1 TD26_CC_SiC 06-September-2011 Assembly procedure of TD26_CC_SiC F. Rossi.

Slides:



Advertisements
Similar presentations
COOLING TUBE ACCELERATING STRUCTURE MANIFOLD COUPLER VACUUM INTERFACE FLANGE RF INTERFACE FLANGE TUNING STUD ENGINEERING DESIGN AND FABRICATION OF X-BAND.
Advertisements

CLIC08 workshop Structure production: CERN activities and Master Schedule G. Riddone, W. Wuensch, R. Zennaro, Contributions from C. Achard, S. Atieh, V.
MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
MICE RF Cavity Design and Fabrication Update Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 27, 2004.
SSRF1 ALUMINUM ALLOY VACUUM CHAMBERS FOR SSRF L.X. Yin, D.K. Jiang, H.W. Du, X.L. Jiang SSRF Vacuum Group Shanghai National Synchrotron Radiation Center.
18/6/2007 M.Taborelli, TS-MME Structure fabrication techniques and possibilities M.Taborelli Disk structures Quadrant structures ….most of it inspired.
Status of KEK production July 11, 2008 at SLAC KEK T. Higo et al., Accelerator div. T. Takatomi et al., Mech. Eng. Center.
1 RF-Structures Mock-Up FEA Assembly Tooling V. Soldatov, F. Rossi, R. Raatikainen
Gage Blocks.
Structure stacking alignment tolerances CLIC Workshop January 2015 CERN Anastasiya Solodko, on behalf of the CLIC study team.
2 nd collaboration meeting on X-band Accelerator Structure Design and Test-Program Structure fabrication Comparative analysis of disk and quadrant manufacture.
Wrap up Xband accelerating structures review N. Catalan Lasheras
Improvements for next parts PIMS production meeting February 2013 Rolf Wegner.
K. Alam, CLIC workshop, October 16-18, CLIC workshop, October 2007 Working group “ Two beam hardware and integration” Test module in the two.
ENGINEERING DESIGN AND FABRICATION OF PETS V. Soldatov¹, D. Gudkov¹, I. Syratchev², A. Samoshkin¹, G. Riddone², A. Olyunin¹, S. Atieh² 1 – JINR, Dubna,
Status of vacuum & interconnections of the CLIC main linac modules C. Garion TE/VSC TBMWG, 9 th November 2009.
International Workshop on Linear Colliders 2010 Design and fabrication update on PSI/Trieste X-band phase- space rotator structure Dmitry Gudkov 21-OCT-2010.
INTEGRATION OF RF STRUCTURES IN THE TWO-BEAM MODULE DESIGN G. Riddone, CERN, Geneva, Switzerland A. Samoshkin, D. Gudkov, JINR, Dubna, Russia Abstract.
Gage Blocks Unit 12.
Investigation threads on fabrication technologies for the CLIC X-band Accelerating Structures C. Rossi on behalf of the CLIC X-band Activity Thanks for.
PETS EuCARD. Present status and precision assembly L. Sánchez, F. Aragón, J. Calero, J.L. Gutiérrez, E. Rodríguez, F. Toral, CIEMAT 26/10/2011.
Mechanical Issues SPL cavities/cryomodules Workshop CERN 30 Sep. 2009
CLASSE prototype: mechanical concepts G. De Michele, EPFL-PSI-CERN on behalf of CERN team SLAC, 16 th April, 2012.
RFQ Fabrication Plan, Schedule and QC PXIE RFQ Fabrication Readiness Review LBNL – June 26, 2013 Steve Virostek - Engineering Division Lawrence Berkeley.
Vacuum Fundamentals High-Vacuum Technology Course Week 6 Paul Nash HE Subject Leader (Engineering)
10/2007 M.Taborelli, TS-MME Structure Manufacturing, Achievements and Challenges M.Taborelli -Technology -Shape accuracy -Surface quality -Assembly accuracy.
1 Status of the CLIC two-beam module program A. Samochkine, G. Riddone Acknowledgements to the Module WG members 4 February 2014 CLIC Workshop 2014 (3-7.
CLIC RF structure development meeting Structure cost study (introduction) G. Riddone,
ABSTRACT The Compact Linear Collider (CLIC) is currently under development at CERN as a potential multi-TeV e + e – collider. The manufacturing and assembly.
Surface Treatment Issues for RF Structure Fabrication Juwen Wang SLAC National Accelerator Laboratory X-Band Accelerating Structure Review November, 2014,
