1 MOBILIZING EU FUNDS Lessons Learned in a Pre-Accession Country Hachemi Bahloul, UNDP Bulgaria.

Slides:



Advertisements
Similar presentations
Financing of OAS Activities Sources of cooperation Cooperation modalities Cooperation actors Specific Funds management models and resources mobilization.
Advertisements

PRIME MINISTRY SECRETARIAT GENERAL FOR EU AFFAIRS ABSORBING EU FINANCIAL ASSISTANCE THE CASE OF TURKEY Ahmet YÜCEL Deputy Secretary General October 19,
Joint presentation by respective units in DGs AGRI, EMPL and REGIO IPA Components III, IV and V: Conditions for successful preparation and absorption of.
Planning and Timely Implementation of Structural Funds Interventions Katarína Mathernová Director, DG Regional Policy European Commission 24 November 2005.
EU-Regional Policy and Cohesion Structural Funds and Accession 1 ANNUAL MEETING OF ISPA PARTNERS 2003 FROM ISPA TO COHESION AND STRUCTURAL FUNDS BRUSSELS,
Regional Conference “THROUGH COOPERATION TOWARDS INTEGRATION” Montenegro, 8-9 th October 2007 Working Group II Instrument of Pre Accession and Cross Border.
HR 08 IB SPP 02 TWINNING PROJECT “ENHANCEMENT OF CAPACITY FOR EFFECTIVE MANAGEMENT OF EU COHESION POLICY FUNDS” 1 The most significant results of Component.
1 EFCA - 21th March 2002 Raul Mateus Paula. 2 This presentation underlines: The key objectives of the Relex Reform The division of the responsibilities.
Government of the Republic of Macedonia Secretariat for European Affairs TWINNING EXPERIENCE IN MACEDONIA Orhideja Kaljoshevska. MA NCP Twinning “1 st.
1 MINISTRY OF REGIONAL DEVELOPMENT AND PUBLIC WORKS DIRECTORATE GENERAL PROGRAMMING OF REGIONAL DEVELOPMENT Operational Programme Regional Development.
European Commission 1 Participation of candidate countries in European Community Programmes, Agencies and Committees By Vicente NIETO, Co-ordinator of.
NEX and DEX: Theory and Reality
EU-Regional Policy and Cohesion Structural Funds and Accession 1 SPP BUILDING IMPLEMENTATION CAPACITY Training seminar on evaluation Prague February.
ANNUAL REPORT ON THE ABSORPTION OF THE EU FUNDS IN THE REPUBLIC OF BULGARIA IN 2010 MONIKA PANAYOTOVA, CHAIRWOMAN OF THE COMMITTEE ON EUROPEAN AFFAIRS.
The Instrument for Pre-Accession Assistance
GOVERNMENT OF ROMANIA MINISTRY OF PUBLIC FINANCE MANAGING AUTHORITY FOR COMMUNITY SUPPORT FRAMEWORK Evaluation Central Unit Development of the Evaluation.
Date: in 12 pts The cultural dimension of the Eastern Partnership Culture Gyöngyi Mikita Policy Officer, "Culture Policy, Diversity and Intercultural Dialogue"
Audits of pre-accession funds in the State Audit Office of the Republic of Latvia 2000/2001 Uldis Kremers Auditor of the Audit Department of the State.
Project implementation under DIS PRESENTATIONby Mr. Gábor Rónaszéki CFCU Hungary 30 November 2006.
Community agencies: partners in accession Cooperation with EMCDDA - Polish experience Boguslawa Bukowska, National Bureau for Drug Prevention ,
The European Code of Conduct on Partnership Teresa EPALZA European Commission DG Employment, Social Affairs and Inclusion.
James Aiello PricewaterhouseCoopers Africa Utility Week 06 International Good Practice in Procurement.
Presentation WG 2 Managing EU Funds on the Regional Level Republic of Albania Ministry of European Integration (MEI) Regional Conference EU Perspectives.
This project is co-financed by the European Union and the Republic of Turkey 1 Bölgesel Rekabet Edebilirlik Operasyonel Programı’nın Uygulanması için Kurumsal.
(Dr. Peter Heil, ALTUS – Hungary)
Joanna Fiedler Enlargement and Neighbouring Countries Unit DG Environment European Commission REReP → RENA Vision of the European Commission PEIP Regional.
Croatian Experience with Management of EU Funds Nataša Mikuš, Deputy State Secretary Central Office for Development Strategy and Coordination of EU Funds.
MANAGING EXTERNAL AID PROGRAMMES mag. Peter Ješovnik Deputy Director Beograd, 7-8 december 2005.
PACIFIC AID EFFECTIVENESS PRINCIPLES. Purpose of Presentation Provide an overview of Pacific Principles on Aid Effectiveness Provide an overview of Pacific.
Expert group meeting on draft delegated act on the European code of conduct on partnership (ECCP) under cohesion policy
Institutional structures for Structural Funds assistance Ministry of Finance September 10, 2003.
