Presentation is loading. Please wait.

Presentation is loading. Please wait.

Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.

Similar presentations


Presentation on theme: "Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes."— Presentation transcript:

1 Cost valuation reconciliation

2 When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes two weeks to complete Discussed at Monthly CVR meeting © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 2

3 Fundamental principle Prudence Match expenditure with income Uses the application for payment and the architects certificate to substantiate the valuation/Net sales value of the works © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 3

4 Documentation used External valuation – Identification of: Overmeasure Undermeasure Variations in dispute Claims in dispute Materials on site Undercertification © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 4

5 Information flows © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 5

6 Documentation (contd.) Overmeasure schedule Undermeasure schedule Subcontractor liability build-up Architects/Engineers certificates Contra charge invoices © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 6

7 Definitions Overmeasure – Claimed-Unpaid – Claimed-Paid Definition-“Application for monies in advance of their eligibility” Undermeasure Definition-“Work completed that costs have been incurred for but haven’t been included in the application for payment” – Measured works – Variations Work in Progress Definition-“Work that has been carried out in the period between the cost cut-off date and the valuation date” © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 7

8 Basic principle Net sales value uses the application for payment as the baseline Application adjusted as follows: – Overmeasure – Deducted – Undermeasure - Added – Materials on site - Deleted © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 8

9 Basic principle Net sales value uses the application for payment as the baseline Application adjusted as follows: – Overmeasure – Deducted – Undermeasure - Added – Materials on site - Deleted © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 9

10 Documentation supporting the CVR Internal valuation broken down into a set of allowances Overmeasure schedule Undermeasure schedule Cost statement Subcontractor liabilities Buying reconciliation Materials reconciliation Cost to complete exercise Estimated final account/profit margin Architects/Engineers certificate Narrative explaining variances © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 10

11 Cost statement © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 11

12 Adjustments for work in progress © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 12

13 When to report a loss? © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 13

14 Internal and external bills © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 14

15 Adjustments © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 15

16 Simplified CVR pro forma © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 16

17 A more complex example 17

18 Discussions at CVR meeting Profit release Cash flow Turnover Items in dispute – Variations – Claims Items for management action © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 18


Download ppt "Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes."

Similar presentations


Ads by Google