in time for the CBCM, the next beam must be aborted somewhere along the injector chain. The sooner the better, since less intensity/energy = less radiation.

LHCOP / SPS Cycling for LHC15 SPS settings & cycles Let us consider two possible options : 1.One SPS cycle that holds SPS ring, TI2 and TI8 settings. 2.Two SPS cycles:  One cycle for LHC ring 1 filling with SPS ring, LSS6 extraction & TI2 settings. The LSS4 bumpers are not pulsed, the LSS4 kickers are not charged. TT40 (including septum) & TI8 may or may not be pulsed.  Another cycle for LHC ring 2 filling with SPS ring, LSS4 extraction & TI8 settings. The LSS6 bumpers are not pulsed, the LSS6 kickers are not charged. TT60 (including septum) and TI2 may or may not be pulsed.  Internally both cycles refer to the same SPS ring settings to avoid problems with duplicate settings. Ensures that when we change one cycle, the other follows immediately (  settings download !).

LHCOP / SPS Cycling for LHC16 2-cycle-option / 1 Consider the option with 2 cycles, one for filling ring1, one for filling ring 2.  We can use the NORMAL/SPARE mechanism to define a beam where:  NORMAL corresponds to the ring1-cycle.  SPARE corresponds to the ring2-cycle.  no delays from pulse stop / start.  The CBCM can, based on its external conditions (includes sequencer requests), switch between the 2 beams.  We are sure that only one extraction is pulsing. We do not need separate timing events for the 2 extractions.  For the timing system, the decision on the destination must obviously be taken before the first SPS timing event is issued, i.e. > 3000 ms before a ring1(2) cycle starts executing.

17 2-cycle-option / 2  To ease our life we can ‘pad’ (lengthen) the end of the cycle with n BPs (n=2 to 3) :  Gives us margin to decide after the extraction what comes next.  The cycle length increases by (2-3)×1.2/21  10-20%. Note that such a longer cycle has some OP advantages too, because we avoid the effect of eddy currents during the injection plateau (why we used a 28.8 s cycle [+6 BPs !] in 2004).  For J. Lewis, those BPs should ideally be part of a SEPARATE cycle. This is due to his logic where the NEXT cycle is already defined when a cycle starts executing. This could be an acceptable option for the first year(s).

LHCOP / SPS Cycling for LHC18 2-cycle-option / 1  Issues :  TO accommodate the ECONOMY cycle, we can build a separate sequence/cycle of the same length where the SPS is ‘off’.  Implies a sequence change in order to go to ECONOMY.  The same solution must probably be applied in the future for complex cycles involving FT, CNGS and MD beams…  more than one ECONOMY mode !  If the decision comes late and we have beam in the SPS  must prevent extraction :  Automatic beam dump event.  SW and/or quality interlocks on extraction.  The poor-man’s variant of the 2-cycles option :  We define a super-cycle with the cycles for ring 1 and ring 2 one after another.  Then the ring order is ‘fixed’ which will introduce delays whenever we change the order (ring1/2) …  Very simple scheme.  We still have to decide if we want a given beam, and ensure we get rid of it properly if not !

LHCOP / SPS Cycling for LHC19 1-cycle-option / 1 Consider the option with a single cycle.  We use a mechanism similar to ECONOMY to pulse the extractions to ring1 or to ring2:  By default the PCs are ‘flat’.  Extraction events (PCs, interlocks) are generated according to the beam destination either for LSS4/TI8 or LSS6/TI2. The events can be generated during the FB.  By default, i.e. if the CBCM receives no ‘request’, the destination is set to ‘SPS dump’ and NONE of the two extractions is pulsed. Machine-protection-wise this is rather nice ! Any beam that still makes it into the SPS will not be extracted, but dumped at the end of the cycle.  Requires different timing events for ring 1 & ring 2 extractions.  Decision on the destination can be taken later than in the previous scheme :  RF requires the info ~ 10’s ms before injection into the SPS  this is the HARD LIMIT.  CBCM requires the information during injection FB.

LHCOP / SPS Cycling for LHC20 Conclusions  The options have been discussed with J. Lewis, M. Jonker and M. Lamont.  Our tentative conclusions was :  Both options would work.  We should keep both options open.  The 1-cycle option with event generation based on the beam destination is better in terms of efficiency since the delays are more ‘relaxed’.  Some timing system ‘features’ (mostly the definition of NEXT user) are not suited for the long SPS cycles:  Should push to revisit this concept for the SPS.  Next : work out the details and verify that we have not missed a critical item.