The Instrument for Pre-Accession Assistance IPA General overview DG Enlargement Financial Instruments and Regional Programmes Directorate.
Lisbo n, Novem b er Bosnia and Herzegovina Ministry of Civil Affairs Sector for Health COMMUNITY AGENCIES: PARTNERS IN ACCESSION The point.
December_2009 Partnership building. December_2009 Partnership building within the partnering process COREGROUPCOREGROUP FORMAL LAUNCH $ $ $ $ $ cost centre.
Regional policy European Commission EN Update on IPA Component III - environment Brussels, 28 November 2008 Erich Unterwurzacher REGIO.I4 – IPA/ISPA.
UNDP Latvia strategy to support absorption of EU funds Janis AIZSALNIEKS, Project Coordinator UNDP Latvia CAPACITY BUILDING TO ABSORB EU FUNDS LOCAL GOVERNANCE,
8th Cohesion Fund Monitoring Committee 11 April 2008 Technical Assistance for the Cohesion Fund Management in Latvia No.2005/LV/16/C/PA/001.
1 Cohesion Policy Brussels, 9 June 2009 “ Cohesion policy: response to the economic crisis” European Commission seminar for managing and certifying.
PHARE TWINNING CONTRACT BG/2004/IB/TR/02/UE Strengthening the capacity of the Ministry of Transport to manage the Sectoral Operational Programme on Transport.
1 MINISTRY OF REGIONAL DEVELOPMENT AND PUBLIC WORKS MANAGING AUTHORITY FOR COHESION FUND (REGULATION 1164/94) MANAGEMENT OF PROJECTS, FINANCED BY COHESION.
Paulius Baniūnas Ministry of Finance of the Republic of Lithuania EU Structural Support Management Department Monitoring and Analysis Division SYSTEM OF.
Stabilisation & Association Process: the EU Policy for South East Europe Brussels December 2004.
The partnership principle and the European Code of Conduct on Partnership.
WHO EURO In Country Coordination and Strengthening National Interagency Coordinating Committees.
JASPERS for CEF Stéphane OUAKI Head Of Unit
1 EUROPEAN FUNDS IN HALF-TIME NEW CHALLENGES Jack Engwegen Head of the Czech Unit European Commission, Directorate General for Regional Policy Prague,
Belgrade, Donor Coordination Meeting Belgrade, 4 th of June 2012.
TEN-T Executive Agency and Project Management Anna LIVIERATOU-TOLL TEN-T Executive Agency Senior Programme and Policy Coordinator European Economic and.
Information Overview SF: Planning & Programming Workshops for EC Delegation Patrick Colgan & Ján Krištín PROGRAMMING PROCEDURES in Support of Regional.
The EU Water Initiative and the EU ACP Facility New Instruments to promote sustainable development of water resources and affordable access Antonio Garcia-Fragio.
Ministry of Finance Compliance assessment of the management and control systems of the managing authorities under the Operational programmes. Conclusions.
Ministry of Finance Financial management and control of the Operational Programmes, co- financed under the Structural funds and the Cohesion fund of EU.
Financial Implementation of the Assistance from the Structural Funds and the Cohesion Fund of the EU Sylvia Indjova Head of Certifying Authority Director.
National Qualification Framework Romanian Experience.
ROUND TABLE “Exchanging Experience in Absorption of the European Funds: Perspectives for Bulgaria and Poland” 1 April 2011, Sofia Tomislav Donchev Minister.
JASPERS activities to promote intermodal projects March 2010 Bratislava György BESSENYEI Transport Sector Specialist.
PRE-ACCESSION PROJECT IMPLEMENTATION IN CROATIA
JASPERS Presentation to Member States
Ministry of Finance Contribution of the Operational Programmes to the implementation of the NSRF objectives Boriana Pencheva Director Management.
Key Moments and Forthcoming Activities in 2009
COORDINATION OF FOREIGN ASSISTANCE IN THE REPUBLIC OF MACEDONIA
Regional and Bilateral cooperation instruments
Establishment aid coordination and management mechanisms
The ERA.Net instrument Aims and benefits
Supporting Cities and Regions through Projects and Programmes
The role of the ECCP (1) The involvement of all relevant stakeholders – public authorities, economic and social partners and civil society bodies – at.
Helene Skikos DG Education and Culture
Principles of Financial Management and Disbursement
EC approach towards financing infrastructure projects Dagmar KALJARIKOVÁ Policy Officer for Turkey, Montenegro, REC CEE and NGOs Unit for Enlargement.
Panel II: Adequate capacity for absorbing financial assistance
Presentation transcript:

