Fall Chinook Acclimation Project (FCAP) Overview Under ESA NMFS lists Snake River fall chinook as threatened in 1992 Co-managers agreed to release 450,000.

Slides:



Advertisements
Similar presentations
UMATILLA HATCHERY MONITORING AND EVALUATION PROJECT Richard Carmichael, Wes Stonecypher, Gerold Grant, and Will Cameron Project # Oregon Department.
Advertisements

Project Principal Investigator: Stephen J. Rocklage Co-authors: Billy D. Arnsberg and Dale S. Kellar Nez Perce Tribe Department of Fisheries.
COMPARATIVE SURVIVAL STUDY (CSS) of PIT-tagged Spring/Summer Chinook and PIT-tagged Summer Steelhead CBFWA Implementation Review Mainstem/Systemwide.
A Study to Evaluate Delayed (Extra) Mortality Associated with Passage of Yearling Chinook Salmon Smolts through Snake River Dams Project No
UMATILLA HATCHERY AND SATELLITE FACILITIES OPERATION AND MAINTENANCE
Grande Ronde Supplementation Lostine River: Operation and Maintenance and Monitoring and Evaluation Sponsor: Nez Perce Tribe Project Number:
Nez Perce Tribal Conservation Enforcement Presentation by Chief Adam Villavicencio for the System-wide Provincial Review July 18, Copyright.
Workshop: Monitoring and Evaluation of Harvest on Columbia River Salmonids July 31- August 1, 2007.
Nez Perce Tribe Department of Fisheries Resource Management CBFWA Presentation September 22, 2004 Clearwater Subbasin Focus Watershed Program
Chinook Salmon Adult Abundance Monitoring Paul Kucera and Dave Faurot Nez Perce Tribe Department of Fisheries Resources Management BPA Project
Phase I Okanogan River Spring Chinook Production Proposal #29050 Sponsored By: Colville Confederated Tribes Presented By: Stephen Smith.
Survival Estimates for the Passage of Juvenile Salmonids Through Dams and Reservoirs of the Lower Snake and Columbia Rivers (Project ) CBFWA March.
Implement the Grande Ronde Model Watershed Program Administration and Habitat Restoration Projects Project Lyle Kuchenbecker, Project Planner.
SELECT AREA FISHERY EVALUATION BPA Project # CEDC, ODFW, WDFW.
Lolo Creek Watershed Project #
Evaluation of Juvenile Salmonid Outmigration and Survival in the Lower Umatilla River Project No Tara White, Shannon Jewett, Josh Hanson,
Assessment of A-run Steelhead population in the Clearwater Nez Perce Tribe Department of Fisheries Resources Management.
UMATILLA RIVER FISH PASSAGE OPERATIONS
Imnaha River Smolt Survival and Smolt to Adult Return Rate Quantification (Imnaha River Smolt Monitoring Program) BPA Project Number Nez Perce.
Chinook Salmon Adult Abundance Monitoring Project Dave Faurot Nez Perce Tribe Pacific Northwest National Laboratory.
Monitoring and Evaluation of Yearling Fall Chinook Salmon Released Upstream of Lower Granite Dam Nez Perce Tribe Department of Fisheries Resources Management.
Fishery Management Overview - Context Sponsored By: Colville Confederated Tribes Presented By: Stephen Smith.
Protect & Restore The North Lochsa Face Analysis Area Watersheds (# ) Nez Perce Tribal Fisheries/Watershed Jack J.S. Yearout.
Lower Columbia River and Columbia River Estuary Habitat Restoration Program Mission of the Estuary Partnership is to protect and enhance the lower Columbia.
Evaluate Spawning of Fall Chinook and Chum Salmon Just Below the Four Lowermost Columbia River Mainstem Dams Project PNNL.
Little Canyon Creek Subwatershed Steelhead Trout Habitat Improvement Project Sponsored by: Lewis Soil Conservation District.
Nez Perce Tribal Hatchery (NPTH) DEPARTMENT OF FISHERIES RESOURCE MANAGEMENT 1 - CENTRAL INCUBATION FACILITY FOR SPRING AND FALL CHINOOK 3 - FALL CHINOOK.
Restore McComas Meadows /Meadow Creek Watershed Project # Restore McComas Meadows/ Meadow Creek Watershed Project # Nez Perce Tribe Fisheries.
Principal Investigators: Sherman Sprague-Spring Chinook Billy Arnsberg-Fall Chinook Nez Perce Tribal Hatchery Monitoring & Evaluation BPA Project #
Snake River Fall Chinook Glen Mendel Debbie Milks William Young.
LOWER YUBA RIVER ACCORD Monitoring and Evaluation Program Redd Surveys Casey Campos PSMFC.
