Overview and status of international systems Reminder of the principal deliverables Status reports on: Spectrometer solenoids Radio Frequency Coupling.

Slides:



Advertisements
Similar presentations
1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
Advertisements

Coupling Coil Test Facility Update Ruben Carcagno Fermilab September 20, 2012.
Status of the AFC at RAL Tom Bradshaw John Cobb Wing Lau Matt Hills Elwyn Baynham Mike Courthold Victoria Bayliss MICE Project Board 28 th June 2011.
MICE Superconducting Solenoids: Status and Update RAL: T W Bradshaw M Courthold J Rochford M Hills D Baynham Oxford: J Cobb W Lau S Yang MICE.
Plans for 201-MHz Cavities Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory November 18, 2010.
Trip Report on the visit to ICST of HIT, Harbin, China Derun Li Mike Green Steve Virostek Mike Zisman Lawrence Berkeley National Laboratory (from December.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
Spectrometer Solenoid Design and Procurement Review Steve Virostek Mike Green Mike Zisman Lawrence Berkeley National Lab MICE Collaboration Meeting October.
Spectrometer Solenoid Report and Coupling Coil Update Michael S. Zisman MICE Operations Manager Center for Beam Physics Lawrence Berkeley National Laboratory.
Cooling Channel Summary Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICE Collaboration.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 14, 2009.
9 June 2006MICE CM-15 Fermilab1 Progress on the MICE Cooling Channel and Tracker Magnets since CM-14 Michael A. Green Lawrence Berkeley Laboratory.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
1 MICE Project Board Schedule and milestones Reconstructing the schedule Present status Monitoring and feedback Key schedule drivers and concerns Andy.
1 MICE Funding Agency Committee PM report Overview Organisation and project management Schedule reconstruction The Step IV subsystems Andy Nichols, STFC,
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM24 at RAL June 1, 2009.
1S. Virostek - LBNL Spectrometer Solenoid Fabrication Update Vendor still expecting to complete first magnet by the end of November, before X-mas more.
RFCC Module Tech Board Schedule Discussion Steve Virostek Lawrence Berkeley National Lab MICE CM25 at RAL November 4, 2009.
Spectrometer Solenoid and RFCC Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Spectrometer Solenoids and Coupling Coils Primary Activities and Risks Going Forward Spectrometer Solenoids Completion of SS#2 magnetic mapping Completion,
RF Cavity / Coupling Coil Module
PM report International MICE programme Principal deliverables Schedule summary Schedule considerations and drivers Status of SS, RFCC and EMR, LH2 & LiH.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab Roy Preece Rutherford Appleton Lab October 28, 2011 MICE Collaboration Meeting.
Office of Science 3/8/ LBNL MICE Project Status Spectrometer Solenoids, Coupling Coils and RFCC Modules Steve Gourlay MICE Project Board March.
1 MICE CM32 Summary Scheduling and planning; aims for this year Schedule update Main schedule drivers Keeping us on schedule Comment on Steps V & VI Detail.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MAP Winter Collaboration Meeting at JLab, Virginia February 28, 2011.
1 PM report International & UK programmes Overview Reconstructing the schedule The UK Project Management team Progress with major subsystems Substation.
UKNF/MICE PSAG, 3/5/11 Spectrometer solenoids: –Repair plan still ‘in approval’, already two months late –Workshop/mini review at LBNL 10 th /11 th May.
