How RISKY Is This??
How RISKY is This?? Buy a lottery ticket Only 3 will be sold Cost for a ticket $80 million Jackpot $2,000,000,000 Where is the RISK!!
The Program 1 lump sum contract 4 years 5 light rail lines 30 miles of infrastructure 100 vehicles $2,000,000,000 investment
Lets Talk RISK The Relationship Risk Development agreement Design/Build contract Operations & maintenance contract Financing plan
Development agreement Design/Build contract Operations & maintenance contract Financing plan Facility Provider Integrated Master Development Structure Lets Talk RISK The Relationship Risk
The Evolution RISK - Team Building Civil Engineer + Facility Provider D/B Contractor(s) Financiers + Vehicle Supplier
The Evolution RISK - Team Building Civil Engineer + Facility Provider Financiers + Vehicle Supplier O & M Contractor
Development Agreement CE & facility provider marriage Scope & definition Transparent costing Construction sequencing & schedule Utility agreements Property acquisition Risk register
RISK Register 154 Items 92 Facility provider 62 METRO / owner 35 Categories 30% - 15% Project value $460M - $250M
RISK Register Imputed risks Real (equity) risks Cost going in = Cost coming out Risk take of last resort
The Ultimate RISK METRO will not buy/own the project Availability payment Debt service – year five (5) onward Operating – year one (1) Avoid latent defect risks Long term business model Long term lease Buy out in increments Buy out total Private or public operation
The Vehicle RISK METRO takes what industry makes No specs No custom work No kidding!
Design / Build 3,000’ – 5,000’ segments one & done No change order No claims No litigation No liquidated damages Target cost pricing mechanism Risk vs. Incentives
Would you RISK IT??