Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT November 20, 2013.

Slides:



Advertisements
Similar presentations
What Makes Up a FAS Package
Advertisements

Right of Way Acquisition Process Jesse W. Smith Right of Way Manager.
Section 12 Under Construction. Your role as the owner What to expect at the preconstruction meeting Dos and Dont during construction How to handle change.
Constructability Review
Contract and Grant Provisions and Administration Section 105 (Page 30) Title I The Act.
Presentation by: Tshewang Gyeltshen. The SBD is prepared in line with the PRR 2009 & SBD Large Works General principals of procurement to be applied prescribed.
LPA – Utility Coordination Natalie Parks, P.E. American Structurepoint, Inc. January 22, 2014.
Standards Aligned Systems MANDATE WAIVER PROGRAM 2008.
With the Genesee County Road Commission By Fred Peivandi, P.E. And Ken Johnson, P.E. Local Road Funding.
Coordinating with Project Manager Cindy Kowalski, PMP Utility Coordinator, Parsons December 2013.
OVERSIGHT & COMPLIANCE BRANCH (OCB) INVOICE PAYMENTS February 16,
Project Close Out CTC-470.
Review of 2010 Biennial Audit of Capital Projects Cyndi Fout Project Services Director February 28, 2011.
Greenfield District Utility/RR Engineer, INDOT
Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015.
GANTT CHARTS & SCHEDULES Chris Hammond, P.E. Transportation Department Manager, United Consulting August 27, 2014.
LPA – Utility Coordination Natalie Parks StructurePoint November 20, 2013.
A New Paradigm for Utility Coordination Kenny Franklin INDOT Director of Utilities and Railroads.
Coordinating with Project Manager Cindy Kowalski, PMP Utility Coordinator, Parsons November 19, 2013.
1 Addendum Preparation Process ESC-OE Caltrans. 2 Introduction An addendum is a change in contract requirements for an advertised project for which bids.
IDM Chapter 104 Utility Coordination Joe Gundersen Senior Utility Engineer, INDOT August 21, 2014.
GANTT CHARTS & SCHEDULES Chris Hammond, P.E. Transportation Department Manager, United Consulting December 18, 2013.
Monitoring & Oversight Adult Education and Literacy (AEL) Programs Brenda B. Williams Project Manager Texas Workforce Commission Regulatory Integrity Division.
DEPARTMENT OF HEALTH CARE SERVICES Audits & Investigations – Financial Audits Branch Presented by: Gary Diffenderffer, CIA Health Program Audit Manager.
A New Paradigm for Utility Coordination Kenny Franklin INDOT Director of Utilities and Railroads.
Utility & Rail Coordination in Project Development Jennifer McCleve Utilities & Rail Branch Manager.
HIGHWAY/UTILITY PROGRAM OVERVIEW ROADWAY CONFERENCE APRIL 20, 2009.
PLANNING DEPARTMENT CITY OF PEARLAND PLANNING DAY MARCH 13, 2008.
Insights from a Former Federal Auditor Briget Biernat Jans Director of Financial Aid Compliance DePaul University.
Research Phase, Indiana 811, Initial Notice, Verification Deborah Porter Project Engineer/Utility Coordinator Clark Dietz, Inc.
Project management Dr. Khaled Bubshait 1 Dr. Khaled A. Bubshait Project Management.
IDM Chapter 104 Utility Coordination Joe Gundersen Senior Utility Engineer, INDOT November 19, 2013.
Genesee County Road Commission Fred Peivandi, P.E. County Highway Engineer MTPA July 15, 2011 TIP Project Administration.
SPS policy – Information Presentation Presentation to ROS June 16, 2004.
Contract Training Class I
HiLumi LHC is co-funded by the EU FP7 Capacities Programme, Grant Agreement Svet Stavrev (EU Projects Office, CERN) Administrative Manager 17.
IDM Chapter 104 Utility Coordination Gail Lee Utility and Railroad Engineer, INDOT June 10, 2015.
DEPARTMENT OF HEALTH CARE SERVICES Audits & Investigations – Financial Audits Branch.
Highway Utility Engineer, INDOT
Construction Review LaVon M Marshall Greenfield District Utility/RR Engineer, INDOT June 11, 2015.
LPA – Utility Coordination Natalie Parks, P.E. American Structurepoint, Inc. December 19, 2013.
“SPEAR” W ORKSHOP O CTOBER 19 & 30, 2015 ANGELLE GOMEZ S UBAWARD R ISK A SSESSMENT / MONITORING.
Plans of Correction (PoC) Donna Tiberi, RN Standards Interpretation p: e: 1.
Contract Compliance Training. Department Personnel Office of the General Counsel (OGC) Mario K. Castillo General Counsel John Guest Deputy General Counsel.
Improving Compliance with ISAs Presenters: Al Johnson & Pat Hayle.
Coordinating with Project Managers Cassie Reiter, P.E., ENV SP Utility Coordinator/Project Manager CMT Engineers and Consultants June 2016.
Heritage Trust Fund Grant Orientation Session. HTF Staff and Contact Information Katrina Ringler Grants Manager ext. 215
Department of Child Support Services OFFICE OF AUDITS AND COMPLIANCE.
Gantt Charts & Schedules Mike Hoy Utility Engineer, INDOT June 22, 2016.
IDM Chapter 104 Utility Coordination Gail Lee Highway Utility Engineer, INDOT June 21, 2016.
A New Paradigm for Utility Coordination Kenny Franklin VP of SUE Development Blood Hound.
Miscellaneous Property Insurance
Construction Oversight
2012 Business Guidelines for Association Membership
Grant Orientation Session
Lesson 4 Systems Engineering Plan Exercise Team #
Overview of Stakeholders and Key Roles
Training Appendix Revised January 2018.
THE OFFICE OF PROCUREMENT CONTRACT TRAINING MAY 2018
Force Accounts.
Taking a stroll through a term
Handling offers.
Research Phase, Indiana 811, Initial Notice, Verification
Grant Orientation Session
Aschalew Aberra, P.E. Senior Utilities Engineer INDOT June 14, 2017
Construction Review.
Work Plan Development.
A Paradigm for Utility Coordination
105 Indiana Administrative Code Article 13
Project Manager / Utility Liaison
Presentation transcript:

Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT November 20, 2013

Outline Learning objectives –why work plan? Top five reasons why a work plan is important What are the recent updates? Target date, signing first or second page, emergency contact, pre-construction & post construction activity, etc. Work plan development (Process): preparation, review, revision & approval. Practical exercise 2

It is the Law! 105 IAC (b) (1): A work plan shall be submitted whether or not any facility relocations are required. It is not a matter of opinion or an option, it is the LAW. Utilities are obligated to submit their work plans in order to accommodate a highway improvement project.

Focus on deliverables Target out of conflict date. Pre-construction schedule. Construction schedule. Relocation drawing. Cost estimate & proof of property interest.

A signed commitment/contract A work plan is a signed commitment by a utility to accurately relocate its facilities on schedule. Projects are let based on information obtained from utility work plans. A utility shall be held accountable, for utility related delay claims.

No surprises! Work plan is a major tool to avoid surprises during construction. The utility team shall demonstrate due diligence in reviewing & approving work plans. Last chance before construction stage!

Use of work plan as an input Utility risk management report. Gantt chart. Utility special provision. Utility coordination certificate.

A tool for resolution of scheduling and location conflicts

Preamble 105 IAC : Work plan is defined as a plan of the utility to carry out facility relocation to accommodate an improvement project. Use preliminary final project plan (Stage 3/90%). Prepare and send letter Request Work Plan. Use the most recent work plan template. Go to the INDOT website.

When is a work plan due? Sixty (60) days for a minor project; and One hundred twenty (120) days for a major project. An additional thirty (30) days will be allowed to furnish the work plan if coordination is required with another utility or utilities. If a work plan is not received on time: contact the authorized representative and notify the oversight agent.

Work plan revision Non compatible work plans shall be returned to the utility immediately. The utility shall submit a revised work plan within 30 days. If the revised work plan is not compatible, the UC will prepare an alternate work plan. The utility shall accept/make changes to the alternate plan within 30 days. 11

Section 1: General Information 12

General info……cont’d 13

Section 2: Location info. 14

Section 3 & 4 Property interest & Work in contract 15

Section 5: Pre-construction 16

Section 6: Construction 17

Section 7, 8, & 9: Attachments 18 $500, (Not Reimbursable)

Work Plan Review Ensure each work plan is compatible with: INDOT permit requirements The project plans The construction schedule Other utility relocation work plans Ensure the relocation scheme and cost for compensable work is reasonable 19

Section 10 & 11: Approval 20

Work plan addendums: Addendums can either be INDOT initiated or utility initiated. A utility shall submit a revised work plan with a new cost estimate (if reimbursable). The utility coordinator shall review the addendum; and send it to the approval of the oversight agent. If an addendum is issued during construction, a copy shall be sent to the construction engineer. 21

Questions? 22 Questions?

Practical Exercise Group exercise Identify 3 or 4 items that need to be corrected.