Introduction & Opening Remarks l Hurricanes of 2004 & 2005 highlight the need for a fresh look at these issues l We support this effort and will be active.

Slides:



Advertisements
Similar presentations
Project Management An Electric Utility Perspective Michael Jackovich President and Owner Project Management Plus, Inc. May 18, 2009 Copyright 2009 Project.
Advertisements

Museum Presentation Intermuseum Conservation Association.
Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &
FPUA Storm Readiness 2007 Florida Public Service Commission Internal Affairs May 23, 2007 Craig Brewer- Superintendent of Electric T&D.
Storm Preparedness Workshop Verizon Florida, LLC May 23, 2007.
Electric Utility Infrastructure Florida Public Service Commission Workshop Paul Davis, Director Energy Control Center Tampa Electric Company January 23,
Lee County Electric Cooperative 2006 Hurricane Preparedness Plan.
Progress Energy Florida 2007 Hurricane Preparedness Florida PSC Hurricane Preparedness Meeting May 23, 2007.
Florida Public Service Commission Internal Affairs Hurricane Season Preparation Paul Davis, Director Energy Control Center June 5, 2006.
JEA Storm Readiness 2006 Florida Public Service Commission Internal Affairs June 5, 2006 Presenter: Ted Hobson, VP, Fuels, Purchased Power & Compliance.
Outage Reporting Hierarchy Background Data Capture Structure Next Steps.
FPL Hurricane Assessment Operating Committee January 25, 2005.
Tampa Bay Harbor Safety & Security Committee
Challenges in the Implementation of Enterprise GIS – TNB’s Experiences Malaysia Geospatial Forum 2012.
Advisory Working Groups Town of Union Vale April 8, 2015.
An Overview of the Energy Education Program Monroe County CSC November 3, 2009.
DEPAUL UNIVERSITY SERVICE LEVEL AGREEMENTS AND PERFORMANCE METRICS Marge Hayes Ashton Hayes Group January 31, 2000.
1 March 1, 2007 Report An Overview October 30, 2006 – Staff Workshop.
Utility Asset Management Application on Pump Stations Jens Sapin, P.E. Environmental Services - Facility Compliance and Incident Response Utility Asset.
1 Power Quality Mary Santori, P.E. Senior Engineer September 12, 2013.
Experience you can trust. Hurricane Hardening Commission Staff Workshop on Electric Utility Infrastructure Richard E. Brown, PhD, PE Tallahassee,
1 Impact of the 2004 Hurricanes Hurricane Charley Landfall on August 13 th Customers affected Poles replaced Transformers replaced Miles of wire replaced.
Implementing Major Cost Control Strategies While Improving Effective Service Levels BackgroundBackground The client, a major regional telecommunications.
Electric Infrastructure Workshop Gulf Power Company January 23, 2006.
SDG&E Electric Reliability Reporting CPUC Workshops May 26-27, 2015.
WESTERN UNDERGROUND COMMITTEE 2015 Spring Conference 65 th ANNIVERSARY 1950‐2015 Welcome Remarks Bill Chiu Director of Engineering – T&D Southern California.
Florida Power & Light 2006 Hurricane Preparedness Plan June 5, 2006 Presented by: Geisha Williams.
Experience you can trust. 1 Electric Infrastructure Hardening Rebuilding Utility Infrastructure LSU Center for Energy Studies Bill Snyder
Lee County Electric Cooperative 2007 Hurricane Preparedness Activities.
Infrastructure Development & Needs From a Commercial Viewpoint Chris Hendrix General Manager, Texas Retail Energy, LLC Manager of Energy Procurement, Wal-Mart.
FPSC Electric Utility Infrastructure Workshop Florida Municipal Electric Utilities Alan Shaffer Assistant General Manager - Delivery Lakeland Electric.
Utility Engineers, PC.  Generation  Transmission  Distribution.
The Risk Management Process
Electric Utility Infrastructure Commission Staff Workshop January 23, 2006.
Florida Municipal Electric Utilities May 6, 2009 Paul Kalv, Director City of Leesburg Electric Department Florida Public Service Commission Docket No.
1 Verizon Florida, LLC Hurricane Season Preparation PSC Workshop – May 6, 2009.
Tampa Electric Company 2009 Hurricane Season Preparation Regan Haines Director, Energy Delivery May 6, 2009.
Glades Electric Cooperative Infrastructure Miles of Line 2,213  Overhead Dist.2,180  UndergroundDist. 33  Transmission 87 16,402 meters Average 7.
2009 Hurricane Season Preparations Florida Public Utilities Company May 6, 2009.
2015 HURRICANE SEASON PREPARATIONS March 18, 2015.
2014 Hurricane Season Preparation Informal Meeting for Electric Utilities with Florida Public Service Commission Staff March 26, 2014.
2009 Hurricane Preparedness Richard Shaheen Sr. Director, Engineering & Technical Services May 6, 2009.
2006 Hurricane Preparedness June 5, 2006 Sumter Electric Cooperative, Inc R. Ben Brickhouse: Director of Engineering & IT John J. LaSelva: Director of.
Hurricane Season Preparation Briefing Florida Public Service Commission May 1, 2008 Kevin Wailes General Manager – Electric Utility.
Tampaelectric.com Presented to the Florida Public Service Commission May 1, 2008 Tampa Electric Company 2008 Hurricane Season Preparation Regan Haines.
Transmission Substation 2004 Storm Season. Transmission & Substation 2 HURRICANE CHARLEY August 13, 2004 Transmission Sections Locked Out ………………………… 44.
2009 Hurricane Season Preparedness Briefing Gulf Power Company Presented by Andy McQuagge Power Delivery Services Manager May 6, 2009.
2008 Hurricane Season Preparedness Briefing Gulf Power Company Presented by Andy McQuagge Power Delivery Services Manager May 1, 2008.
May 6, STORM PREPAREDNESS EMBARQ – FLORIDA, INC. Sandra Khazraee – Regulatory Manager.
2014 Storm Preparedness Jeff Brewer – Manager of Engineering Tri-County Electric Cooperative, Inc.
2015 Hurricane Season Preparedness Briefing Jorge Puentes Engineering Manager – Northeast and Northwest Divisions March 18, 2015.
2014 Hurricane Season Preparedness Briefing Jorge Puentes Technical Projects Manager – Northeast and Northwest Divisions March 26, 2014.
Exercising, Maintaining and Reviewing BCM Arrangements ERMAN TASKIN
Informal Meeting with FPSC Staff 2015 Hurricane Season Preparation March 18, 2015.
LESSONS LEARNED FROM RECENT PIPELINE INCIDENTS FLORIDA NATURAL GAS ASSOCIATION (FNGA) OPERATING & MARKETING CONFERENCE ROD WALKER PRINCIPAL CONSULTANT.
Florida Keys Electric Cooperative Association, Inc. Storm Hardening Florida Public Service Commission May 1, 2008 Scott Newberry, CEO John Stuart, COO.
Florida Public Service Commission’s 2007 Storm Preparedness Workshop
2008 Hurricane Season Preparations
Florida Public Service Commission
Hurricane Preparedness Plan 2008
Progress Energy Florida 2008 Hurricane Preparedness Florida PSC Hurricane Preparedness Meeting May 1, 2008.
Today’s Agenda Introduce ourselves
2007 Hurricane Season Preparations
Florida PSC 2014 Hurricane Season Preparation
Florida PSC Hurricane Preparedness Meeting May 6, 2009
2007 Hurricane Season Preparedness Briefing
Hamilton County / National Grid Meeting
Hamilton County / National Grid Meeting
Presentation transcript:

Introduction & Opening Remarks l Hurricanes of 2004 & 2005 highlight the need for a fresh look at these issues l We support this effort and will be active participants l Help shape infrastructure strategy that works for Florida l Be clear what we’re trying to improve; make sure any change is for the better

FPSC Infrastructure Hardening Workshop Presented by: Michael G. Spoor, P.E. Florida Power & Light January 23 rd, 2006

Florida Power & Light Co. 27,000 sq. miles & 35 counties 4.2 M customer accounts 535 substations Over 6K miles of transmission lines Over 65K miles of distribution lines Over 68K transmission structures Over 1.1M distribution poles Over 800K distribution transformers 2

Overview Summary of 2004 hurricane season Lessons learned from 2004 Summary of 2005 hurricane season Lessons learned from 2005 Next Steps 3

2004 Hurricane Season Tropical storm force winds Hurricane force winds Hurricane Charley Category 4 Hurricane Frances Category 2 Hurricane Jeanne Category 3 4

2004 Hurricane Season – Distribution and Transmission Equipment Repaired Distribution –10,379 FPL poles –960 miles of OH conductor –590 miles of OH service conductor –1 million OH splices –30 miles of UG cable –100 miles of UG service cable Transmission / Substation –174 structures –15 miles of conductor –3 substation transformers –10 regulators –39 breakers 5

Lessons Learned from 2004 Hired 3 rd party consultant to help evaluate system performance and restoration processes –Key findings  FPL met or exceeded standard utility restoration practices  FPL’s distribution, transmission, & substation facilities performed well  FPL’s transmission system was restored effectively –Areas of opportunity  Enhance customer communications by providing lower level ETR’s  Establish critical infrastructure priorities with local EOC’s  Establish partnerships to improve resource acquisition capabilities Internal reviews –Distribution  Introduced forensic team to perform detail analysis  Streamlined processes for underground conversions –Transmission/Substation  Reviewed remainder of system from lessons learned  Implemented plans accordingly 6

2005 Hurricane Season Tropical storm force winds Hurricane force winds Hurricane Katrina Category 1 Hurricane Wilma Category 3 7

2005 Hurricane Season – Distribution and Transmission Equipment Repaired Distribution –12,632 poles (FPL & non-FPL) –930 miles of OH conductor –570 miles of OH service conductor –1.1 million OH splices –30 miles of UG cable –100 miles of UG service cable Transmission / Substation –100 structures –7 miles of conductor –1 substation transformers –7 regulators –16 breakers 8

Lessons Learned from 2005 –Distribution Performance –Distribution Standards –Quality Processes –Pole Maintenance –Transmission Performance –Substation Performance –Weather Assessment –Industry Benchmark Retained independent outside consultant (KEMA) to examine the performance of FPL facilities during Wilma in an attempt to better understand whether transmission and distribution structures performed appropriately Key Finding FPL’s transmission, substation and distribution systems are designed to meet or exceed all required safety standards, and, during Wilma, performed as expected and in accordance with FPL standards Most of FPL’s poles are designed 50% stronger than required by the NESC 9

Next Steps Evaluate recommendations from KEMA study Develop infrastructure hardening plan –”Hardening Roadmap”. Items under consideration: –Strengthen Poles –Shorter Spans –Conductor Size –Undergrounding of Facilities –Vegetation Management –Other Design Considerations –Substation Facilities 10

Questions 11