Project risk and control. Tender risk Programme and method – Tightness of completion LAD’s Extent of change – Construction method Temporary works Change.

Slides:



Advertisements
Similar presentations
A Joint Code of Practice Objectives and Summary Presentation
Advertisements

Construction Engineering 221
CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension.
Project Procurement & Contract Administration Jiwei Ma
Contracts – important issues
AACEI Contingency Forum Contingency Management
Design-Build: RISKS OR REWARDS for the Consulting Engineer?
Nabil dmaidi1 Miller Act H Enacted in 1935 H Federal Contracts over $25,000 H Contractor shall provide Bonds H Performance Bonds in the amount to protect.
4/28/20151 PRESENTED BY NAKABAGO JOHN CONTRACT MANAGEMENT AND ADMINISTRATION IPPU PRESENTATION JOHN NAKABAGO.
Delays and the consequences and time management
LECTURE 7 CLAIMS RELATED TO SUB-CONTRACTORS
The Defence & Security Public Contracts Regulations 2011 Sub-Contracting and Offset Arrangements Katherine Calder 8 June
John Boon ZUT November Procurement Systems The organisation of the interaction between the purchaser of a new building and the suppliers of goods.
1 Basics of Government Contracting. Federal Procurement Background The U.S. Government is the world’s largest purchaser of goods and services 2.
A Match made in Heaven? Connecting you with a builder.
1 BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Procurement Methodology David Dale NLSL II Procurement Manager.
Paulina wawryca Paweł bilski Piotr mazur. Project risk.
ATMES Spring Meeting April 26-27, 2012 Myrtle Beach, South Carolina International Projects.
Software Development Contracts and Legal Issues Cost plus Fixed price Combined.
Construction Contract Administration (ENGC 6363) ( FIDIC Chapter 15) EMPLOYER BY TERMINATION Presented by: Mustafa Al tayeb.
Rethinking Construction Review of traditional construction models and a comparison of product development processes with other industries School of Architecture.
Washington Metropolitan Area District Office SBA.
Construction Industry Development Board development through partnership Construction Procurement documents 2c.
1 Collaborating for competitive advantage: SMEs and the Supply Chain Achieving better SME involvement in Partnering Michael Thompson The TEAM FOCUS Group.
Quotations, Contracts and Tenders Presentation by Simon Gresham.
Risk and Uncertainty © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 1.
Introductions Mike Dement Multi Management Services
1 Guide for the use of framework agreements Considerations for calling off from framework agreements 1.Have you identified one or more framework agreements.
Valuations and interim certificates. Purpose Value the works taking account of: – the physical work done on site; – any extra work ordered by the client;
U.S. Small Business Administration
Drafting the Request for Tender Offers: Important Terms and Conditions – Charles Rumbaugh Guest Lecturer Naval Postgraduate School IDARM International.
Key Provisions in Standard Contract Conditions Presented by Simeon A. Sahaydachny Kyiv, 20 April
Construction Contracts and Project Delivery Methods
Risk Management in the Built Environment Qualitative and Quantitative Risk Management By Professor Simon Burtonshaw-Gunn – licensed under the Creative.
Public Procurement Procedure – Bidding Documents
1. Introduction Time is of essence in basically every construction project Yet, delays of some sort are general rule, rather than the exception Consequence:
Budgets. Types of budget Organisational goals informed by the strategic plan and the organisations ability to meet its historic targets – Strategic Turnover.
LECTURE 4 FORMULATION & PRESENTATION OF MONETARY CLAIMS  Recovery of Loss / Expenses / Damages  Notice of intention to claim  Particular and further.
Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.
© OECD A joint initiative of the OECD and the European Union, principally financed by the EU Ensuring Good Quality PPP Projects Martin Darcy United Kingdom.
FORMULATION & PRESENTATION OF EOT CLAIMS
Programme and progress. Programme Employer requirements – Sectional completion Pre-tender programme – Use for ascertaining completion risk – Subcontractor.
Cash Flow Analysis Part 2 King Saud UniversityCE511- Construction Planning & Control 1.
Project Procurement Management
CASUALTY LOSS RESERVE SEMINAR SESSION 2 SEPTEMBER 10, 2001 CONTRACT SURETY CASE RESERVES STEPHEN J. TRECKER SENIOR VICE PRESIDENT XL SURETY PHILADELPHIA,
 Section Where you go if you disagree on either three elements entitlement, impacts or costs  Begins with the contractors notice 5 working days.
Contract Performance In Traditional and E-Contracts; Breach of Contract and Remedies Chapter 18 & 19.
The Design/Build Contract. What Is A Design/Build Contract? Contract that combines design & construction into one agreement The design/build team provides.
BIDDING PRIVATE AND PUBLIC WORK Major Differences between Private and Public How to determine whether a project is Public or Private: "Who owns the dirt"
Service Departments © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 1.
Final Accounts. Accounts Submissions Last Bill for Contracted Works ( excluding Retention) Presented at Practical Completion Practical Definition dependant.
Company Structure © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 1.
Collaboration of Entitlement and Cost Efforts in Claims Analysis Rubino & McGeehin Consulting Group June 27, 2005.
Helen S. Henningsen Department of Veterans Affairs Office of General Counsel.
Building Capacity of SMEs for Participation in Public Procurement Draft Presentation for Training of Trainers June 2014.
Getting work © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 1.
Construction Tender Process Tender steps between Client, Contractor and Subcontractor Dr A Kimmance.
What Small and Emerging Contractors Need to Know Understanding Selected Key Provisions of Construction Contracts © Copyright 2017 NASBP.
Guide for the use of framework agreements
Ch 11 - Procurement Management Learning Objectives
CERN-ITER Workshop CERN Procurement Anders Unnervik 16 Jan 2017
Extension of time and how it is granted to a contractor (Referencing JCT 2005)
Project delays and Payment delays
COST PLANNING AND ESTIMATION
Chapter 12: Project Procurement Management
Resource procurement.
Corporate governance and management
Contractual Arrangement
Contracts and documentation
Financial management.
Presentation transcript:

Project risk and control

Tender risk Programme and method – Tightness of completion LAD’s Extent of change – Construction method Temporary works Change of sequence Reuse – Ground conditions Measurement and “contractors” risk Who measures, how paid for consequential method-related costs? © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 2

Tender risk cont Subcontractors – Extent of quotation – Qualifications – Relationship with main contractor – Specificity Suppliers and materials – Fixed ? Price – Which rate to use? – Wastage allowance – Small load charges – Muscle? – Time for resend out © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 3

Commercial opportunity An opportunity to make the tender more competitive – Sometimes called “scoping” allowance – Calculated figure which results in a net reduction of the tender total – Usual to have a project commercial strategy Design team ability Client approach Quality of documentation Type of procurement Competitiveness of subcontract market Valuation and variation provisions © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 4

Reduction in tender price © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 5

Contract risk Delay and disruption – Responsibility Delay-impact on overall handover Delay-impact on sequencing – Disruption Direct measurable consequences Can take place without any measurable delay Who is at fault – Contractor – Client – Both – No-one Who determines – Architect – Engineer – Approach of contract © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 6

Delay- some terms Compensable delay – An employer risk event where the contractor is entitled to an extension of time and time- related costs Concurrent or parallel delay – Where there are two or more delays and at least one is an employer risk event and another a contractor risk event Critical delay – Delay to a critical activity which causes delay to overall completion of the project Excusable delay – Where the contractor is relieved from delay damages and where there may be time and money entitlement under the contract Non-excusable delay – Delay caused by the contractor for which there is no relief from delay damages and no time or money entitlement Global delay – Where actual completion exceeds planned completion but individual employer risk events are not identified Local delay – Delay to noncritical activities which do not impact the contract completion date. © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 7

Claims Extension of time awarded – Relevant event/compensation event – No culpable delay – Culpable delay Loss and expense – Records, records, records Evaluation of prolongation expenses – Who and how © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 8

Insolvency Risk rating Definitions Bankruptcy Voluntary agreement Administrative receivership Administration Winding up Voluntary liquidation Compulsory liquidation © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 9

Termination and insolvency The effect of termination – Notices – Impact Subcontractor insolvency – Practical difficulties Programme Evaluation of the work Notional account and final account Employer insolvency – Practical difficulties Recovery Contractual position Subcontract position Contractor insolvency – Options available © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 10

Subcontractor price weighting criteria © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 11

Post auction stage © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 12

Bidding activities © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 13

Popularity? Price only? Reduced buyer/supplier trust Need for completeness of tender information No opportunity to offer comparable materials Little opportunity for integrated procurement Future in a price-oriented market? © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 14