1 MOBILIZING EU FUNDS Lessons Learned in a Pre-Accession Country Hachemi Bahloul, UNDP Bulgaria

2 EU pre-accession support 3 pre-accession instruments: Phare, ISPA and SAPARD Mirror the Structural & Cohesion Funds (SCFs) and aim at strengthening institutional capacity for SCFs EC support is accession driven: APs, NPAA and NEDP ( ) EC Regular Reports monitor progress towards accession

3 Institutional set up of Phare support Centralized national overall substantive co- ordination of Phare assistance Coordination, monitoring and assessment of Phare (National Aid Coordinator) Centralized national overall financial management of Phare assistance A National Fund requests, redistributes, controls and reports to the EC on use of funds (National Authorizing Officer) Limited number of Implementing Agencies Line ministries expected to manage structural funds designated as IAs (Programme Authorizing Officer) CFCU implements programmes which are multi-sectoral (PAO)

4 Phare Programming Cycle Line ministry 1 Line ministry 2 MF NAC EC Brussels DG Enlargement Project Fiche Proposals Package of proposals General comments on the package Programming Missions Start of programming Phare 2002 (September 2001) Programming missions by EC Commission (December 2001, February 2002) Financing Proposal by Government (April 2002) Phare Management Committee approval (June 2002) Financing Memorandum Phare 2002 signed (November 2002) Phare programme 2002 funds received (June 2003)

5 Phare Project Implementation National Fund Impl. Agency Technical Management Tendering and contracting Beneficiary Line ministry Technical management Technical monitoring CFCU Tendering and contracting Reports Funds transfer Contractor Technical inputs Reports Funds transfer Contractor Technical monitoring Payments EC Brussels EC Delegation Monitoring Payments Funds transfer/Reports

6 Bottlenecks in Phare Absorption Large volume of resources (EURO 250 million per year) Limited Govt administrative capacity (project formulation and implementation)  Slow disbursement of EU funds/partial achievement of objectives  Critical EC Regular Reports (delayed accession)  Looks bad on Government/Delegation/DG Enlargement

7 Opportunities for UNDP Strong motivation of Government to improve delivery/results BUT mixed feelings on the part of the EC Delegation on UNDP support: UNDP viewed as not raising institutional capacity Government dependency on UNDP of a future EU member No EC guidelines for the selection of UNDP as “sole source”

