Information Technology Project Management By Denny Ganjar Purnama, MTI Universitas Pembangunan Jaya April 2014.

Slides:



Advertisements
Similar presentations
Chapter 3 Managing the Information Systems Project
Advertisements

Scheduling the Project
MEM 612 Project Management Chapter 5 Scheduling the Project.
Scheduling The Project  Scheduling Planning, budgeting and scheduling are all part of the same process Planning a project, developing a budget for it,
Chapter 10: Project Schedule Planning
1 Project Management Principles ΥΠΕΥΘΥΝΟΣ: Θ. ΜΑΝΑΒΗΣ Lecture 3 – Planning and Scheduling.
Project Scheduling: Networks, Duration estimation, and Critical Path.
MGMT 483 Week 8 Scheduling.
SW Project Management Project Schedule and Budget
Dr. Neal CIS 480 MS Project Concepts Dr. Greg Neal CIS 480 Systems Analysis and Design.
Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.
Project Time Management
Importance of Project Schedules
Information Technology Project Management
Project Time Management
Managing Project Scheduling. What is Project Scheduling? The process of: – defining project activities – determining their sequence – estimating their.
Chapter 6 Introduction to Microsoft Project
Information Technology Project Management
HIT241 - TIME MANAGEMENT Introduction
© 2006 ITT Educational Services Inc. System Analysis for Software Engineers: Unit 5 Slide 1 Chapter 3 Managing the Information Systems Project.
Software Project Management Task Sequencing Activity Sequencing Concepts PERT charts Critical Path Analysis.
Chapter 3 : Managing the Information Systems Project.
Time Management Week 7 - Learning Objectives You should be able to: n List and describe the processes, activities, inputs, and outputs in time management.
Abeer Bin Humaid. Project management is “the application of knowledge, skills, tools, and techniques to project activities in order to meet project requirements”
Scheduling Sequence & Time.
1-1 Information Technology Project Management by Jack T. Marchewka Power Point Slides by Richard Erickson, Northern Illinois University Copyright 2003.
Lecture 5 Title: Project Time Management By: Mr Hashem Alaidaros MIS 434.
POST GRADUATE PROGRAM OF INFORMATION TECHNOLOGY
EGNR 300 Project Management Planning & Scheduling ENGR 300 Dept. of Computer Science and Engineering University of Bridgeport,
Project Schedule and Budget 1. T HE P ROJECT P LANNING F RAMEWORK 2.
MS project Abeer Bin Humaid. What is project management? Project management is “the application of knowledge, skills, tools, and techniques to project.
The Project Schedule and Budget
© Construction Management Association of America. Do Not Duplicate or Reproduce. Standards of Practice Course CPM Scheduling Lab.
Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.
Software Project Management
By Ctrl+C & Ctrl+V. Project Schedule & Budget: Project plan contains all of the details of the project’s schedule & budget. It will be used to guide the.
PMP, CAPM, PgMP, PMI-SP, PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services.
Advanced Project Management Project Time Management Ghazala Amin.
Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.
Project Management Part 5 Project Scheduling. Topic Outline: Project Scheduling Identifying relationships among activities Project network diagrams Identifying.
Richard Fisher 1 The University of Texas at Dallas Project Management Richard Fisher The University of Texas at Dallas.
Richard Fisher 1 The University of Texas at Dallas Project Management Richard Fisher The University of Texas at Dallas.
Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.
Chapter 3 Managing the Information Systems Project
Information System Project Management.  Some problems that org faced with IS dev efforts include schedule delays, cost overrun, less functionality than.
Chapter 6: Project Time Management Information Technology Project Management, Fourth Edition Using Critical Path and MS Project 2003 Tuesday, February.
MEM 612 Project Management Chapter 5 Scheduling the Project.
CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)
Chapter 7 – PERT, CPM and Critical Chain Operations Management by R. Dan Reid & Nada R. Sanders 4th Edition © Wiley 2010.
Project Time Management Ashima Wadhwa. Schedule Development – Determining start and finish dates for project activities – Without realistic dates, project.
Project Management Concepts Gantt Chart – shows tasks as bars whose length indicates timing. PERT* chart (Network Diagram) – shows relationships between.
PERT Gantt WBS.
Information Technology Project Management – Fourth Edition By Jack T. Marchewka Northern Illinois University Power Point Slides by Gerald DeHondt Grand.
BET2413 Project Scheduling Lecture 6: Relationships in Project Network.
Project Time Management Based on PMBOK 5 th Edition Abdelrahman Sheta, PMP,ITIL 1PMP - Project Time Managementfacebook.com/Sheta.Page.
Managing the Information Systems Project Cont’d
Project Management MGT 30725
Business System Development
The Project Schedule and Budget
The Project Schedule and Budget
Information Technology Project Management – Fifth Edition
Information Technology Project Management
CHAPTER 6 PROJECT TIME MANAGEMENT
Project Time Management
Information Technology Project Management – Fourth Edition
Project Time Management
Project Time Management
Project Time Management
Project Time Management
CHAPTER 6 PROJECT TIME MANAGEMENT
Presentation transcript:

Information Technology Project Management By Denny Ganjar Purnama, MTI Universitas Pembangunan Jaya April 2014

Chapter 7 The Project Schedule and Budget

Learning Objectives Describe the Project Management Body of Knowledge (PMBOK®) called Project Cost Management. Develop a Gantt chart. Develop a project network diagram using the activity on the node (AON) technique. Identify a project’s critical path and explain why it must be controlled and managed. Develop a PERT diagram. Describe the concept of precedence diagramming and identify finish-to-start, start-to-start, finish-to-finish, and start-to-finish activity relationships. Describe the various costs for determining the project’s budget. Define what is meant by the baseline project plan.

The Project Planning Framework

PMBOK® Project Cost Management Resource planning Cost estimating Cost budgeting Cost control

Schedule Development Put it all together to determine the start and end dates for the project Iterations may be necessary A realistic project schedule is the goal!

Developing the Project Schedule Project Management Tools –Gantt Charts –Project Network Diagrams Activity on the Node (AON) Critical Path Analysis Program Evaluation and Review Technique (PERT) Precedence Diagramming Method (PDM)

Gantt Chart for Planning

Gantt Chart Reporting Project’s Progress

Activity Analysis for AON (Activity On the Node) ActivityDescriptionEstimated Duration (Days) Predecessor AEvaluate current technology platform 2None BDefine user requirements5A CDesign Web page layouts4B DSet-up Server3B EEstimate Web traffic1B FTest Web pages and links4C,D GMove web pages to production environment 3D,E HWrite announcement of intranet for corp. newsletter 2F,G ITrain users5G JWrite report to management1H,I

Activity on the Node (AON) Network Diagram

Possible Activity Paths Possible PathsPathTotal Path 1A+B+C+F+H+J Path 2A+B+D+F+H+J Path 3A+B+D+G+H+J Path 4A+B+D+G+I+J19* Path 5A+B+E+G+I+J

Critical Path Longest path Shortest time project can be completed –Zero slack (or float) The amount of time an activity can be delayed before it delays the project Must be monitored and managed! –Project manager can expedite or crash by adding resources –Fast tracking – running activities in parallel which were originally planned as sequential –The CP can change –Can have multiple CPs

PERT Program Evaluation and Review Technique Developed in 1950s to help manage the Polaris Submarine Project Developed about the same time as the Critical Path Method –Often combined as PERT/CPM Employs both a project network diagram with a statistical distribution

Activity Analysis for PERT ActivityPredecessorOptimistic Estimates (Days) Most Likely Estimates (Days) Pessimistic Estimates (Days) Expected Duration (a+4b+c) 6 ANone BA CB DB EB FC,D GD,E HF,G IG JH,I

Possible PathsPathTotal Path 1A+B+C+F+H+J Path 2A+B+D+F+H+J Path 3A+B+D+G+H+J Path 4A+B+D+G+I+J20.5* Path 5A+B+E+G+I+J Possible PERT Activity Paths

Precedence Diagramming Method - PDM Based on 4 fundamental relationships –Finish-To-Start (FS) –Start-To-Start (SS) –Finish-To-Finish (FF) –Start-To-Finish (SF)

PDM Relationships

Lead and Lag times Lead is starting the next task before the first task is complete Example: Begin installing the operating systems when half of the PCs are set up Lag (or negative lead) is the adding of a buffer of time before the next task begins Example: Once the walls have been painted, wait one day before laying the carpet so that the walls have had a chance to dry

Developing the Project Budget 1.Define what resources will be needed to perform the work 2.Determine the quantity of resources that are needed 3.Define the cost of using each resource 4.Calculate the cost of the task or activity 5.Ensure that the resources are leveled, that is, resources have not been over allocated assigned to more than one task scheduled at the same time

Project Management Software Tools A number of project management software tools are available to plan and track the progress of your project However, having a fundamental understanding of these project management techniques is important to make the most of these software tools

Microsoft Project ® 2003 Gantt Chart View

Microsoft Project® 2003 PERT Chart View

Microsoft Project® 2003 Calendar View

Microsoft Project® 2003 Adding Resources to A Project

Microsoft Project® 2003 Project Status

Finalizing the Project Schedule and Budget The project schedule and budget may require several iterations before it is acceptable to the sponsor, the project manager, and the project team Once the project schedule and project plan are accepted, the project plan becomes the baseline plan. Once accepted, the project manager and project team have the authority to execute or carry out the plan.