Genesee County Road Commission Fred Peivandi, P.E. County Highway Engineer MTPA July 15, 2011 TIP Project Administration.

Slides:



Advertisements
Similar presentations
1 CLIENT CONSULTANT AGREEMENT. 2 Negotiations Types of Consulting Contracts Standard Form of Contract Form of Contract General Conditions Special Conditions.
Advertisements

Project Estimates There are two types of estimates 1Partial Payment Estimate 2Final Payment Estimate.
Metro Muncipal Agreement Program
USDA - RURAL DEVELOPMENT
Roles & Responsibilities in Construction Management
TQM Study in Royal Commission of Jubail CEM 515. Purpose of the royal commission Is to develop, construct and maintain the infrastructure of Jubail-2:
Presented by: Fouad Al-Malazi ID No.: Managing Construction Contracts By Robert D. Gilbreath Chapter 1 CONSTRUCTION CONTRACTS: Roles and Relationships.
Financial Operations Emergency Relief Procedure iHUB-F-Financial Management-Financial Ops – Program Accounting – Financial Operations Emergency Relief.
District Agreement Process Temi Latinwo Federal Aid Agreement Technician.
Floyd County Board of Commissioners Special Town Hall Meeting Topic: Update on status of Georgetown WWTP.
Federal Fund Exchange Training. What is the Federal Fund Exchange? This is a voluntary program in which a Local Public Agency can trade its federal obligation.
With the Genesee County Road Commission By Fred Peivandi, P.E. And Ken Johnson, P.E. Local Road Funding.
CONSTRUCTION ADMINISTRATION Preconstruction Operations Dr. Alaattin Kanoğlu Spring, 2013 Professional Practice Management I.B.U. Architecture Undergraduate.
January 18, 2011 Genesee County Road Commission Non-motorized Project Coordination Non-motorized Project Coordination with the Genesee County Road Commission.
State Aid (SALT) prepares the Federal Agreements and the Amendments for  Force Account (FA)  Right of Way (ROW)  Preliminary Engineering (PE)  Construction.
Community Facility Loans/Grants Architect Flow Chart Owner has need for project. RD Area Office is contacted. RD visits project site and discusses project.
Overview of the Federal Aid Process for Transportation Projects.
Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015.
Local Agency Program General Information 1. Local Agency Program (LAP) is a re- imbursement program 2. Each Invoice to FDOT should only include one.
COMPLIANCE WITH GRANT IMPLEMENTATION PROCEDURES TxDot Grant Fund Project.
Bridge Building Timelines Presented by The Richland County Engineers Office Thomas E. Beck, PE, PS 77 North Mulberry Street Mansfield, Ohio Jan.
Procedural Requirements For Force Account Work on Federal and State Projects 2015 ACCA Conference Orange Beach, Alabama.
Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT November 20, 2013.
Mn/DOT AUDIT COUNTY HIGHWAY ACCOUNTANTS SINGLE AUDIT DISCUSSION.
Completing the State Aid Payment Request (SAPR). Tips Each spring check on the State Aid Finance web page for the current version of the State Aid Pay.
Closing Out a Federal Aid Construction Project Missouri Local Programs How to Close-Out a Federal Aid Construction Project.
NC Region Speakers:. Now What?  EBS  Pothole  Vac Truck  T & M  Force Account  Con Mod/Change Order  LCS  QMP (QC, QV, IA)  QC  QV  IA Excavation.
Utility & Rail Coordination in Project Development Jennifer McCleve Utilities & Rail Branch Manager.
HIGHWAY/UTILITY PROGRAM OVERVIEW ROADWAY CONFERENCE APRIL 20, 2009.
Anna Bergmark Region 7 Local Program Local Program ARRA Training: ARRA Reporting Requirements.
Center for Risk Management of Engineering Systems University of Virginia, Charlottesville 1 Process Development and Integration for the Six-Year Program.
Mock State Aid Project County Highway Accountant’s Conference 2015.
Redevelopment Grant Program Implementation Workshop Spring 2010.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Superstructure and Bridge Replacements in Regions 2 & 9 Design-Build Project (PIN , D900022) Herkimer,
Third Party In-Kind Contributions as Match for FHWA Planning Funds Michigan Transportation Planning Association Conference Flint, Michigan July 15, 2011.
Highway Utility Engineer, INDOT
Trivia Certification Program Trivia Mark Foster ODOT Region 1 Liaison and Federal Aid Specialist March 12, 2010.
FEDERAL/STATE FUNDING EXCHANGE PROGRAM MICHELE RISKO, CEAO.
NWPP Multiple-Award Technical Support Contract (eff. 08/2005) Unit 8 Unit 8 “Managing the Task Order”
Local Agency Programs An Overview Gonzalo Puente, PE Shaun Bates, PE Development Engineer Project Manager.
American Recovery and Reinvestment Act of 2009 Energy Efficiency and Conservation Block Grant Program Small City and County Grant Kick-Off Meeting California.
State Aid prepares the Agreements for  Force Account (FA)  Right of Way (ROW)  Preliminary Engineering (PE)  Construction Engineering (CE) State Aid.
Measurement and Payment
OTC Pres Project Del P5 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Jeff Gower, State Construction.
UNIVERSITY OF DAR ES SALAAM t Selection and Employment of Consultants Negotiations with Consultants; Monitoring Performance of Consultants; Resolving Disputes.
Technical Assistance Office TCP Projects 2005 Contractual and Financial Management Administrative and Financial Handbook Prepared by IA, 14/12/2001 SOCRATES.
POST-APPROVAL MANAGEMENT CONFERENCE CHICAGO REGIONAL OFFICE POST-APPROVAL MANAGEMENT CONFERENCE CHICAGO REGIONAL OFFICE.
WEST VIRGINIA INDUSTRIAL ACCESS ROAD PROGRAM West Virginia Economic Development Council January 27, 2016.
MnDOT AUDIT 2016 COUNTY HIGHWAY ACCOUNTANTS CONFERENCE ANNUAL FEDERAL CITY COUNTY AUDIT DISCUSSION.
Community Crossings Matching Grant Fund Program Kathy Eaton-McKalip
QUALITY ASSURANCE MODULE 3. Definitions Quality Assurance - A process/effort that ensures that processes are followed, that the processes of doing right.
Compliance with CCNA F.S..  Advertisement  Longlist  Shortlist  Request for Proposal  Scope of Services Meeting  Technical Proposal Review.
Contract Compliance Training
What is Tax Increment Financing?
2017 ACEA Annual Conference
CONTRACT ADMINISTRATION
FAR Part 2 - Definitions of Words and Terms
Construction Oversight
County Highway Accountant’s Conference 2015
Contract Compliance Training
State Aid Construction
Completing the State Aid Payment Request
Federal Funding for Agreements
General comments: These projects are locally owned and the LPA should be involved and informed throughout the project. The project agreement is between.
Federal Funding for Agreements
FY 2020 Community Grants Training
Delta Water Supply Project
State Aid Construction
Construction Management Services April 16, 2018
Diversity management system (DMS)
Presentation transcript:

Genesee County Road Commission Fred Peivandi, P.E. County Highway Engineer MTPA July 15, 2011 TIP Project Administration

Procedures - Projects submitted to MPO for funding Eligible Fed-Aid road projects are prioritized based on:Eligible Fed-Aid road projects are prioritized based on: PASER, ADT, date last improved, lane width. GCRC selects number of projects and submit them to MPO for consideration. GCRC selects number of projects and submit them to MPO for consideration. - Project is identified in the TIP MPO, through similar process and budget constraints develops the TIP MPO, through similar process and budget constraints develops the TIP - Project placed in the budget Once project is funded, it’s placed in the GCRC budget for the designated year. Followed by job authorization number to keep track of finances and progress.Once project is funded, it’s placed in the GCRC budget for the designated year. Followed by job authorization number to keep track of finances and progress.

Preliminary (Design) Engineering (PE) - Design Engineering Either done in house or contracted to a local engineering firm. Either done in house or contracted to a local engineering firm. Preparation of plans & specifications begins. Preparation of plans & specifications begins. - Challenges faced during PE Design issues. Design issues. Acquisition of ROW or grading permits. Acquisition of ROW or grading permits. Environmental issues such as flood plain, wet land, drainage, as well as required permits from proper agencies. Environmental issues such as flood plain, wet land, drainage, as well as required permits from proper agencies. Utilities conflict resolution. Utilities conflict resolution. - 80% plan completion Programming Application and plans & specification are sent to MDOT local agency engineer. Programming Application and plans & specification are sent to MDOT local agency engineer.

Preliminary (Design) Engineering (PE) (Continued) - GI scheduled A Grade Inspection (GI) meeting is scheduled by MDOT engineer. A Grade Inspection (GI) meeting is scheduled by MDOT engineer. All interested and involved parties are invited to attend. All interested and involved parties are invited to attend. Design, programming for obligation, utility conflicts & resolutions, and other local issues are discussed. Design, programming for obligation, utility conflicts & resolutions, and other local issues are discussed. - Construction plans completed and submitted for obligation All comments and concerns are incorporated with the plans & specifications and submitted to MDOT engineer for approval & obligation. All comments and concerns are incorporated with the plans & specifications and submitted to MDOT engineer for approval & obligation.

Next Level MDOT/GCRC contract executed - MDOT/GCRC contract executed Local agency contract through it’s normal process is approved by county road commissioners and sent back to MDOT for execution. Local agency contract through it’s normal process is approved by county road commissioners and sent back to MDOT for execution. Project advertised and let by MDOT - Project advertised and let by MDOT - Pre-construction meeting - Project awarded by MDOT

Construction Engineering (CE) - Provide full time inspection CE assigns a full time inspector to the project. CE assigns a full time inspector to the project. An outside testing firm is also assigned to the project to perform material testing. An outside testing firm is also assigned to the project to perform material testing. - Generate bi-weekly pay estimates It is important for the inspector on the job to accurately record contractor’s pay activities and report to CE in a timely matter. It is important for the inspector on the job to accurately record contractor’s pay activities and report to CE in a timely matter. Contractor’s payments are made by MDOT. Contractor’s payments are made by MDOT. - Other duties Field conflict resolution, Change Orders, Contract Modifications, and Testing Orders.Field conflict resolution, Change Orders, Contract Modifications, and Testing Orders. - Construction completion - Project acceptance - MDOT audit - Final payment to contractor

Project Close Out - Final billings 3rd party billing is submitted for reimbursement if applicable. 3rd party billing is submitted for reimbursement if applicable. Final request for FA (CE, Testing) reimbursement is submitted to MDOT for payment. Final request for FA (CE, Testing) reimbursement is submitted to MDOT for payment. - Final invoices Design and testing consultant firm invoices are paid. Design and testing consultant firm invoices are paid. Final MDOT invoice for the local participation is paid. Final MDOT invoice for the local participation is paid. - Close out report filed (GCRC)

TIP Project Administration Summary - PE - Obligation - Contract - Award - Construction - Project Accounting - Project Close Out Report

Questions?