Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out Square Foot Estimating.

Slides:



Advertisements
Similar presentations
HEAT LOSS & HEAT GAIN HEAT FLOW. Heat flows from high temperature to low temperature There are 3 types/methods of heat flow/transfer: 1.Conduction- through.
Advertisements

Taking off and ESTIMATING
Parts of typical slab formwork
Reinforced Concrete QTO Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
What are they and what are they used for?. Contract Documents Architects working drawings Specifications Schedules Bill of Quantities.
CHAPTER 9 Thermal & Moisture Protection
Chapter 14: Cost Approach. Cost Approach  The Cost Approach is most useful when:  Property is unique  Property is reasonably new and the improvements.
Chapter 3 Measuring Excavation and Sitework
Earthwork QTO Stage 1 Preconstruction Stage 2: Procurement
IBC 2006 Chapter 5 Building Height and Areas After determining occupancies, the code analysis determines what height and areas are allowable for the occupancy.
Creating a section view using floor plans
Assemblies Estimating Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
How to do an estimate. Steps 1) Estimate from bottom up –How you construct the project –Lets you get an understanding of project path –Lets you find errors.
Construction Estimating Using Excel Professor Locurcio CON4003, CVE4073, CVE5073.
Cost Estimating EGR 386. Estimating Up till this point in our economics lesson –assumed known future cash flows, but… An important aspect of engineering.
It’s more than adding and subtracting..  Before bidding, the site should be examined for the following:  Distance from the office  Site conditions.
Conceptual Cost Estimating
INTRODUCING THE COST APPROACH Chapter 11. Base cost Builder’s profit Building shell Building size and shape Comparative square-foot method Construction.
You will learn to solve problems that involve the perimeters and areas of rectangles and parallelograms.
Sinking in Concrete Calculating materials for a concrete job.
REVIEW – CHAPTER 4 & 5 Stretching & Shrinking By: Ms. D. Kritikos.
By: Brian Toomer ET-494 Senior Design Dr. Cris Koutsougeras Advisor: Mr. Rode’
Calculations On completion of this unit the Learner should be able to demonstrate an understanding of: The formula used to calculate: Areas Volumes Ratios.
Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE.
Detailed Quantity Estimating Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
1 HVACR116 – Trade Skills Plan Views Elevations Plan Views Elevations.
Warm-Up Rules of Engagement Office hours are in the afternoons, unless you have made other arrangements. If the door is open, I’m in the area come look.
Construction Math This presentation gives examples of scenarios one would use math in construction situations.
CON 4003 Construction Estimating Prof R. V. Locurcio.
FORMS, SCAFFOLDING and STAGING
EDT Elevations1 Weekend Cabin Retreat Project Elevations Sacramento City College EDT 300/ENGR 306.
Integrals  In Chapter 2, we used the tangent and velocity problems to introduce the derivative—the central idea in differential calculus.  In much the.
Chapter 7 Budgeting: Estimating Costs and Risks © 2012 John Wiley & Sons Inc.
HVACR116 – Trade Skills Plan Views Elevations. Plan Views.
EDT Cabin Design Project - Elevations1 Weekend Cabin Retreat Project Elevations Sacramento City College EDT 300 Kenneth Fitzpatrick, P.E.
Construction Estimating Using Excel Professor Locurcio CON4003, CVE4073, CVE5073.
General Exam Tips Think Read the question carefully and try to understand the scenario, then think about the Maths you will need to do. Is it perimeter,
Area: Day 1 Math 10-3 Ch.3 Measurement. Area- basics Area is the surface of a 2-D object. A good way to visualize area is to imagine coloring in between.
Chapter 13 Estimates for Remodeling Work
CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE.
Preconstruction & conceptual estimating design-build cm at-risk or cmgc negotiated projects.
1 PS&E Plans, Specifications and Estimate. 2 Contract Letting Plans-Show what is being built Plans-Show what is being built Specifications-Show how project.
Determine the cost to purchase and install all the 2 x 4 studs listed in Prob The wall is 8’-0” high. Windows are 4’-0” high and doors are 6’-8”.
Introducing The Cost Approach
The relation between a ratio and a proportion is: the proportion shows that two ratios are equal. If 84 is divided into three parts in the ratio 3:5:6,
CEE 492 Lab Session #1 February 3, CEE 492 RS Means –Introduction –Exercise ICE MC2 –Installation –Introduction and Overview Outline.
© Goodheart-Willcox Co., Inc. Permission granted to reproduce for educational use only 1 PowerPoint Presentation Publisher The Goodheart-Willcox Co., Inc.
CEE 492 Lab Session #1 February 3, CEE 492 RS Means –Introduction –Exercise ICE MC2 –Installation –Introduction and Overview Outline.
© Awad S. Hanna, PhD, P.E.1 Estimating and Scheduling CEE 492 Lecture 8 Sources of Estimation Data.
ESTIMATING STEEL FOR CONCRETE POURS. REBAR -Estimated by the pound or ton -Must know the size of steel bar needed -Must know linear feet needed -Bars.
DR. Nabil Dmaidi F ACTORS THAT D ETERMINE V ARIATION IN E STIMATES.
Chapter 3: Cost Estimation Techniques
Chapter 3: Cost Estimation Techniques
Principles of Architecture & Construction
Estimating and Scheduling CEE 492
Estimating Project Costs
Drawing Interpretation
Estimating the Cost for the Concrete Pad
“Planning and Scheduling a SIMPLIFIED Construction Project” BCT458 September 27, 2009 Group Signatures Taggart.
Chapter 3: Cost Estimation Techniques
Chapter 3: Cost Estimation Techniques
Elevation Layout and Drawing Techniques
Check it out! 1.2.1: Normal Distributions and the 68–95–99.7 Rule
10 The Cost Approach—Part I: Reproduction/Replacement Cost
Thermal Impact of Different Interior Finishing Materials on Energy Consumption YOGESH JATAV
House Construction Budget Plan
LINEAR BALANCE METHOD & MATRIX SCHEDULE
Keystone Library Deliverables
Chapter 3: Cost Estimation Techniques
Presentation transcript:

Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out Square Foot Estimating

S.F. Estimating Similar to the ROM estimating method Based on knowing the area and few more details Conducted during the conceptual phase for budgeting purposes Means publishes two guides: Assemblies cost data book (Fig 5-7) and Square Foot Data book (Figures 5-8 and 5-9)

Using the Reported SF Data Estimates are obtained using the Assemblies Cost Data Book, same as ROM estimating. Prices are based on 11,500 projects and are organized according to the quality (1/4, 1/2, or 3/4) Estimates are computed by multiplying the floor area times the price per SF. Adjustments are then made to the price as the ROM estimate. The price includes O&P but not design fees. Adjust for location, time, and design fees. Advantages: represent actual project data (true costs) Disadvantages: difficult to know exactly what is included in the price and it does not reflect the effect of different project situations

Example The cost of a 15,000 ft 2 library In Panama City, FL to start in June 2009 assuming median quality is: –15,000 X 161$/ft 2 from figure 5-7 = $2,415,000

Size factor (Figure 5-3) = 15,000/12,000 = 1.25 Cost multiplier (Figure 5-3) = 0.98 Cost adjusted for the size = $1,558,200 Location: Panama City Index = 70.6 Panama City Cost = X 1,558,200 = $1,100,089

–Time: Assuming 5.1% annual increase (as assumed under the historical cost indexes table in R.S Means Guide, the estimate was done assuming start of January For 1/2 year, the projected increase in price is 1.025% project cost in Panama City June 2009 = 1.025X1,100,089 = $1,127,591 (Fig 5.4)

Design fee from figure 5-10, design fee is about 7.27% Overhead and profit: Included Cost in Panama City June 03 including design fees = X 1,114,390 = $1,195,544 (( )/( ))*( ) -7.3= 7.27

Using the Modeled SF Data A more detailed method, requires more information than the area, the estimate is better fine-tuned Different projects of different sizes are tabulated, the cost of material, labor and equipment is estimated per unit. Knowing the size of the structure, the SF cost is also given. Two tables are given for each structure: –a table similar to ( Figure 5-8 )that gives the cost of the building according to SF, perimeter, type of exterior wall, story height, and area of basement. With the table, prices for common additives are given. O&P,design fees and size are included.

