STATUS OF CF CO-FUNDED PROJECTS 11 April 2008 AIVARS JURJĀNS Ministry of Environment Head of Projects Implementation Department.

Slides:



Advertisements
Similar presentations
Central Office for Development Strategy and Coordination of EU Funds ABSORPTION CAPACITY FOR IPA COMPONENTS III AND IV IN CROATIA 19 October 2009 Zvonimir.
Advertisements

Evaluation Plan in Hungary Dr. Tamás Tétényi Head of Department for Strategy and Evaluation National Development Agency.
Floyd County Board of Commissioners Special Town Hall Meeting Topic: Update on status of Georgetown WWTP.
Development of Ventspils District Heating System in Latvia 2005/LV/16/C/PE/001.
Cohesion Fund Monitoring Committee Development of District Heating System in Ventspils, Latvia Aivars Jurjāns Director, Project Implementation Department,
Development of the Wastewater Collection and Treatment System in Szombathely County Town Implementation of sewage-sludge Composting Plant 2003/HU/16/P/PE/021.
PROJECT OVERVIEW FM Budget € Total contracted € –EU Grant € –National Co-financing –Total contracted /
Progress on developing, preparing and financing environmental investment projects REPUBLIC OF MACEDONIA.
1 MINISTRY OF REGIONAL DEVELOPMENT AND PUBLIC WORKS DIRECTORATE GENERAL PROGRAMMING OF REGIONAL DEVELOPMENT Operational Programme Regional Development.
Titlul proiectului subtitlu EU Financing in Environmental Sector during Raluca FRATILA Ministry of Environment and Forests, Managing Authority.
„Extension and modernization of water and wastewater infrastructure in Arad County”
NATO/CCMS Pilot Study Meeting on Prevention and Remediation in Selected Industrial Sectors: Mega-Sites, Ottawa, Canada 12-16, June 2005 The State of Remediation.
Support for programme and project development: JASPERS and ELENA Ralf Goldmann EMA network Meeting
MINISTRY OF TRANSPORT OF THE REPUBLIC OF LATVIA Implementation of Cohesion Fund Projects in Transport Sector Cohesion Fund Monitoring Committee 11 April.
Latvia–Lithuania Cross Border Cooperation Programme 2007–2013 WORKSHOP “How to prepare good application?” Joint Technical Secretariat 3rd.
COHESION FUND MONITORING COMMITTEE 11 April 2008 Jurijs Spiridonovs Ministry of Environment Head of Project Development Department.
Italian Ministry for the Environment, Land and Sea National Workshop: Developing Environmental Infrastructure Projects in the Waste Sector in Serbia Case.
New Decade - New Challenges Annual Conference September 2010 Water Services Training Group 14 th Annual Conference New Decade – New Challenges 9 th September.
Ministarstvo finansija Vlada Republike Srbije Instrument za pretpristupnu pomoć Instrument for Pre-Accession Assistance – IPA
Projects financing and implementation experience Dr.sc.ing. Ilze Purina Chairperson of the Board Latvian Environmental Investment Fund ____________________________.
Audits of pre-accession funds in the State Audit Office of the Republic of Latvia 2000/2001 Uldis Kremers Auditor of the Audit Department of the State.
Administrative Territorial Reform in Latvia The Ministry of Regional Development and Local Government.
EU Financing in Environmental Sector during April 2008.
Project No 2005/LV/16/C/PE/003 Development of water services in Riga, stage III This project helps to reduce economical and social disparities among the.
Latvian Education Informatisation System (LIIS) ISSS/LORIS Conference, Hradec Kralove March, 2004 Professor Juris Mikelsons.
STEPS FOR FUNDING ELI-NP March 11 st 2011 Dan Cutoiu.
Co-operation within water management sector in Latvia B.Gulbe, CEO, Latvian water and wastewater works association.
Phare 2003 Sector: Economic and Social Cohesion Title: Water Supply and sewerage in tourism and resort settlements.
A National Prioritized Project Pipeline and Environmental Operational Program Republic of Turkey Ministry of Environment and Forestry.
Public Private Partnership + EU Funds in Poland general overview and the future outlook.
Environmental Investment Centre (EIC) ISPA Unit Rävala pst 8, TALLINN Tel: Fax:
Министерство финансов Республики Узбекистан Тел.: ( ) , Министерство экономики Республики Узбекистан Тел.: ( )