ENGINEERING DESIGN AND FABRICATION OF X-BAND DAMPED DETUNED STRUCTURE V. Soldatov¹, D. Gudkov¹, A. Samoshkin¹, G. Riddone², A. Grudiev², S. Atieh², A.
1.3GHz Input Coupler for ILC
LCWS13, November 2013 At the University of Tokyo W.–D. Möller Status of the TTF3 RF Power Coupler.
CLIC08 workshop CLIC module layout and main requirements G. Riddone, on behalf of the CMWG Home page of the TBM WG:
Assembly Procedures of the cavities Ancillaries (RF power coupler, Tuning system, RF cables) 19/03/2014Mathieu Therasse BE/RF/SRF1 Special Linac WG meeting:
CLIC Module WG 20/07/2009 H. MAINAUD DURAND, BE-ABP/SU Pre-alignment system and impact on module design.
1 Thermal tests planning for mock-up TM0 Thermal tests planning for CLIC prototype module type 0 May 30th,
Fabrication and measurement of RF components for CLIC study
Americas Cavity Specification C.M. Ginsburg (Fermilab) On behalf of the Fermilab cavity crew October 20, 2010.
1 Assembly and installation of TM0 Lab components Assembly and installation of TM0 Lab components F. Rossi.
Eric Montesinos - CERN - First SPL collaboration meeting - CERN December 11th 2008 First SPL collaboration meeting Experience with the LHC Main power Coupler.
ENGINEERING DESIGN AND FABRICATION OF X-BAND ACCELERATING STRUCTURE TD24 WITH WFM Abstract To achieve high luminosity in CLIC, the accelerating structures.
1 Thermal tests planning for mock-up TM0 Thermal tests planning for CLIC prototype module type 0 July 17,
Main features of PETS tank J. Calero, D. Carrillo, J.L. Gutiérrez, E. Rodríguez, F. Toral CERN, 17/10/2007 (I will review the present status of the PETS.
1 Assembly and installation of TM0 in the Lab Assembly and installation of TM0 in the Lab F. Rossi September.
1 Assembly procedure for PETS and AS 11-July-2011 Assembly procedure of PETS and AS for T0 module Lab F.
5 th CLIC-ACE Structure production in laboratories and industries G. Riddone, 02/02/2010 (contribution from KEK/SLAC colleagues) 1.
Bellerophon on Pegasus S. Atieh RF structure development meeting.
Mechanical design and tests of the new X-band flange
TD26CC PLANS FROM CIEMAT Laura Sánchez on behalf Electrical Engineering Group of CIEMAT.
7-Sep-2011 CLIC RF Structure Development Meeting «BE/RF» TD26 WITH COMPACT COUPLER FOR CLEX (TD26 CC SiC) ENGINEERING DESIGN this structure will be used.
RF power couplers vacuum issues J.M. Jimenez Vacuum, Surfaces and Coatings Group (TE-VSC)
Vacuum for DTL G.Vandoni on behalf of the TE/VSC Linac4 team 13 September, 2011G.Vandoni, TE-VSC1 Acknowledgements M.Malabaila, J.Hansen, A.Mongelluzzo,
MICE RFCC Module Update Steve Virostek Allan DeMello Lawrence Berkeley National Laboratory MICE CM27 at RAL, UK July 8, 2010.
02-Dec XB Dec-2010 XB-10 Engineering design, production and follow-up of X-band RF components G. Riddone in collaboration.
Hao Guo LINAC Department Institute of Modern Physics.
SPS High Energy LSS5 Thermal contact & cooling aspects
GOLD- ELECTROPLATING COOLING FITTING ADAPTER ACCELERATING STRUCTURE CONCEPTUAL DESIGN OF X-BAND ACCELERATING STRUCTURE TD26 CC SIC Abstract Many accelerating.
Adjustable tuner HENRY PRZYBILSKI / PIERRE-ALAIN LEROY.
Status of the CLIC module R&D G. Riddone on behalf of the CLIC module WG (special contributions from A. Samoshkin, D. Gudkov, A. Solodko, N. Gazis)
Two-beam module layout
LCWS11 WG4 Fully featured accelerating structure engineering design
Coupled thermal-structural FEA of AS tooling for brazing of manifolds to disk stack R. Raatikainen, F. Rossi
NA62 LAV Anti1 REMOVAL & TESTS
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
CLIC WORKSHOP January 2013 BODYCOTE Your main sub-contractor for thermal processes Raymond SAEZ-Patrick JACQUOT.
Dump Core Studied Design Solutions
WP 15.2 Progress and critical aspects
IMP Cryomodule Assembly and Alignment
Presentation transcript:

1 TD26_CC_SiC 06-September-2011 Assembly procedure of TD26_CC_SiC F. Rossi

2 TD26_CC_SiC INTRODUCTION ACCELERATING STRUCTURE PETS Vacuum flange Manifold RF flange and waveguide Wakefield monitor Cooling circuit Interconnection bellow AS Damping load 500 mm 220 mm REQUIREMENTS COAXILITY ERROR: < 10 µm ALIGNMENT ERROR BETWEEN MANIFOLDS AND DISKS STACK: ±10 µm REQUIREMENTS COAXILITY ERROR: < 10 µm ALIGNMENT ERROR BETWEEN MANIFOLDS AND DISKS STACK: ±10 µm ON-OFF mechanism Vacuum flange RF flange Coupler Cooling circuit Octant with damping material Frictional contact Frictional contact EBW REQUIREMENTS COAXILITY ERROR: < 25 µm REQUIREMENTS COAXILITY ERROR: < 25 µm

3 TD26_CC_SiC INTRODUCTION Main technologies involved in the assembly procedure:  Bonding (atmosphere: H 2, temperature: ~1000 °C)  Brazing (atmosphere: H 2 or vacuum, temperature: ~1000 °C, brazing alloy: AuCu or AgCu)  EBW  (Laser welding)

4 TD26_CC_SiC STEPS (1) MACHINING (1) MACHINING (3) CLEANING 1.Etching with SLAC solutionEtching with SLAC solution 2.Degreasing + deoxidation + passivationDegreasing + deoxidation + passivation (3) CLEANING 1.Etching with SLAC solutionEtching with SLAC solution 2.Degreasing + deoxidation + passivationDegreasing + deoxidation + passivation (4) H 2 DIFFUSION BONDING (1040 °C) 1.Disks stack (x2)Disks stack (x2) (4) H 2 DIFFUSION BONDING (1040 °C) 1.Disks stack (x2)Disks stack (x2) (2) QUALITY CONTROL 1.Inlet inspectionInlet inspection 2.Dimensional controlDimensional control 3.SEMSEM 4.Preliminary RF testsPreliminary RF tests (2) QUALITY CONTROL 1.Inlet inspectionInlet inspection 2.Dimensional controlDimensional control 3.SEMSEM 4.Preliminary RF testsPreliminary RF tests (5) H 2 BRAZING (Au/Cu 25/75, 1040 °C) 1.Manifold cover (x2)Manifold cover (x2) 2.WFM (x4)WFM (x4) 3.Waveguides (x8)Waveguides (x8) 4.Cooling system (x8)Cooling system (x8) (5) H 2 BRAZING (Au/Cu 25/75, 1040 °C) 1.Manifold cover (x2)Manifold cover (x2) 2.WFM (x4)WFM (x4) 3.Waveguides (x8)Waveguides (x8) 4.Cooling system (x8)Cooling system (x8) (6) MACHINING 1.Waveguides (x8)Waveguides (x8) (6) MACHINING 1.Waveguides (x8)Waveguides (x8) (7) CLEANING 1.Degreasing + deoxidation + passivationDegreasing + deoxidation + passivation (7) CLEANING 1.Degreasing + deoxidation + passivationDegreasing + deoxidation + passivation (8) H 2 BRAZING (Au/Cu 25/75, 1040 °C) 1.Vacuum manifolds (x6)Vacuum manifolds (x6) (8) H 2 BRAZING (Au/Cu 25/75, 1040 °C) 1.Vacuum manifolds (x6)Vacuum manifolds (x6) (9) H 2 BRAZING (Au/Cu 35/65, 1020 °C) 1.4 vacuum manifolds + 1 disks stack + 1 interconnection flange + 8 steel inserts + tuning studs (x2)4 vacuum manifolds + 1 disks stack + 1 interconnection flange + 8 steel inserts + tuning studs (x2) (9) H 2 BRAZING (Au/Cu 35/65, 1020 °C) 1.4 vacuum manifolds + 1 disks stack + 1 interconnection flange + 8 steel inserts + tuning studs (x2)4 vacuum manifolds + 1 disks stack + 1 interconnection flange + 8 steel inserts + tuning studs (x2) (11) H 2 BRAZING (Au/Cu 50/50, 980 °C) 1. 2 accelerating structures (11) H 2 BRAZING (Au/Cu 50/50, 980 °C) 1. 2 accelerating structures (15) VACUUM BAKING (650 °C, 10 days) (15) VACUUM BAKING (650 °C, 10 days) (14) RF CHECK AND TUNING (14) RF CHECK AND TUNING (16) CONDITIONING (16) CONDITIONING (10) QUALITY CONTROL 1.Vacuum testVacuum test 2.Cooling circuit testCooling circuit test (10) QUALITY CONTROL 1.Vacuum testVacuum test 2.Cooling circuit testCooling circuit test (12) EBW 1.Covers and vacuum flangesCovers and vacuum flanges (12) EBW 1.Covers and vacuum flangesCovers and vacuum flanges (13) QUALITY CONTROL 1.Vacuum testVacuum test (13) QUALITY CONTROL 1.Vacuum testVacuum test

