Western Carolina University Town Hall Meeting May 6, 2003 Chuck Wooten Vice Chancellor for Administration and Finance
Bond Funds Project Title Current Funds Humanities and Fine Arts $27,919,644 Stillwell Lab Building 15,057,500 McKee Classroom Building 5,289,700 Bird Building 1,836,500 Old Student Health Center 1,887,100 Breese Gymnasium 1,161,300 Housing Facility for 300 Students 15,204,600 Chiller Replacement 1,489,600 Infrastructure Improvements 10,639,000 Killian Annex 3,129,900 Killian Building 1,546,300 Forsyth Building 7,064,000 Land Acquisition 3,093,000 Technology Infrastructure 5,018,600 TOTAL$100,336,744
Humanities and Fine Arts December 2003 Completion Date 60% Complete
Stillwell Building Under Design
McKee Classroom Building May 12, 2003 Completion 90% Complete
Bird Building May 12, 2003 Completion 90% Complete
Old Student Health Center Under Design
Breese Gymnasium Under Design
Housing Facility for 300 Students October 2003 Completion Date 20% Completed
Chiller Replacement In Construction
Infrastructure Improvements Under Design
Killian Annex Under Design Bid Date – Late May
Killian Building Under Design
Forsyth Building Designer Selection March 2004
Land Acquisition In Progress
Technology Infrastructure Under Development
Work Force Building June 6, 2003 ScheduledCompletion
University Center Addition July 1, 2003 – Scheduled Completion UC Theatre UC Glass Ceiling
Athletic Facilities Improvements – I $5,164,880 Baseball Lights – Complete Baseball Lights – Complete Sports Medicine Room – Complete Sports Medicine Room – Complete Field House Addition – May 31, 2003 – Field House Addition – May 31, 2003 – Schedule Completion Team Meeting Room – Complete Team Meeting Room – Complete Football Stadium – August 31, 2003 – Football Stadium – August 31, 2003 – Schedule Completion
Athletic Facilities Improvements – II $3,027,220 Baseball Field – Bids Received on April 30th Baseball Field – Bids Received on April 30th Track, Soccer, Tennis Pre-Grading – Bids Received On April 30 th. Track, Soccer, Tennis Pre-Grading – Bids Received On April 30 th. Tennis and Soccer Grandstands – In Design Tennis and Soccer Grandstands – In Design New Softball Stadium – In Design New Softball Stadium – In Design
Belk Renovations $605,000 Contractor Preparing to Begin Project
Hospitality Management Building $10,000,000 Under Design
Student Recreation Center $12,250,000 (Under Design)
Highlands Biological Center Duplex $268,500 Under Construction
Greek Village $7,500,000 UnderDesign