Presentation is loading. Please wait.

Presentation is loading. Please wait.

Tampa Electric Company 2009 Hurricane Season Preparation Regan Haines Director, Energy Delivery May 6, 2009.

Similar presentations


Presentation on theme: "Tampa Electric Company 2009 Hurricane Season Preparation Regan Haines Director, Energy Delivery May 6, 2009."— Presentation transcript:

1 Tampa Electric Company 2009 Hurricane Season Preparation Regan Haines Director, Energy Delivery May 6, 2009

2 Tampa Electric Company - 2009 Hurricane Season Preparation Hurricane Preparedness Briefing Multi-prong approach System Infrastructure Coordination Pre-Storm Preparation

3 System Infrastructure System Hardening Wood Pole Inspections Ten Point Plan Initiatives Three Year Storm Hardening Plan 2007-2009 Tampa Electric Company - 2009 Hurricane Season Preparation

4 System Infrastructure Distribution System Wood Pole Inspection Program – Approx. 39,000 each year Includes Wind Loading Analysis Reinforcements & Repairs Tampa Electric Company - 2009 Hurricane Season Preparation

5 System Infrastructure Transmission System – 26,000 poles system-wide Above Ground Inspections Groundline Inspections Includes Wind Loading Analysis Repairs Tampa Electric Company - 2009 Hurricane Season Preparation

6 System Infrastructure Storm Hardening – Ten Point Plan Initiatives Vegetation Management Transitioning to a three year tree trim for all feeders and laterals 30% increase in trimming for 2009 Critical Transmission circuits patrolled semi-annually Tampa Electric Company - 2009 Hurricane Season Preparation

7 System Infrastructure Storm Hardening – Ten Point Plan Initiatives Joint Use Audit 100% of system has been audited 2007-2008 Plan to begin next audit in 2010 Completed Implementation of new GIS Participate in Joint Research Projects with PURC Forensics Tampa Electric Company - 2009 Hurricane Season Preparation

8 System Infrastructure Three Year Storm Hardening Plan Distribution construction standard - NESC Grade B Extreme Wind Pilot Hardening Projects Saint Joseph’s Hospital Port of Tampa Tampa Electric Company - 2009 Hurricane Season Preparation

9 System Infrastructure Tampa Electric Company - 2009 Hurricane Season Preparation

10 System Infrastructure Three Year Storm Hardening Plan Convert Overhead Distribution Interstate Crossings to Underground Completed conversion of Lois Ave 4kV Network protectors inspected, tested, and repaired Tampa Electric Company - 2009 Hurricane Season Preparation

11 System Infrastructure Three Year Storm Hardening Plan Transitioned Underground Construction Standard to Stainless Steel Pilot Submersible Switchgear and “Storm Secure” Break Away OH Services Tampa Electric Company - 2009 Hurricane Season Preparation

12 Coordination Planning and Coordination with Governmental Agencies Hurricane planning with Emergency Operation Centers Hillsborough County, City of Tampa, City of Temple Terrace, City of Plant City, City of Oldsmar, Pinellas County, Polk County, Pasco County Coordination with the Tampa Bay Regional Planning Council and Hillsborough County Hazard Mitigation Group Tampa Electric Company - 2009 Hurricane Season Preparation

13 Coordination Planning and Coordination with Governmental Agencies Participation in Storm Preparedness Workshops US Coast Guard Tabletop City of Tampa Mock Storm Exercise Hillsborough County Mock Storm Exercise City of Tampa Mass Casualty Exercise Tampa Electric Company - 2009 Hurricane Season Preparation

14 Pre-Storm Preparation Tampa Electric Company - 2009 Hurricane Season Preparation ED Mock Storm Exercise May 14, 2009 - ED Call-out Group VP ED and direct reports Functional ED departments Customer Service Corporate Communications Emergency Management IT, Telecom, Treasury Conducted mock storm circuit patrol training Review and order storm material inventory Conduct mock storm exercise Updated Storm damage model Reviewed, updated and exercised disaster recovery plans Reviewed, updated and synchronized circuit priorities with Hillsborough County EOC

15 Tampa Electric Company - 2009 Hurricane Season Preparation Summary Inspections & Repairs Vegetation Management Storm Hardening Plans Improved Coordination Training & Pre-Storm Season Activities Ready for 2009 Storm Season


Download ppt "Tampa Electric Company 2009 Hurricane Season Preparation Regan Haines Director, Energy Delivery May 6, 2009."

Similar presentations


Ads by Google