8th Cohesion Fund Monitoring Committee 11 April 2008 Technical Assistance for the Cohesion Fund Management in Latvia No.2005/LV/16/C/PA/001.
Projects spanning over two programming periods Department for Programme and Project Preparation Beatrix Horváth, Deputy Head of Department Budapest, 5.
1 MINISTRY OF REGIONAL DEVELOPMENT AND PUBLIC WORKS MANAGING AUTHORITY FOR COHESION FUND (REGULATION 1164/94) MANAGEMENT OF PROJECTS, FINANCED BY COHESION.
ХVIII Meeting of the Monitoring Committee of Operational programme “Transport” – 3 June 2015 Pravets.
Progress with Priority Environmental Infrastructure Investment Projects in Croatia PEIP Regional Meeting - 26 th November 2007 Brussels MINISTRY OF ENVIRONMENTAL.
Cross-border projects 2007: Jelgava - Siauliai Jelgava city administration Liene Rulle project manager.
„Support for renovation of industrial premises”
Sustainable public transport – electric transport development project for the capital.
Structural Funds Managing Authority – Ministry of Finance 1 Technical Assistance Ilze Aleksandroviča Head of Control and Development Division EU Funds.
INTERREG IIIC - REGENERGY Promoted by the European Union Development of municipal District heating supply in Latvia Gaidis Klavs Institute of Physical.
1 Maribor Wastewater Treatment Plant Presentation of PPP Model in Maribor - Slovenia Conference Danilo ŠALAMON – Chief of the Infrastructure projects Department.
Statistical office of Montenegro (MONSTAT) & Environmental Protection Agency of Montenegro (EPA) GENEVA, 04 November 2013.
Implementation progress of Activities within the competence of the Ministry of Health.
BOSNIA AND HERZEGOVINA MINISTRY OF FINANCE AND TREASURY Aid Coordination and Effectiveness activities in DCF Meeting Sarajevo, 24 February 2009.
The Cohesion Fund in Poland and the Selection System for Environmental Investments Andrzej Guła Institute of Environmental Economics – Poland CEE Bankwatch.
Latvian Education Informatization System (LEIS) Strategy, Results, Perspective LEIS project laeder Jānis Bičevskis, University of Latvia,
9 th Cohesion Fund Monitoring Committee CR 1164/94 ISPA Measure 2002 BG 16 P PE 018 Shoumen Water Cycle Improvements.
Ing. Alena Bujnová, Head of Water Policy Department Ministry of Environment of the Slovak Republic.
WASTEWATER TREATMENT PETRIT TARE GENERAL DIRECTOR OF UKKO JSC CONFORMING TO EU WASTEWATER TREATMENT DIRECTIVE CASE STUDY OF KORCA CITY, ALBANIA.
TAIEX – REGIO Multi Country Workshop on management practices for environmental investments 8-9 December 2015, Vilnius Presentation by BULGARIA Ministry.
Lithuanian Water Suppliers Association LEGAL REGULATION OF WASTEWATER DISPOSAL AND TREATMENT IN LITHUANIA.
The Central purchasing in Bulgaria: Current status and prospective TAIEX Seminar 9-10 December 2015 Ivanina Beleva Director of the Central Purchasing Body.
Ministry of Finance Compliance assessment of the management and control systems of the managing authorities under the Operational programmes. Conclusions.
1 Financing in water sector - times of change Antti Tooming Ministry of the Environment / Water department, Head of Project bureau 19/05/2016.
MINISTRY OF ENVIRONMENTAL PROTECTION AND REGIONAL DEVELOPMENT OF THE REPUBLIC OF LATVIA 1 ENVIRONMENTAL ISSUES – PROGRESS IN WATER, WASTE WATER AND WASTE.
Overview on current situation and priorities in military sites of Latvia Daina Galaktionova, Head of Environment Division, Real estates management department.
Structural Funds Programming Predeal, Romania
National Administration “Romanian Waters” NARW Bucharest - Romania
GOOD PRACTICES AND REFORM OF PUBLIC ADMINISTRATION
Lithuanian Energy Institute
Water projects under The Cohesion Fund.
PUBLIC PROCUREMENT SYSTEM IN UZBEKISTAN
COHESION FUND MONITORING COMMITTEE
Ilze Danga Chief Economist of the Budget Division
Instrument za pretpristupnu pomoć
ANALYSIS OF FIRE SAFETY SYSTEMS IN THE MUNICIPALS OF LATVIA: THE POSSIBILITY OF BUILDING NEW FIRE STATIONS Jānis Bartušauskis, Riga Technical University.
STATUS OF CF CO-FUNDED PROJECTS
Brief overview of the environment sector in Serbia
Presentation transcript:

STATUS OF CF CO-FUNDED PROJECTS 11 April 2008 AIVARS JURJĀNS Ministry of Environment Head of Projects Implementation Department

2 Within the framework of CF projects approved in :  A total of 210 agreements signed in the value of EUR 504 M (incl. VAT)  A total of 109 agreements completed in the value of EUR 219 M (incl. VAT)  It is planned to organize another 30 procurements The main problem affecting the timeframe for implementation of the projects is increase in construction costs. Finding solution to this increase in costs delays the signing of procurement agreements. STATUS

3 Development of water supply and sewage services in Riga, No.2000/LV/16/P/PE/001  Status of agreements: All agreements in the framework of the project (1 works and 1 services agreement) are completed.  Winding-up report and final declaration of expenditure of the project were submitted to the Ministry of Finance on 26 March 2008

4 Development of water supply and sewage services in Jelgava, No.2000/LV/16/P/PE/002  Status of agreements: All agreements in the framework of the project have been completed (2 works agreements, 2 supplies agreements and 3 services agreements).  Winding-up report and final declaration of expenditure of the project were submitted to the European Commission on 31 January  No comments have yet been received from the Commission.

5 Solid waste management in Liepāja district, No.2001/LV/16/P/PE/005  Status of agreements: All agreements in the framework of the project have been completed (2 works agreements, 2 supplies agreements and 1 services agreement).  Winding-up report and final declaration of expenditure of the project were submitted to the European Commission.

6 Technical assistance for environment projects in Latvia, No.2000/LV/16/P/PA/001  Status of agreements: All agreements in the framework of the project (8 services agreements) have been completed.  On 26 March 2008, the Ministry of Environment repeatedly submitted to the Ministry of Finance a revised winding-up report and final declaration of expenditure of the project.

7 Development of water services in the river basins of Eastern Latvia, No.2001/LV/16/P/PE/007 (I)  Work performed since 01/11/2007: Extension and reconstruction of water pipes and sewage networks in Salacgrīva, Sigulda, Ķegums, Priekuļi, Lielvārde, Valmiera, Alūksne, Preiļi, Cesvaine, Valka and Smiltene. Status of agreements:  45 agreements were signed in the framework of the project :  2 services and 2 supplies agreements;  13 agreements on renovation and construction of waste water treatment facilities;  21 agreements on extension and reconstruction of water pipes and sewage networks;  7 agreements on construction of preparation equipment for drinking water – in Smiltene, Sigulda, Valmiera, Lielvārde, Ogre, Valka, Preiļi, Cesvaine, Dagda.  In Q2 and Q3 of 2008 it is planned to launch 8 procurement procedures: 1 on renovation and construction of waste water treatment facilities – in Cesvaine; 3 on construction of preparation equipment for drinking water – in Alūksne, Salaspils, Līvāni. (By the end of April 2008 it is planned to sign agreements on construction of preparation equipment for drinking water in Salacgrīva and Ķegums).

8 Development of water services in the river basins of Eastern Latvia, No.2001/LV/16/P/PE/007 (II) Topical problems :  Increase in costs has been identified in procurement tenders of the project – EUR 12,997, more compared to the European Commission Decision. According to paragraph 25 of Minutes No.9 of the Cabinet sitting of 12/02/2008, additional state budget funding was allocated to the project for covering the increase in costs on condition that the beneficiaries would co-finance EUR 2, of the increase in costs. Increase in costs : EUR 12,997,  State budget (~81%): EUR 10,542,  Beneficiaries (~19%): EUR 2,455,368.48

9 Jūrmala water services development, No.2001/LV/16/P/PE/008  Work completed since 01/11/2007: Implementation of the agreement “Jūrmala water services development”, No.2001/LV/16/P/PE/008-4 has been completed  Status of agreements: All agreements in the framework of the project (3 works agreements and 1 services agreement) have been completed.  Winding-up report and final declaration of expenditure of the project were submitted to the Ministry of Finance on 26 March 2008.

10 Development of water services in Rēzekne, No.2002/LV/16/P/PE/009  Status of agreements : 2 works agreements (1 networks and 1 drinking water) and 1 supplies agreement have been implemented. Implementation of 1 works (WWTP) agreement and 1 services agreement (construction supervision) continues (until 11 August 2008).