OKANOGAN RIVER SPRING & SUMMER/FALL CHINOOK
Rebecca Buchanan and John Skalski, University of Washington Gregory Mackey, Douglas County PUD Charles Snow, Washington DFW TRIBPIT: ESTIMATING SALMONID.
DEVELOPING THE WALLA WALLA HATCHERY Design criteria for maximizing survival.
US Army Corps of Engineers BUILDING STRONG ® Mid-West Electric Consumers Association September 16, 2014 Corps of Engineers US Army Missouri River Mainstem.
Overview of Current Production Programs Across the Columbia River Basin.
NWHA- Panel Discussion “Spawning Better Ideas for Fish Passage”
Nez Perce Tribal Hatchery Complex Program Overview Nez Perce Tribe Department of Fisheries Resources Management.
Lower Snake River Fish & Wildlife Compensation Plan Scott Marshall LSRCP Program Manager US Fish & Wildlife Service.
Spokane Tribal Hatchery Sherman Creek Hatchery Lake Roosevelt Volunteer Net Pens Monitoring by Lake Roosevelt Fisheries.
Cedar River Instream Flow Management Balancing Certainty and Flexibility.
Federal Columbia River Power System Operations Planning.
Variation in Straying Patterns and Rates of Snake River Hatchery Steelhead Stocks in the Deschutes River Basin, Oregon Richard W. Carmichael and Tim Hoffnagle.
Pacific Fishery Management Council Jurisdiction –3 miles to 200 miles –4 states (includes Idaho) Members -- appointed –State governments –Federal Agencies.
Lower Snake River Fish & Wildlife Compensation Plan Scott Marshall LSRCP Program Manager US Fish & Wildlife Service.
May 10, 2012 Presented by Micki Varney Oregon Department of Fish and Wildlife.
Lower South ForkClearwater River Lower South Fork Clearwater River Nez Perce Tribe DFRM Watershed Division Mark Johnson-Project Leader
Steelhead Stock Status Review and ESA Oregon Rhine Messmer ODFW District Staff Oregon Department of Fish and Wildlife Pacific Coast Steelhead Management.
The Columbia River Basin Where we’ve been. Where we’re going. October 18, 2005.
Fiscal Year 2004 April 10, FY 2002FY 2003FY 2004 EnactedBudgetBudget COLUMBIA RIVER BASIN: Army Corps of Engineers Bureau of Land.
Kilarc-Cow Creek Hydroelectric Project Decommissioning FERC Project No. 606 Technical Meeting May 16, 2007, 1-4 pm Red Lion Redding, CA.
BUILDING STRONG SM Partnering and Coordination to Accomplish the Navigation Mission.
Lower Snake River Comp Plan M & E Program SPY’s thoughts based on 3 weeks.
Washington’s Lower Snake River Compensation Plan Steelhead Program – A retrospective and program adaptive management overview Mark Schuck and Joe Bumgarner.
Downstream Survival of Juvenile Stream Type Chinook Salmon and Steelhead Through the Snake/Columbia River Hydropower System and Adult Return Rates AFEP.
Findings of Congress The Endangered Species Act is the last resort for species at risk of extinction. Under the ESA, the National Marine Fisheries Service.
Puget Sound Salmon Hatcheries April 2003 Puget Sound Salmon Hatchery Management Decision Making ESA & NEPA Processes Independent Scientific Review Process.
Release Strategies to Improve Post-Release Performance of Hatchery Summer Steelhead in Northeast Oregon. Lance Clarke, Michael Flesher, Shelby Warren,
Performance of a New Steelhead Line Derived from Hatchery Parents Collected in Autumn in the Grande Ronde River Lance Clarke, Michael Flesher, Shelby Warren,
Implementing Hatchery Reform The Dawn of a New Beginning or more of the same old thing? Mike Delarm NOAA Fisheries.
Historical Review Fish Migration Data. Two Management Approaches Spill for Fish Passage Planning dates Percent passage dates.
2016 Smolt Monitoring Program Juvenile Passage Data and
Northwest Fisheries Science Center Technical Management Team
Northwest Fisheries Science Center Technical Management Team
Steelhead status in Idaho – 2012 Update
Impacts from elevated TDG Spring 2017
2017 TMT Year-end Review December 12, 2017 Brandon R. Chockley
Albeni Falls Dam Operations
Steelhead status in Idaho 2010 update
Steelhead status in Idaho 2010 update
Presentation transcript:

Fall Chinook Acclimation Project (FCAP) Overview Under ESA NMFS lists Snake River fall chinook as threatened in 1992 Co-managers agreed to release 450,000 yearlings above Lower Granite Dam & up to 2.4m sub-yearlings US Congress funds project for FY95 Began operations in 1996 with the release of 115,000 yearlings from Pittsburg Landing. Complete construction and begin operation of Big Canyon facility in 1997 and of Capt. John Rapids facility in Pittsburg Landing: Snake River Captain John Rapids: Snake River Big Canyon: Clearwater River

GOAL OF PROJECT Supplement natural production of Snake River fall chinook above Lower Granite Dam. DESCRIPTION OF SERVICES Provide acclimation and final rearing of Lyons Ferry yearling and sub-yearling fish through the operation of two facilities on the Snake River and one site on the Clearwater River.

FCAP Project: Long-term- linked to delisting - at least 8 more years Approved through U.S. v Oregon FCRPS Bi-Op: Safety-net project Key role played by Nez Perce Tribe Lyons Ferry Hatchery - Gene Bank for Snake River fall chinook

Captain John Rapids Facility River Mile 163, Snake River

Captain John Rapids Yearling Delivery

Pittsburg Landing Facility, Snake River, r.m. 213 (31 miles downstream of Hells Canyon Dam)

Pittsburg Landing Facility ft diameter Aluminum Tanks,

Big Canyon Facility, Clearwater River, r.m. 35, near Peck, ID – 16-20ft diameter Aluminum Tanks

Methods: March 1 – 150,000 yearlings to each facility Reared for 6 weeks, densities held to 0.1 lbs/cu.ft./in. River water supply to prevent localized spawning Yearlings released in mid-April at about 10 fpp during rising water conditions. Up to 2.4m subyearlings at 90 fpp - divided among the facilities in early May Subyearlings released at 60 fpp about sometime in June, before river flows begin to drop Fish Culture Methods: As per Integrated Hatchery Operation Team (IHOT) guidelines Fish health procedures as per AFS Blue Book, IHOT, NPT Fish Health Protocals

Production Numbers

ANNUAL BUDGET $654,400 PRODUCTION STAFF Project Leader - Bruce McLeod Project Foreman - Mike Key (12 months) Technician I - 6 (6 months) Technician II - 4 (6 months)

PROGRAM CHANGES PENDING Fish Health: Co-managers will continue to monitor BKD and adjust procedures as required. Big Canyon: 1. Acquire lease from NPT to allow installation of domestic well and septic system. 2. Address equipment problems with U.S. Army Corps of Engineers, Walla Walla. Captain John Rapids: Address equipment problems with USACOE. Pittsburg Landing: Negotiate special use permit with with U.S. Forest Service for another site to lower costs.