MICE RF – TIARA and General Progress Tim Stanley RAL 5 June 2013.

Slides:



Advertisements
Similar presentations
Andrew Moss ASTeC MICE RF workshop 16t h February 2012 Daresbury Laboratory Response to RF review for the MICE RF system.
Advertisements

Andrew Moss ASTeC MICE Project Board 28 th June 2011 MICE RF System.
MICE Refurbishment of CERN RF equipment for MICE M. Vretenar, CERN AB/RF.
Collaboration meeting, RAL, 4 th – 7th November 2009 Andrew Moss ASTeC Collaboration meeting, RAL, 10 th – 13 th november 2009 MICE RF Amplifier Status.
RF systems for MICE Andrew Moss The MICE RF Group and the TIARA WP7 Team Contributions include Daresbury, RAL, CERN, LBNL, LANL, FNAL, Strathclyde & Sheffield.
Andrew Moss Daresbury Laboratory Collaboration Meeting th 19 th October 2012 RAL MICE RF System review.
Andrew Moss Daresbury Laboratory August 2013 Latest results of MICE amplifier testing.
THE MICE RF SYSTEM J.F.Orrett* A.J.Moss, ASTeC, Daresbury Laboratory, WA4 4AD, UK Accelerator Science and Technology Centre
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
MICE RF TEST STAND Major Milestones (2006) –Testing of BURLE 4616 circuit September 2006 –Testing of 4616 circuit with full amplitude and phase control.
Daresbury MICE Progress Andrew Moss Joe Orrett Peter Corlett.
Paul Drumm 9 Feb 2004 MICE at RF system: power source, distribution Paul Drumm RAL Ambitious title!
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO May 5, 2009.
1 RF Power infrastructure Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
MICE Collaboration Meeting Harbin, China 13 – 17 January 2009 Integration Issues By Wing Lau, Oxford University.
DESIGN OF A HIGH POWER TEST STAND FOR ESS SPOKE CAVITIES
Electrical & Control CM40 Daresbury Laboratory. CM40 Electrical Infrastructure Update RRM2 Latest Latest on Installation Progress Rack Allocations Racks.
Andrew Moss ASTeC 7 th December 2011 MICE RF System.
Andrew Moss Daresbury Laboratory Collaboration Meeting th -16 th February 2013 Coseners House MICE RF HP System rprogress.
Collaboration meeting, DL, 19 h – 23 h October 2008 Andrew Moss ASTeC Collaboration meeting, DL, 19 th – 23 th October 2008 MICE RF distribution system.
MICE - UK Project Progress Roy Preece 30 th April 2013.
TIARA WP2 Report and wrap-up Final Annual Meeting R. Aleksan Nov. 27 th, 2013.
1 MICE-Video Conference Status of MICE Hall Contents: General status Electrical Mechanical Preparing for Steps II & III Risks and worries Andy Nichols,
Linac Marx Modulator Update Trevor Butler 10/29/2014.
1 MICE RF Daresbury Laboratory Support Joe Orrett - ASTeC.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
Control and Monitoring System / EPICS Pete Owens Daresbury Laboratory.
MICE Status (with a UK slant) Paul Drumm, MICE Collaboration UK-NF June 2003.
S A Griffiths Target Review Jan 2009 Target Electrical / Control Schematic HexBridge Power electronics Interface PSU Capacitor Bank Local Control Interface.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
RSLR mtg 28/3/2014 RLSR mtg Alan Grant. 2 RLSR mtg 28/3/ MICE Finances - Forward Look.
Andrew Moss ASTeC Collaboration meeting CM29 15 th - 18 th February 2011 MICE RF System.
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
Electrical & Control Power Supplies Trevor Hartnett.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Al Pendzick LEReC Civil Construction.
Andrew Moss ASTeC CM32 9t h February 2012 RAL MICE RF System.
MICE RF System Power Supplies, Control and Monitoring Status report February 2012 Chris White, STFC Daresbury Laboratory MICE Collaboration Meeting CM32,
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
Decay Solenoid – what do we have to do to make it work?
Progress on the MICE RF High Power Drive Systems K Ronald, University of Strathclyde For the MICE RF team 1MICE CM38 RF Parallel Session.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
L-band test stations in End Station B Richard Swent.
ESS WP 12 Project Management & Capabilities Overview Neil Bliss Projects & Mechanical Engineering Group Leader ESS PDR, Lund, 10 th November 2015.
12 GHz Stand alone power source at CERN G.McMonagle AB/RF.
Progress on Hydrogen R&D System
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
Andrew Moss ASTeC TIARA Mid term meeting 12 th 14 th June 2012 CIEMAT ICTF Progress on the MICE RF System.
MICE RF System Overview Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory Andrew Moss STFC Daresbury Laboratory MICE UK.
1 Mice Collaboration Meeting CM27 STFC Rutherford Appleton Laboratory, UK 7 th -10 th July 2010 Daresbury Laboratory Electrical Infrastructure Report Authors.
SNuMI: WBS 1.1 Booster Upgrades Eric Prebys $642K FY06$ (no contingency, no G&A) xx% contingency Main Injector & Recycler BNB NuMI Tunnel Booster Ring.
RF Review CM37 Andrew Moss. Amplifier results at Daresbury 2MW at 35kV, good efficiency and gain.
MICE RF Power Status Paul Drumm ~ Sunday August 1 st 2004.
ATC / ABOC 23 January 2008SESSION 6 / MTTR and Spare Parts AB / RF GROUP MTTR, SPARE PARTS AND STAND-BY POLICY FOR RF EQUIPMENTS C. Rossi on behalf of.
MICE Project Progress Update Power Converters Rack housing MQ1 to MQ3 magnet power converters –Marshalling for all other quadrupole & dipole units –Houses.
MICE RF – Installation at RAL Tim Stanley RAL 7 November 2013.
MICE RF – Installation at RAL Tim Stanley, MICE RF Engineer, RAL 2 June 2014.
Standalone Commissioning Plan in MICE Hall K Ronald, University of Strathclyde For the MICE RF team 1MICE RF Review 9th Sept 2016.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
1 UK Project Finance & Schedule. Overview Finance  Budget Setting 2013/14  June Finance  Forward look to complete stepVI Schedule  Overview 2.
MICE HPRF Up-date Tim Stanley RAL – Testing 212 kW achieved from driver stage 4616 #1 at DL, ready for endstage 116 #2. Good experience, in tuning.
Andrew Moss ASTeC, Daresbury Laboratory October 2010 MICE RF Amplifier Status.
S A Griffiths CM42 June 2015 Electrical & Control.
TIARA WP 7 Ionisation Cooling Test Facility (ICTF) Task 7.2 Novel Pulsed RF Power Amplifier Design.
Chris Booth Sheffield 29th March 2006
Status of the MICE RF System
MICE RF System Power Supplies, Control and Monitoring Status report
Electrical & Control.
MICE Target Report Video Conference 29/11/07
The 9th Collaboration Meeting
Rack and Interconnect Design in E-plan
Presentation transcript:

MICE RF – TIARA and General Progress Tim Stanley RAL 5 June 2013

RF Amplifiers - Testing Aim: achieve 2 MW at Daresbury Lab before transfer of the TIARA system to RAL Previously achieved: Just over 1 MW achieved last Autumn.

Current position: – False trips of protection circuit (crowbar) in PSU; limits supply voltage to RF amplifiers. – Diagnostic tests over the last few weeks. – Replacement with re-used crowbar device (thyratron) gave some improvement; further conditioning and+ trials to recommence tomorrow at Daresbury Lab – High-spec thyratron available from Strathclyde University (circuit mods required) might enable RF testing programme to resume up to 2 MW

– Best long-term solution is probably to procure solid-state crowbar devices. (8-weeks delivery and dependent on budget). RF testing: Once crowbar issue is fixed, main task is to optimise tuning of the end-stage tube amplifier at/for high power; an iterative process.

TIARA System

TIARA Preparations for Installation Draft drawings have been produced, TS and AN at DL tomorrow to discuss detail Modifications to mezzanine floor have commenced Safety Document generated by RF group and being ratified at RAL. TS to be appointed EMF Protection Advisor.

De-mineralised cooling water system defined and drawn; interface/control panel to be built, and tested on TIARA amplifier system at DL before installation in MICE hall at RAL. Water supply, of sufficient spec for TIARA, is currently available in MICE hall.

a local water-monitoring and protection circuit is advisable for TIARA until the full control system is installed. trigger-generation unit required for timing of RF pulses in absence of LLRF full control system.

On-site supply of electricity: No remedial work expected until 2017; this might not even incur interruption of supply Compressed air for amplifiers: layout/routing yet to be finalised. Pressurisation (nitrogen gas) of co-ax transmission-lines, to dummy-load, is not necessary for TIARA RF milestone.

Procurement – Full System Substantial procurement of RF components through University of Mississippi – New Tetrode amplifier set delivered to University of Mississippi from Photonis. – 4 new tetrode valves ordered from Photonis – Loads on order from Altronics.

Distribution Network – RF 4” elbows delivered to U. Mississippi – Order placed for all other required co-ax components with Mega; numbering/ID system implemented and deliveries have commenced. – Orders for 2 additional capacitors for RF system 2 placed with GA. – Capacitor chargers ordered from Lambda – List of support equipment being prepared, including Solid state replacement for crowbar. RF test gear SSPAs – Don Summers (and colleagues) working on procurement; latest update: components for tuner-system ordered ($150K)

All major components required for TIARA deliverables ordered.