11 Solid waste management in Austrumlatgale region, No.2002/LV/16/P/PE/010  Status of agreements: All agreements in the framework of the project (1 supplies, 1 works and 1 services agreement) are completed.  Winding-up report and final declaration of expenditure of the project were submitted to the Ministry of Finance on 25 March 2008.

12 Solid waste management in Dienvidlatgale region, No.2002/LV/16/P/PE/011 (I)  Status of agreements: All agreements in the framework of the project (1 supplies, 1 works and 1 services agreement) are completed.  Winding-up report and final declaration of expenditure of the project were submitted to the Ministry of Finance on 26 March 2008.

13 Technical assistance for environmental sector in Latvia, No. 2003/LV/16/P/PA/008  Proposals for modifications of the Financing Memorandum have been sent to the Ministry of Finance. The modifications of the Financing Memorandum suggest extending the project end date to 31/12/2009 and adding 3 components to the project: Development of a sewerage system model in Jelgava Implementation and extension of data transmission system (Daugavpils) 88 agglomerations (assessment of investments).  On 21 December 2007 letter No was received from the European Commission informing that the proposals for modifications of the Financing Memorandum will be supported and that the EC is preparing a decision on the project. Status of agreements :  11 agreements have been signed and completed in the framework of the project (implementation of 9 services and 1 supplies agreement has been completed).  In Q2 of 2008 it is planned to implement 2 procurement agreements (Development of a sewerage system model in Jelgava and Implementation and extension of data transmission system (Daugavpils)) and at the beginning of 2009 – 1 procurement agreement (88 agglomerations).

14 Technical assistance for water services development projects in Latvian municipalities, No.2004/LV/16/C/PA/002  Work completed since 01/11/2007:  Intensive acoustic measurement of water supply networks in 7 municipalities in Kurzeme region - Kandava, Roja, Saldus, Skrunda, Stende, Talsi, Ugāle;  Washing of water supply pipelines and measurements of sewage flow in Talsi municipality in Kurzeme region;  Inspection of sewage pipelines in 8 municipalities in Kurzeme region - Brocēni, Dundaga, Kandava, Kuldīga, Roja, Skrunda, Stende, Talsi.  Status of agreements :  12 agreements are signed in the framework of the project (10 services and 2 supplies agreements).  Implementation of 2 supplies and 7 services agreement is completed. ______________________________  After completion of all agreements within the framework of the project savings have been made in the amount of EUR 370, Taking into account the fact that additional needs have been identified in the area of water services, the Ministry of Environment decided to add a new component to the project – “Inspection reports on nitrates, priority and hazardous substances in surface and underground water objects”. On 3 April 2008 a proposal for amendments to the EC Decision was submitted to the Ministry of Finance.

15 Development of water services in Ventspils, stage II, No. 2004/LV/16/C/PE/001  Work completed since 01/11/2007:  Reconstruction and construction of water and sewerage networks. Construction of 13.8 km of water networks and 13.5 km of sewerage and rainwater collection networks, as well as 5.2 km of water mains.  Status of agreements:  27 agreements signed in the framework of the project (2 services, 4 supplies and 21 works agreements of which 3 works agreements signed in 2008)  10 works, 4 supplies and 1 services, agreements completed.  In 2008 it is planned to organise 3 procurement tenders in the framework of the project.

16 Development of water services in Ventspils, stage II, No. 2004/LV/16/C/PE/001 Topical problems:  Increase in costs has been identified in procurement tenders of the project – EUR 8,446,379 more compared to the European Commission Decision and already allocated funds for covering the increase in costs, therefore it will not be possible to implement the project to the initially planned scope.  According to paragraph 9 of Minutes No.11 of the Cabinet sitting of 19/02/2008, it was decided in principle to allocate additional state budget funding after reduction of the scope of project and coordination of the changes with the European Commission.

17 Development of water services in Olaine and Jaunolaine, No. 2004/LV/16/C/PE/002  Work completed since 01/11/2007:  Implementation of the agreement “Reconstruction of water supply and sewerage networks in Jaunolaine” has been completed. Within the framework of the project 12 km of sewerage networks were reconstructed.  Status of agreements:  7 agreements signed in the framework of the project (1 services agreement and 6 works agreements).  1 works agreement has been completed.  In Q2 of 2008 it is planned to sign 1 works agreement for Jaunolaine component.