5 TD26_CC_SiC WORKFLOW: AS 1 5. H 2 brazing (AuCu 25/75, 1040 °C) 5. H 2 brazing (AuCu 25/75, 1040 °C) 8. H 2 brazing (AuCu 25/75, 1040 °C) 8. H 2 brazing (AuCu 25/75, 1040 °C) 6. Machining 7. Cleaning 10. QC 4. H 2 bonding (1040 °C) 4. H 2 bonding (1040 °C) 9. H 2 brazing (AuCu 35/65, 1020 °C) 9. H 2 brazing (AuCu 35/65, 1020 °C) Disks stack Waveguide Manifold WFM Manifold Manifold cover 1.Vacuum test 2.Cooling circuit test 1.Vacuum test 2.Cooling circuit test

6 TD26_CC_SiC WORKFLOW: AS 2 5. H 2 brazing (AuCu 25/75, 1040 °C) 5. H 2 brazing (AuCu 25/75, 1040 °C) 6. Machining 7. Cleaning 4. H 2 bonding (1040 °C) 4. H 2 bonding (1040 °C) Disks stack Waveguide Manifold Manifold cover 8. H 2 brazing (AuCu 25/75, 1040 °C) 8. H 2 brazing (AuCu 25/75, 1040 °C) 10. QC 9. H 2 brazing (AuCu 35/65, 1020 °C) 9. H 2 brazing (AuCu 35/65, 1020 °C) 1.Vacuum test 2.Cooling circuit test 1.Vacuum test 2.Cooling circuit test

7 TD26_CC_SiC WORKFLOW 12. EBW 11. H 2 brazing (AuCu 50/50, 980 °C) 11. H 2 brazing (AuCu 50/50, 980 °C) 13. QC 1.Vacuum test

8 TD26_CC_SiC ASSEMBLY PROCEDURE CLIC’s requirements shape accuracy: ± 2.5 µm roughness Ra: µm 1. MACHINING DIAMOND TOOLS Low coefficient of friction and smoothness High thermal conductivity Low compressibility Low thermal expansion Dimensional stability About 7 tools are necessary to machine each disk Hybrid turn/mill machine

