FLOOD MITIGATION OBSERVATIONS AND LESSONS FROM A FLOOD IN THE SMITH FIELDHOUSE BRIGHAM YOUNG UNIVERSITY AUGUST 2006.

Slides:



Advertisements
Similar presentations
1 Shelter-in-Place A Practical Guide. 2 Chemical Fire Aboard Train Prompts Evacuation in Kentucky City Danville, KY - Portions of Danville, Kentucky were.
Advertisements

Lesson Identifying Hazards in Agricultural Mechanics.
Museum Presentation Intermuseum Conservation Association.
BUILDING EMERGENCY ACTION PLAN
Restoring Peace of Mind ServiceMaster of Greater Tacoma.
Emergency Evacuation Zayed University, Dubai Campus.
Brio 2000 / Brio 2000-M E-Learning Service Manual Rev. 0.0.
Emergency Action Plans
1 Low Conductivity Water (LCW) Connection Training Environmental Energy Technologies Division Safety Topic January 9, 2012.
Welcome! Academics and Events in One Database: How publishing event data from a single source can enhance communication, minimize risk and assist in disaster.
Post Flood Mold Risks and Rehabitation Tony Gaglierd, Allegheny County Health Department.
Emergency Preparedness Program Nursing Services Orientation April 2010.
Dining Room and Dish Room Safety Prevention and Treatment.
Slips, Trips, and Falls. What are Slips, Trips & Falls? Slip A slip occurs when there is too little traction or friction between the shoe and walking.
Emergency Guidelines SOEST Fiscal Office August 20,
Natural Gas Pipeline Safety EDM Services, Inc. April 2009.
FIRE SAFETY Information and Prevention April 2009.
Tornadoes A tornado is a violently rotating column of air extending from a thunderstorm to the ground  May have a transparent appearance until dust and.
City of Radcliff Preparing for Weather Emergencies.
ONLINE SELF-STUDY Emergency Coordinator Annual Update.
Fire Prevention and Safety Health Science Class. Rationale: Fires may occur at any time, as a result of overloading wiring, smoking, improper chemical.
FIRE PREVENTION AND SAFETY PRACTICES Health Science.
Environmental Considerations Location –Quarter mile stretch along the banks of the Mississippi river –Approximately 50 yards from the river bank.
Contractor Safety Training | Westbrook | 1 Emergency Response.
May 2013 Webinar The contents of this webinar are not prescriptive best practices for every school or school district, but rather suggestions to consider.
Managing Company Tactical Operations
2008© COPYRIGHT 1 1 ATHN DATA SUMMIT DISASTER PREPAREDNESS JULY 31, 2008 PANEL MEMBER - JOY MAHURIN COMPREHENSIVE BLEEDING DISORDERS CENTER CONTINUITY.
Kenneth (Kenny) Mercado Division Vice President of Distribution Electric Operations Turning on the Lights.
PAR CONFERENCE Homeland Defense A Provider’s Perspective Lessons from TMI Dennis Felty November 15, 2001.
Disaster Recovery: Lessons from Katrina Gail Ann McCreary, CRM Mississippi Power Company.
Children & Young People Services Suppliers & Contractors April 2012 Business Continuity Rick Thornton, Business Continuity Manager.
A Major Business Disruption A Strategy for Minimising the Downtime Anthony Hegarty Mitigating Risks.
EPMA. Overview of Servpro Large loss capability Emergency Ready Profile.
THIS IS AN EARTHQUAKE… PROTECT YOURSELF!!! /broadcast/universal/ShakeOutDrillBr oadcastSoundEffects.mp3.
Unit Objectives  Describe the types of hazards to which your community is vulnerable.  Describe the functions of CERTs.  Identify preparedness steps.