18 Topical problems:  Increase in costs has been identified in procurement tenders of the project – EUR 1,935, more compared to the European Commission Decision. According to paragraph 9 of Minutes No.11 of the Cabinet sitting of 19/02/2008, additional state budget funding was allocated to the project for covering the increase in costs on condition that the beneficiaries would co-finance EUR 1,012, of the increase in costs Increase in costs: EUR 1,935, State budget (~47,70%): EUR 923, Beneficiary (~52,30%): EUR 1,012, Development of water services in Olaine and Jaunolaine, No. 2004/LV/16/C/PE/002

19 Development of water services in Liepaja, stage II, No. 2004/LV/16/C/PE/003  Works completed since 01/11/2007:  Designing and reconstruction of inverted syphons of water supply pipelines under Liepāja Lake, Ālande (Tāšupīte) valley and Fortress Channel  Status of agreements:  17 agreements are signed in the framework of the project (7 works, 8 supplies and 2 services agreements).  Implementation of 8 supplies agreements and 1 works agreement is completed.  In October 2008 it is planned to organise 1 (last) procurement procedure.

20 Development of water services in Liepaja, stage II, No. 2004/LV/16/C/PE/003 Topical problems:  In the project there is the indicator “Improvements in sewage treatment facilities and urgent outlet repair works”. Part of this indicator – urgent outlet repair works was completed in 2005 using the funds of limited liability company “Liepājas ūdens”. Amendments to the EC Decision on granting of funds:  For the indicator “Reconstruction of drill holes/wells – change from 26 wells to 24 wells;  Within the framework of the project there is a surplus of EUR 238,000.00;  Inclusion of an additional component “Sludge treatment facility”.

21 Development of water services in Daugavpils, stage II, No. 2004/LV/16/C/PE/004 Status of agreements:  All planned agreements in the framework of the project (3 works and 1 services agreement) are signed. Planned deadline of completion of works is Q Topical problems:  Increase in costs has been identified in procurement tenders of the project – EUR 12,541, more compared to the European Commission Decision. According to paragraph 9 of Minutes No.11 of the Cabinet sitting of 19/02/2008, additional state budget funding was allocated to the project for covering the increase in costs on condition that the beneficiaries would co-finance EUR 2,131, of the increase in costs. Incerase in costs: EUR 12,541, State budget (~83%): EUR 10,410, Beneficiary (~17%): EUR 2,131,354.40

22 Zemgale region solid waste management, No.2004/LV/16/C/PE/005 Status of agreements:  3 agreements are signed in the framework of the project (1 services, 1 supplies and 1 works agreement). Topical problem:  Out of the 22 waste dump sites to be rehabilitated 15 are located on local government owned land, 5 – on private land and 2 – on the land of JSC “Latvian State Forests”. Rent agreements have been signed with the private owners, and rent agreements with JSC “Latvian State Forests” are being drawn up.  According to the opinion of the Ministry of Finance on eligibility of rehabilitation costs of dump sites located on private land, a review of the list of dump sites to be rehabilitated is possible, without changing the scope of work established in the EC Decision.

23 Maliena region solid waste management project, No. 2004/LV/16/C/PE/006 Works completed since 01/11/2007:  In February 2008, construction of Maliena region solid waste landfill “Kaudzītes” was completed. Status of agreements:  5 agreements are signed in the framework of the project (3 works, 1 services and 1 supplies agreement).  Implementation of 1 supplies and 1 works agreement is completed.  It is planned to complete all construction works of the project in December 2009.

24 Maliena region solid waste management project, No. 2004/LV/16/C/PE/006 Topical problems:  Increase in costs has been identified in procurement tenders of the project – EUR 450, more compared to the European Commission Decision. According to paragraph 25 of Minutes No.9 of the Cabinet sitting of 12/02/2008, additional state budget funding was allocated to the project for covering the increase in costs on condition that the beneficiary would co-finance EUR 76, of the increase in costs. Increase in costs: EUR 450, State budget (~83%): EUR 373, Beneficiary (~17%): EUR 76,686.68

25 Development of Ventspils district heating system, No.2005/LV/16/C/PE/001 Status of agreements:  1 services agreement has been signed in the framework of the project.  It is planned to launch 3 procurement tenders in Q2 of 2008:  “Designing and construction of the district heating system connecting pipeline in Ventspils by using horizontal drilling method”;  “Designing and construction of a CHP plant at 69 Talsu Street, Ventspils, including a 110kV power cable connection and backup heating plant”;  “Engineering supervision of construction works of the connecting pipeline and CHP plant in Ventspils”.  Planned deadline for completion of construction works – 09/2011.