8 Conditions/entry points for UNDP General conditions:  General capacity/credibility/track record of the UNDP CO  Strong relationship of trust with line ministry through strong UNDP presence and credibility in the sector Project specific condition: Government/EU must clearly see the value added of UNDP involvement Limited Govt substantive capacity: support for the conceptualization/formulation of the project Limited Govt management capacity/complex/sensitive project: management support Limited EU technical expertise (Roma issues) Need for additional flexible financing: cost-sharing for preparatory activities (project maturity), cost-sharing for PMU costs

9 What UNDP must do 1. Phare programme formulation cycle about to start Propose/discuss project ideas with ministries with which track record of co-operation (in line with accession priorities) Consult informally with the EC Delegation Feel the mood in Brussels through the UNDP Liaison Office 2. Phare programme formulation cycle has started Identify projects in preparation in areas of interest to UNDP whose formulation is problematic (problematic implementation) Propose assistance to Government, inform EC Delegation, feel the mood in Brussels (through the UNDP Liaison Office)

10 What UNDP must do In all cases UNDP must be actively involved in the project formulation cycle at some stage The Government must be ready to provide strong arguments in front of the EC for UNDP involvement UNDP’s exact role and how UNDP involvement will be formalized must be clearly stated in the Project Fiche Remark: the more politically sensitive and/or the more complex the project, the more likely that the Government and/or the EC will want UNDP to be involved

11 Arguments to use UNDP support guarantees: Relevant technical expertise (Roma issues) Efficient and timely achievement of objectives High delivery (99% in Bulgaria) Transparency and accountability Contributes to institutional strengthening UNDP support is cheap or free (when compensated by TRAC) UNDP can provide project co-financing EU visibility will be ensured

12 Formalization of UNDP support EU Funding: “Community Contribution Agreement with an International Organisation” (2003 EC/UN Framework Agreement) signed with the Govt IA/CFCU and endorsed by the Delegation Project Fiche annexed to the Agreement All project funding (UNDP/EU/Govt): UNDP Prodoc signed with the IA

13 Specific implementation features in Bulgaria In a pre-accession country the EU funds are managed by the Govt (National Fund + the designated IA) 2003 Framework Agreement is a EC/UN agreement and it is not binding for the Govt - but it was accepted It resolved a number of procedural problems (exchange rate risk, tendering procedures, reporting etc.) BUT  Funds are paid to UNDP by the Government IA  UNDP reports to the Government IA

14 Specific implementation features in Bulgaria The Government IA may have specific requirements: EU funds paid to UNDP in EURO by the IA in installments on the basis of a UNDP request for transfer of funds EU funds advanced by UNDP in EURO to the IA special project account on the basis of a NEX request for advances of funds (project must be NEX) Project payments with EU funds made from that account (double signature Govt/UNDP)

15 Implementation with UNDP Support National Fund CFCU Tendering and contracting CA PMU UNDP EC Brussels Line ministry Technical management Transfer of EU funds Transfer of Government funds EUR Project Account LC Project Account Transfer of Government and UNDP funds Transfer of funds EU Prodoc Payments

16 Flow of funds PMU CFCU Conversion of USD in LC EUR Project Account Transfer of funds Direct payments UNDP EUR Account Transfer of funds Request for funds UNDP New York UNDP USD Account Transfer of funds Replenishment GovernmentUNDP LC Account LC Project Account Transfer of funds NEX Financial Report Transfer of funds NEX Financial Report Management Consultants Training Equipment Works Payments C/S as per prodoc

17 Recent developments The closer the country is to EU accession the less likely for the EC to endorse UNDP overall project management support (UNDP supporting the IA) The EC insists on full Govt responsibility and institutional strengthening for the SCFs UNDP role acceptable as provider of technical assistance (even this type of UNDP involvement perceived as a factor of project success) Implications for UNDP Try for overall project management support, but if strong resistance, settle for the TA component of the project

18 THANK YOU