1 MICE PSAG PM report Brief overview Re-planning the project Solenoids, decay and spectrometer Open issues and worries Andy Nichols, STFC, PSAG, 5/5/10.
MICE Coupling Coil Update Steve Virostek for Allan DeMello Lawrence Berkeley National Laboratory MICO January 23, 2013 January 23, 2013.
1 MICE CM28 PM Report Progress since CM27 Schedule, dates, milestones Electrical substation Visiting RAL Andy Nichols, STFC 4 th October 2010.
The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration.
Technical Board and Safety Summary Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
Spectrometer Solenoid Overview Roy Preece 31 st January 2011.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
MICE Cooling Channel Magnets: Spectrometer Solenoid Procurement RF Module Coupling Coil Proposal Steve Virostek Lawrence Berkeley National Lab NFMCC 07.
Magnet vacuum vessel w/radiation shield and cold mass in place Magnet leads (left) and the three cryocoolers on the top of the spectrometer solenoid service.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM29 at RAL, UK February 17, 2011.
1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
MICE RF Cavities and RFCC Module Update Allan DeMello and Derun Li Lawrence Berkeley National Laboratory MICE CM32 at RAL, UK February 9, 2012 February.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
MICE Oversight Committee Meeting RAL, 24 April 2014 Paul Soler on behalf of the MICE Collaboration Status of MICE and Spectrometer Solenoids.
MICE Coupling Coil Testing at Fermilab All Experimenters Meeting Ruben Carcagno March 19, R. Carcagno - MICE CC Testing at Fermilab3/19/2012.
Spectrometer Solenoid Fabrication Status and Schedule RF Cavity / Coupling Coil Module Plan and Progress Steve Virostek Lawrence Berkeley National Lab.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
MICE VC Alain Blondel 1 1. MOM is now Victoria 2. Linda Coney is new MICE Online Group coordinator (rep Jean-Sebastien) May we held.
Muon Ionization Cooling Experiment Update 1Alan Bross AEM October 14, 2013.
MICE Prototype Coupling Coil Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM38 - Napa California February 25, 2014 February.
1 MICE Schedule Review no 1 Aims of review and description of review charge Motivation and external drivers Aims of the review A few of the problems Description.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory Oxford, UK July 7, 2011 July 7, 2011.
Progress on MICE RFCC Module for the MICE Experiment * Allan DeMello, Nord Andresen, Michael Green, Derun Li, Heng Pan, Steve Virostek, Michael Zisman.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
MICE Coupling Coil Update Allan DeMello Lawrence Berkeley National Laboratory Illinois Institute of Technology June 17, 2013 June 17, 2013.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
MICE Coupling Coil Vacuum Vessel Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory Coupling Coil Working Group January 28, 2014 January.
RFCC Engineering Status and Plans Allan DeMello Lawrence Berkeley National Laboratory MAP Winter Meeting March 6, 2012 March 6, 2012.
1 MICE Coupling Coil Cryostating and Test Steve Gourlay March 1, Office of Science.
1 MICE CM29 Engineering Summary Cooling channel moving platforms – Norbert Floor Beams and plates – Andy L Magnetic modelling – Mike RF Engineering – Andy.
UK Project Plan Roy Preece STFC RAL RLSR 26 th October 2015.
Status of the MICE Construction Project
MICE CM31 Schedule summary
Spectrometer Solenoid Fabrication Status and Schedule
MICE Coupling Coil Update
Presentation transcript:

Overview and status of international systems Reminder of the principal deliverables Status reports on: Spectrometer solenoids Radio Frequency Coupling Coils (RFCC) Electron-Muon Ranger (EMR) Absorbers, liquid and solid Conclusion Acknowledgements to Steve Gourlay, Ruslan Asfandiayarov, Alan Bross, Ruben Carcagno, Steve Virostek, Alan DeMello 1 Andy Nichols, STFC, MICE OsC,

Principal deliverables EMR (Electron Muon Ranger) UNIGE responsibility, in manufacture, recent injection of manpower Q SS (Spectrometer solenoids) First magnet ready for mapping, second in advanced state of construction Q3, 2013 RFCC (Radio Frequency Coupling module) Cryostat/cold mass parts now in manufacture at LBNL, very good news – assembly plan for all three magnets in US is advanced but not complete. Cavities are being electro-polished, tuning mechanisms well advanced LHe cooling pipe leak now by-passed, first coil test underway RFCCs are the main driver for MICE Steps V & VI Other international equipment is now covered by M&O But owners are still engaged, eg INFN for TOF/KL & UMISS for cKOV 2

Principal deliverables Liquid hydrogen absorber #1 Required for Step IV Delivered for some time, but… Much work required to understand integration Liquid hydrogen absorber vessel #2 Required for MICE Step V In manufacture at KEK, update required LiH absorber US responsibility – has been complete for sometime MOU between US and UK under construction When this is done, risk assessment for acceptance can begin 3

Spectrometer solenoids Main points to note: Magnet #1 has passed its acceptance criteria Decision taken by MICE to do mapping at US rather than UK- had hoped to save time CERN mapping gear being shipped now, CERN magnet Group will arrive when we know exact arrival date Virostek shielding needs fitting, will be shipped soon, Tim & Roy will assist Then it’s ready for mapping Second magnet going well, cold mass is wrapped and inserted in vessel services turret is being assembled on bench and may well be fitted by now 4

5 Much activity at Wang NMR Training and assembly in parallel No shortage of effort! Significant support from DL Controls Group

RFCC/Coupling magnets Progressing on four fronts: Cold mass test at FNAL – plan is to train coil before final assembly into magnet Vessel fabrication at LBNL Coil winding at Qi-Huan – successful review held in December last, main driver is obviously successful training of first coil Cavity production at LBNL – electro-polishing, completion of electro- mechanical tuners

Cooling Pipe Leak 7 Problem with leaky cooling tube Solved with by-pass pipe Has passed FNAL PED

8 Wrapped and unwrapped cold mass On lid supports ready for insertion] Into cryostat This is a significant piece of work

9 Warm test stand commissioning starting this week Cold test stand commissioning and coil cooldown will start as soon as CHL has enough Liquid Helium to support cold operations – CHL startup activities underway – LHe at CHL expected by April 24, 2013 Powered operations expected to start ~ 2 weeks after the start of cold commissioning – Controlled cooldown may take a long time (LBNL model estimate: 2.5 days. First time cooldown may take a week or so) – Week of May 6th? Estimate two months of testing for coil training, including a thermal cycle Commissioning of a new test stand and test of first of a kind coil adds substantial uncertainty to the schedule

10 Vessel fabrication, for three magnets; material delivered to LBNL, 12 th February Fabrication and machining complete in six months – very ambitious indeed

Progress with EMR 11 Increased technician effort at UNIGE Work concentrating on fibre bundles, 20/96 complete as of March All scintillator bars are ready for assembly Delivery to RAL scheduled for mid-June Will aim to run with EMR before Summer ISIS shutdown But we have not yet planned detail work in R.2 for that period yet

Solid absorbers 12 Procured through Y12: – 1 – 20 cm diameter by 4 cm thick disk For thermal studies – cm diameter by 6.5 cm thick disk – 2 half-wedges Disks complete – Thermal measurements complete Meet spec. Wedges still in fab at Y12 – Negotiating a cost to complete CRADA is being negotiated between FNAL And STFC for delivery Process for acceptance and risk assessment cannot begin till we know How it arrives

Liquid and solid absorbers Liquid absorber #1 has been unpacked Very rudimentary check with FC done One pipe might need to ‘persuaded’ Handling/insertion tool required No major worries….. Liquid absorber integration needs to be defined as an engineering package, many interface-type issues: Services, cables, pipes Sealing Pressure testing and PED acceptance Handling and alignment AND, we need to work out how to import the thin windows from LBNL/Mississippi Lithium hydride absorber holder is complete and ready for use 13

Conclusion Very encouraging news with the spectrometer solenoids; injection of engineering effort and realistic planning has paid off Not sure if field mapping in US will save any time or effort, but we’re doing it as the SS is ready and the FC is not The RFCCs are also on a much better engineering footing: Coil #1 test is impressive and training outside the vessel very sensible CC magnet schedule for series production though is very aggressive ‘Administrative’ processes may yet hold us up though: Avoidance of VAT in UK – historic agreement has been rescinded by HMRC Import of LiH and safety framework Import of thin windows