26 Development of Ventspils district heating system, No.2005/LV/16/C/PE/001 Topical problems:  Taking into consideration also the information provided by company “Ventspils ENERGO” that the delivery times of cogeneration station equipment have increased (even up to 5 times), it is not possible to implement the project by 30 November 2009 as stated in the EC Decision.  Taking into consideration the changes in delivery times and assuming that procurement agreements will be signed in July 2008 and that there will be no unexpected circumstances, construction of the object will be completed in August/September 2011, which significantly exceeds the deadlines for physical works stated in the EC Decision.  The Ministry of Environment in its letter No /791 of 15 February 2008 has asked the Ministry of Finance to inform on possibilities to extend the works completion deadlines stated in the EC Decision to September 2011 and the period of eligibility to 31 August 2012.

27 Development of hazardous waste management system, stage I, No.2005/LV/16/C/PE/002 Works completed since 01/11/2007:  Technological equipment, mechanisms and vehicles have been delivered for operation of the hazardous waste landfill. Status of agreements:  All agreements in the framework of the project were signed (3 supplies, 1 services and 1 works agreement).  Implementation of 2 supplies agreements has been completed. ________________________________ Due to the fact that after all planned amendments to the agreement there will be a surplus of approx. EUR 400 thousand in the project budget the Ministry of Finance together with the State Hazardous Waste Management Agency will consider the possibility to prepare proposals for amendments to the EC Decision on including an additional component in the project, which may happen only after completion of the main stages of construction works. It is planned to complete construction works of the project in June 2008.

28 Development of water services in Riga, stage III, No.2005/LV/16/C/PE/003 (I)  Status of agreements:  6 agreements signed in the framework of the project (1 services agreement and 5 works agreements).  1 works agreement completed.  It is planned to carry out 7 more procurement procedures in the framework of the project.

29 Development of water services in Riga, stage III, No.2005/LV/16/C/PE/003 (II) Topical problems:  Due to lengthy approval procedures of the technical design with the responsible institutions delays were caused in drafting of procurement documentation for: Replacement of strategic water supply system valves and creation of water consumption registration zoning, Reconstruction of steel pipelines of water mains, Separation of sewerage systems in Teika- Čiekurkalns – construction of industrial sewerage, Reconstruction of non-pumped flow sewerage ceramic pipes, Reconstruction of reinforced concrete pipelines of water mains, Expanding water supply and sewerage systems in Dārzciems.  There is a risk that 3 works agreements will not be completed by the deadline stated in the EC Decision – 31/12/2009.  The value of agreements signed and the estimated total costs of tenders launched exceed the planned budget of the project.

30 Development of water services in Riga, stage III, No.2005/LV/16/C/PE/003 (III) Topical problems:  The component “Separation of sewerage systems in Teika-Čiekurkalns – reconstruction of the Sirius rainwater collector” will be implemented by splitting it in two stages. In stage I, the works agreement “Separation of sewerage systems in Teika-Čiekurkalns – reconstruction of the Sirius rainwater collector” will be implemented; in stage II, outlet of the collector will be constructed in Ķīšezers lake – this works agreement will be financed by Riga City Council and JSC “Rīgas ūdens”.  After completion of all procurements the need for making changes in the list of project physical indicators will be assessed.  Additional state budget funding was allocated to the project for covering the increase in costs, JSC “Rīgas ūdens” will finance 72% of this increase in costs.

31 Solid waste management in Piejūra region, No.2005/LV/16/C/PE/004 Status of agreements:  8 agreements signed in the framework of the project (4 works agreements 2 services and 2 supplies agreements).  In October 2008, 1 (last) procurement will be launched. ________________________________ According to paragraph 25 of Minutes No.9 of the Cabinet sitting of 12/02/2008, additional state budget funding was allocated to the project for covering 85% of the increase in costs on condition that the beneficiary would co- finance 15% of the increase in costs. Increase in costs: EUR 5,011, State budget (85%): EUR 4,259, Beneficiary (15%): EUR 751,727.71

32 Solid waste management in Ziemeļlvidzeme region, stage II, No.2006/LV/16/C/PE/001  On 10/12/2007 the winding-up report and final declaration of expenditure of the project were approved by the European Commission.

33 Technical assistance for the preparation of projects in water services sector in Latvia, No.2006/LV/16/C/PA/001 Status of agreements :  All 15 planned services agreements have been signed in the framework of the project.  Implementation of 1 services agreement has been completed. Within the framework of the project funds have been saved, and the Ministry of Environment is currently considering proposals on adding a new component to the project.

THANK YOU FOR YOUR ATTENTION!