School Emergency Response Training. Unit 1: Objectives  Describe the types of hazards most likely to affect your home and community.  Identify steps.
THS Automotive Technology Safety Lesson 2: Shop Safety Features and Emergency Procedures Shop Safety Features and Emergency Procedures.
Preparing for Disasters General Liability. Introduction  The one coverage that provides you and your business the most protection is General Liability.
This Won’t Happen To Us: Incident Readiness and Response Jerry Fife Vice Chancellor for Administration Vanderbilt University
COVER YOUR BASES By: Pete Spatara By: Pete Spatara Director of Public Works Director of Public Works City of West Palm Beach City of West Palm Beach.
Staff Induction Fire and Emergency Nick Giles OHS Manager.
The Science of a Blizzard By: Rian White and Jon Malloy T-5.
Fire Safety Month Fire Safety Tips for October Department of Risk Management James Madison University.
Campus Guide to Active Shooter MCLNO Police Department.
EMERGENCY EVACUATION PROCEDURE Fire Emergency Earthquake Emergency Bomb Threat S illiman U niversity V olunteer F ire and R escue U nit.
TRANSITION TO COMPANY OFFICER Arlington Fire Department Officer Development September 2000.
Unit 2: Fire Safety and Utility Controls
Smoke Testing Information
Immediate Action Plans Jay McAmis Santa Barbara County Office of Emergency Management March 6, 2012.
SAFETY. Body mechanics refers to the way in which the body moves and maintains balance while making the most efficient use of all its parts. Muscles work.
Earthquakes are the violent shaking of the earth in response to the movement of tectonic plates.
Inspections. Structural Evaluation Look for any movement, check alignment, bowing, cracks, separation Basement wall/foundation Check floors & ceiling.
Writing an Emergency Operations Plan Why do we need to plan? Spring 2008.
Disaster Preparedness Are you prepared?. Effective Disaster Plans  Your plan should outline the basic preparedness steps needed to handle the anticipated.
COMPUTER HARDWARE SERVICING
Are you ready? Citizen Emergency Preparedness.  You are responsible for your own safety EVEN during an emergency.  You are expected to be self sufficient.
Holiday Safety 10-4 training 10 Slides, 4 minutes Lehigh/Hanson Region West Safety and Health.
 Define Risk Management  Cover Employer and Employee Responsibilities  Types of Emergencies and Critical Incidents  Emergency Preparedness  Ten Stages.
PUT A PLAN IN PLACE.  What should we do to prepare our trainee and their families or care providers?
San Francisco Electricians. Why Do You Need to Call an Electrician? Most of us have studied that one subject about circuits, electricity, and electrons.
1,000 Year Flood Lessons Learned After A State Disaster Norma J
Water Works.
CENTRAL 1 O.C.S.C.C. No. 903 Information Session
Emergencies & Emergency Response
The Great Gas Leak Incident of 2007
Fire Safety By Paige Robinson 8F.
Welcome To the world of Exquisite Heat
Fire Safety Month October 2018
Short & Simple • © 2018 Thinkshortcut Publishing, LLC • Created by MarketingZoo.com If you have any other heat sources, such as portable heaters, kerosene.
Bella Vista Fire Department Procedures on Sprinkled Buildings
Presentation transcript:

FLOOD MITIGATION OBSERVATIONS AND LESSONS FROM A FLOOD IN THE SMITH FIELDHOUSE BRIGHAM YOUNG UNIVERSITY AUGUST 2006

I want to talk to you about what I think are five key elements of flood mitigation. Notification Notification Response/Mobilization Response/Mobilization Clean up Clean up Restoration/Reconstruction Restoration/Reconstruction Evaluation Evaluation

1. Notification Who and how fast - Electronic Alarm notification to University Police - Electronic Alarm notification to University Police -University Police assessment -University Police assessment -Police notify appropriate on call person and Risk Management -Police notify appropriate on call person and Risk Management -On call specialists can handle their areas well but you need a good mechanism to alert upper level management in major events -On call specialists can handle their areas well but you need a good mechanism to alert upper level management in major events

Notification Strengths -Risk management informed early -Risk management informed early -Risk management informed upper level management early -Risk management informed upper level management early -Good cell phone communication -Good cell phone communication

Notification Weaknesses -College notification -College notification -Cell phone batteries -Cell phone batteries -Notification process took too long -Notification process took too long

2.Response/ Mobilization Incident command -Select an incident command person who can delegate responsibilities and stay put. -Select an incident command person who can delegate responsibilities and stay put. Don’t assign a “hands on” person this responsibility. Glen Johns our Risk Management and safety director was on call and served as incident commander. Don’t assign a “hands on” person this responsibility. Glen Johns our Risk Management and safety director was on call and served as incident commander. Have the incident command decision made now before the incident occurs. Have the incident command decision made now before the incident occurs.

2. Response/Mobilization Initial safety assessment -Glen Johns and safety office staff -Glen Johns and safety office staff -Electrocution hazard assessed and mitigated -Electrocution hazard assessed and mitigated

2. Response/Mobilization Reporting Make sure you have a good mechanism for your own line reporting. “Keep your boss informed.” Make sure you have a good mechanism for your own line reporting. “Keep your boss informed.” Incident command only reports through their line Incident command only reports through their line

Response/Mobilization strengths -Handled quickly -Handled quickly -Had good incident commander available -Had good incident commander available

Response/Mobilization weaknesses -Some cleanup was occurring before safety assessment was complete -Some cleanup was occurring before safety assessment was complete Some of my own line reporting was slow. Some of my own line reporting was slow.

3. Cleanup Delegate assignments -In our case Glen Johns our Risk Management director delegated -In our case Glen Johns our Risk Management director delegated -Buildings/Water clean up -Buildings/Water clean up -Electrical/ Utilities service -Electrical/ Utilities service -Food -Food -Media relations -Media relations -Campus academic communication -Campus academic communication

3. Cleanup Pumping problems/ Capacity, Lift, Reach -Electric and mechanical service could not be addressed until water was cleared out. -Electric and mechanical service could not be addressed until water was cleared out. -With water flooding basement areas and filling mechanical rooms water pumping became a major issue. -With water flooding basement areas and filling mechanical rooms water pumping became a major issue.

3. Cleanup Pumping problems/ Capacity, Lift, Reach Gas powered pumps with limited lift presented two problems. Gas powered pumps with limited lift presented two problems. Pumps had good volume capacity but limited lift and limited hose reach Pumps had good volume capacity but limited lift and limited hose reach If pumps were placed in buildings near water sources carbon monoxide became a problem. If pumps were placed in buildings near water sources carbon monoxide became a problem. -We had four large 2 and 3 inch discharge pumps in place and made no headway. -We had four large 2 and 3 inch discharge pumps in place and made no headway.

3. Cleanup Pumping problems/ Capacity, Lift, Reach -We called in Provo City and they supplied a 6 inch diesel powered pump. With our grounds division diesel powered sewer truck and Provo City’s pump we began to make headway -We called in Provo City and they supplied a 6 inch diesel powered pump. With our grounds division diesel powered sewer truck and Provo City’s pump we began to make headway

3. Cleanup Water shutoff problems -Water break was in a loop fed from 2 directions identifying and turning off water was a process that took too long. -Water break was in a loop fed from 2 directions identifying and turning off water was a process that took too long. -One of the shut off valves was allowed to be placed in the flooded basement mechanical room. -One of the shut off valves was allowed to be placed in the flooded basement mechanical room. -Other remote field water line valves were hard to locate -Other remote field water line valves were hard to locate -Break was in a water loop so it had to be shut off from two directions -Break was in a water loop so it had to be shut off from two directions

3. Cleanup Utilities -The major mechanical rooms and electrical rooms were under 10 feet of water -The major mechanical rooms and electrical rooms were under 10 feet of water

3. Cleanup Utilities -Switchgear and transformers were damaged beyond repair and had to be replaced. -Switchgear and transformers were damaged beyond repair and had to be replaced. -Parts were 3 to 5 days out -Parts were 3 to 5 days out