9 TD26_CC_SiC ASSEMBLY PROCEDURE 2. QUALITY CONTROL The inspection takes place in specific room, with all the important issues (clean air, gloves, shoes with gloves, specific glasses and specific machines), in order to check the surface for scratches, dents, pits, cracks. The pieces are also organized in photo archives. If parts are not clean enough, cleaning procedure should be done again. If parts are not clean, measurement can’t be done because any oil or dust could have an influence on measurement machines. Inlet inspection Dimensional control CERN workshop metrology laboratory Class 1 according to VDE/VDI 2627 standard Reference temperature: 20 °C Temperature gradients: 0.2 K/hour, 0.4 K/day, 0.1 K/meter Conditioner with high accuracy of temperature and humidity control (± 0.5 K) Filters needed to prevent dust in the dimensional control room Vibrations control SEM analysis Identify the machining quality (machining marks, burrs) and the general surface quality (contaminations, handling marks, faceting) before operation at high power. Characterize the surface (craters, smoothening, waves, peaks, projections, oxidation). New Leitz PMM-C Infinity Dimensional control of disks Accuracy: ±(0.3 + L/1000) μm Pieces up to 1.2 m Probe head has adjustable force ( N) VEECO Roughness and flatness measurements Uses white light, lens and CCD camera Two hours to measure  80 mm disk and two hours to process the images

10 TD26_CC_SiC 9.Etching with SLAC solution Concentration: o phosphoric acid: 70 % o nitric acid: 23.3 % o acetic glacial acid: 6.6 % o hydrochloric acid: 0.49 % Temperature: room Time:  5 seconds for turning (etching of about 0.6 µm)  30 seconds for turning and milling 10.Rising with water jet 11.Immersion in demineralised water, removal of the screws, rinsing of the holes using a syringe and fixing of the support clip and the hook 12.Final rinsing with demineralised water and ultrasounds, followed by rinsing with ethylic alcohol and ultrasounds Temperature : 30 °C Time : ~ 1 minute 13.Drying with nitrogen 14.Drying in an oven Temperature: 60 °C Time: ~ 5 minutes 15.Drying with nitrogen 16.Packaging with tissue paper ASSEMBLY PROCEDURE 3. CLEANING (FOR BONDING) 1.Unpacking, visual inspection, fixing of the support clip 2.Degreasing with solvents Topklean MC 20A and Promosolv 71IPA This treatment is repeated twice if there are more than two blind holes. After the first degreasing the piece is removed from the basket and it put onto tissue paper. The support clip is removed and is then inserted into the other holes. The disk is placed in the basket and is degreased for the second time. 3.Removal of the support clip, drying the blind holes with nitrogen, packaging with tissue paper for transport to a different area. 4.Unpacking. If there are any blind threaded holes, these have screws inserted to prevent acid ingression. A hook is then fixed to the screw. 5.Degreasing with detergent NGL spec. ALU III and ultrasounds Concentration: 10 g/l Temperature: 50 °C Time: 10 – 15 minutes 6.Rising with water jet and by immersion. 7.Pickling (deoxidation) with hydrochloric acid. Concentration: 50 % Temperature: room Time: ~ 1 minute 8.Rising with water jet and by immersion.

11 TD26_CC_SiC ASSEMBLY PROCEDURE 4. H 2 DIFFUSION BONDING (1040 °C) PRE-ASSEMBLY STRAIGTHNESS MEASUREMENTS Once the assembly procedure is completed, straightness measurements are performed using the Mitutoyo Linear Height LH-600. The measurements are done with the accelerating structure on the V- support and considering two reference lines, called REF A and REF B. The measurement is done before and after transport to the oven and they are organized in charts. Accuracy of V-shape column: ± 1.5 µm REF A REF B Mitutoyo Linear Height LH-600 Measuring range: mm Resolution: 0.1 µm Accuracy: ( L[mm]/600) µm Measuring force: 1N

12 TD26_CC_SiC ASSEMBLY PROCEDURE 4. H 2 DIFFUSION BONDING (1040 °C) TRANSPORT TO FURNACE 1. Load (0.28 MPa) is applied to the disks stack using the load device and thermocouples are mounted to measure the temperature history during the heat treatment. 3. Bonded disks stack4. Particular of the grains aspect after the heat treatment. Grains size order of few millimeters. 2. Bonding inside the furnace: atmosphere: H 2 temperature: 1040 °C Before each bonding cycle, a outgassing cycle is performed. LOAD APPLICATION