–A table similar to (Figure 5-9)that gives the unit and the SF price. The building is divided into 12 systems and 38 components The SF column is used to compute the cost used in the previous table at the specified size and to compare the components The unit cost column is used to obtain a more accurate estimate when a more detailed quantity take off is available. Distinguish between SF of floor area, S.F.. ground, S.F. roof, and S.F. slab. If the unit is “each” the number of units is = cost per S.F. X floor area / cost per unit Check the number of elevators in Figure 5-9, and item 4.6: how many elevators and doors?

Examples Assuming that only the area, perimeter, story height, basement area, type of exterior walls are known, use the first table. You must be able to compute areas and perimeters as fast and accurate as possible. What is the cost to construct a 15,000 ft 2 library in Panama City, FL assuming face brick with concrete block back-up, RC frame? The perimeter is 486 LF and 14’ story height. The building includes 5 Nickel cadmium emergency lights, 20 study carrels, 1 40’ Aluminum flagpole, 300 LF of double face bookshelves, 10 LF charging desk, and 10 laminated reading tables.

Answer Interpolating between (13,000 ft 2 cost $157.95), and (16,000 SF cost $154.05) in Figure 5-8, the cost at 15,000SF = (( )/( ))*( )= $ / ft 2.

Adjustments: –Perimeter = 486 LF: there is about 100 LF more than the typical model. From Figure 5-8, Add $10 Basic S.F. cost = $ $10.00 = $ $/ ft2 Building basic cost = $ X 15,000 = $ 2,480,250

–Additives: –From Figure 5-8: compute the cost of each additive and add it to the basic cost –How about the rest of the adjustments?

Area and Perimeter Computations Break down the area to smaller units. Write down all the computations Use the “recess method” to compute the perimeter. You will be asked in the exam to compute perimeters using this method. If the perimeter is known, the length of a parallel perimeter at a perpendicular horizontal distance HD = Per.  8 HD Examples on perimeter computations, handout

Review of the Adjustments Depending on the type of the estimate, size, design fees, or O&P may and may not be included. Size: –use table 5-2 or 5-3 to get the typical size –compute the size factor = proposed area / typical area –use the graph in Figure 5-3 to determine the cost multiplier based on the size factor cost adjusted for size = base cost X cost multiplier Location: –get the city index from a table similar to Figure 5-4 cost adjusted for location = cost adjusted for size X city index 100

Time: –cost at a time after the year in which the book was written: assume 5.1% annual increase. Fraction of a year is considered. –cost at a time prior to the year in which the book was written: use historical cost indexes cost in a previous year = current 30 city average cost X index at the city in the past or cost in a previous year = current city cost X index at the city in the past current 30 city average index A current index at the city B

cost in a previous year at a city/ index at the city in the past = current 30 city average cost /current 30 city average index = current city cost / current index at the city Or: Cost any location at a certain time index at that location and time = constant

using formula A, there is no need to adjust for location first. Depreciation: today’s value of a building n years old = today’s construction cost X (1-depreciation factor%) –consider the total apparent age of the building not the actual age –to estimate the value of a building built in year a and destroyed in year b, 1942 and 1973 for example, compute today’s value and adjust for depreciation for a-b years. When using the detailed tables: the number of units = cost per S.F. X typical area on top of the table / unit cost

A More detailed Example # 1 Salem, OR in 73,AR

(Included)

–A table (Figure 5-9)that gives the unit and the SF price. The building is divided into 12 systems and 38 components The SF column is used to compute the cost used in the previous table at the specified size and to compare the components The unit cost column is used to obtain a more accurate estimate when a more detailed quantity take off is available. Distinguish between SF of floor area, S.F.. ground, S.F. roof, and S.F. slab. If the unit is “each” the number of units is = cost per S.F. X floor area / cost per unit Check the number of elevators in Figure 5-9, and item 4.6: how many elevators and doors?

Estimating Using Detailed Tables Example (2) Using the unit cost information in the attached tables from of R. S. Means Square Foot Costs, compute the cost of building a 4 story parking garage in Salem, OR in Jan If: –floor area = 120,000, perimeter = 723 ft –ground area = 1.05 slab area –7” RC slab on grade with vapor barrier and granular base –story height = 11 ft –exterior walls are face brick with concrete block back up –three hydraulic passenger elevators. Assume that the cost of a single elevator is the same for 4 or 5 story building.