3. Cleanup Utilities -Emergency power switchgear was inoperable -Emergency power switchgear was inoperable

3. Cleanup Drying out -A large wood playing floor had some water underneath it and needed heavy air flow to save it -A large wood playing floor had some water underneath it and needed heavy air flow to save it -Power availability to run drying fans became a problem -Power availability to run drying fans became a problem -We had to evaluate our resource for drying out after the water was stopped and pumped out. -We had to evaluate our resource for drying out after the water was stopped and pumped out. We did not have de-humidifiers We did not have de-humidifiers

3. Cleanup Contract help

-Don’t be a hero call in available help. We used “Utah Disaster Cleanup”. Their resource for fans and the power to run them was great. -Don’t be a hero call in available help. We used “Utah Disaster Cleanup”. Their resource for fans and the power to run them was great. -We have a lot of equipment here on campus. All totaled we have around 100 floor fans for use around campus. That sounds good but a big clean up contractor will have the following; -We have a lot of equipment here on campus. All totaled we have around 100 floor fans for use around campus. That sounds good but a big clean up contractor will have the following; 1000 floor fans 1000 floor fans Generators and extension cords to run all of them Generators and extension cords to run all of them 25 Air dryers 25 Air dryers Additional manpower with the ability to work around the clock. Additional manpower with the ability to work around the clock. Make sure you have a single contract source for work performed Make sure you have a single contract source for work performed Specialized equipment for computer repair and file retrieval. Specialized equipment for computer repair and file retrieval. Well worth the expenditure Well worth the expenditure

3. Cleanup Strengths Good delegation Good delegation Teamwork Teamwork Incident command handled other problems that allowed non distracted cleanup Incident command handled other problems that allowed non distracted cleanup

Cleanup Weaknesses Failure to establish good contact point with contract help Failure to establish good contact point with contract help Contract help not communicating contact information at shift change Contract help not communicating contact information at shift change

4. Restoration/Reconstruction Mold -Keep air moving until crawl spaces are completely dry. -Keep air moving until crawl spaces are completely dry. -Remove water traps where air can’t circulate. -Remove water traps where air can’t circulate. -Remove soaked gypsum board. -Remove soaked gypsum board.

4. Restoration/Reconstruction Mold -Wall covering will shrink and cannot be re- glued -Wall covering will shrink and cannot be re- glued -Carpet extract or remove. -Carpet extract or remove. -Measure moisture content do not assume -Measure moisture content do not assume

4. Restoration/Reconstruction Odor -Eliminate don’t mask -Eliminate don’t mask -We are still circulating air in some dirt floor crawl space areas. -We are still circulating air in some dirt floor crawl space areas.

4. Restoration/Reconstruction Furniture and electronic equipment -Replace soaked upholstered furniture -Replace soaked upholstered furniture -Computers were sent to contract water damage company and saved about 75% -Computers were sent to contract water damage company and saved about 75%

4. Restoration/Reconstruction New Construction -Complete demolition, haul off and dry out to protect from mold spores -Complete demolition, haul off and dry out to protect from mold spores

4. Restoration/Reconstruction Strengths Had in house labor available for immediate response Had in house labor available for immediate response Did not have a long delay for plans and specifications Did not have a long delay for plans and specifications

4. Restoration/Reconstruction Weaknesses Still some odor in dirt floor crawl spaces Still some odor in dirt floor crawl spaces Some carpet has gone bad long after flood. We should have replaced Some carpet has gone bad long after flood. We should have replaced

5. Evaluation Post incident meeting Large or small discuss your process with all involved Large or small discuss your process with all involved Include occupants, managers, risk management, front line workers in your assessment Include occupants, managers, risk management, front line workers in your assessment Do it with in 60 days of incident Do it with in 60 days of incident

5. Evaluation Post incident meeting Evaluate the cause Evaluate the cause

5. Evaluation Post incident meeting Evaluate future problems Evaluate future problems

I hope your waterfall experiences in the future look like this Not this