13 TD26_CC_SiC ASSEMBLY PROCEDURE 5. H 2 BRAZING (Au/Cu 25/75, 1040 °C) 6. MACHINING Waveguides are machined with reference to RF flanges dimensions, in order to achieve a clearance of mm between the two surfaces where the brazing alloy will flow and create the joint. Graphite plate Ceramic support Ceramic plate WEIGHT Brazing wire groove (Au/Cu 25/75)

14 TD26_CC_SiC ASSEMBLY PROCEDURE 9. H 2 BRAZING (Au/Cu 35/65, 1020 °C) Rod Nut Lower plate Lateral support Lateral spring Lateral plate Upper support Upper spring Wedges Upper spring (graphite): apply a vertical force on the manifolds through the upper support and allow thermal expansion of the assembly during the brazing cycle. Rod (stainless steel): connect upper support and lower plate. Lower plate (graphite): support the assembly during alignment operations and brazing cycle. Wedges (ceramic): allow small adjustment of manifolds in the vertical direction. Lateral springs (graphite): apply an horizontal force to the manifolds through the lateral plates and allow thermal expansion of the assembly during the brazing cycle. Lateral supports (stainless steel): support the springs.

15 TD26_CC_SiC ASSEMBLY PROCEDURE 10. H 2 BRAZING (Au/Cu 50/50, 980 °C) Ceramic Inox plate Ceramic Inox plate 3 DOF 1 st structure2 nd structure and measurement Auxiliary frameAlignment Tooling ready for transport to furnace TOOLING Mitutoyo Linear Height LH-600

16 TD26_CC_SiC ASSEMBLY PROCEDURE 12. EBW Cover Small cover Vacuum flange EBW machine (CERN workshop) EBW machine chunk TOOLING

17 TD26_CC_SiC ASSEMBLY PROCEDURE 13. QUALITY CONTROL Vacuum test 14. RF CHECK AND TUNING After bonding and brazing processes, accelerating structures must be tuned to compensate the different assembly errors. Tuning is performed modifying by plastic deformation the cell walls and checking, at the same time, the results of this operation by means of a network analyser. Plastic deformation is achieved by pushing or pull the tuning studs brazed in the accelerating structure. Leak detector and Helium are used for vacuum tests. Helium is pumped around the accelereting structure and if a leak is present is detected by the machine.

18 TD26_CC_SiC ASSEMBLY PROCEDURE 15. VACUUM BAKING (650 °C, 10 days) 16. CONDITIONING Muffle Accelerating structure Tooling The accelerating structure is positioned inside a container with a protective atmosphere (N 2 ) to prevent copper oxidation.

19 TD26_CC_SiC CONCLUSIONS Requirements for disks machining are very strict (shape accuracy: ± 2.5 µm, roughness Ra: µm) These requirements should be preserved after each step of the assembly procedure Toolings are necessary to fulfill these accuracy needs during the different steps Nevertheless, assembly errors are present at the end and the final RF tuning of the accelerating structure is performed to compensate them.  Main critical issues:  Alignment of manifolds and AS for brazing  Residual deformations after heat treatments at ~ 1000 °C

20 TD26_CC_SiC PROPOSALS Mectalent Manufacturing of toolings for brazing and EBW. For what regards brazing, a close collaboration with Loval is required. Timetable: April Loval Furnaces will be adapted to perform H 2 brazing at 25 mbar. In the meantime, brazing tests can be done for those components for which H 2 atmosphere is not mandatory (like cooling circuits, waveguides, WFM). Timetable: mid of 2012

21 TD26_CC_SiC THANKS G. Riddone A. Samoshkin (Engineering design) P. Piirainen (Engineering design) A. Solodko (Engineering design) S. Lebet (Assembly and brazing) S. Atieh (Machining) A. Olyunin (Quality control) M. Malabaila (Cleaning) J. Shi (RF check and tuning)