EARNED VALUE MANAGEMENT SYSTEM A Project Performance Tool

Slides:



Advertisements
Similar presentations
Project Cost Management
Advertisements

Connoizor Enabling Performance for Businesses through Software Website: Contact:
Budget Management. 57 Budget Management Budget Development Good scheduling skills and abilities Understanding of the project scope Well developed WBS.
1 What Is It ? Why Do I Need It ? How Do I Do It? Earned Value Analysis.
Monitoring and Information Systems
Monitoring and Control Earned Value Management (EVM)
Project Cost Management Sections of this presentation were adapted from A Guide to the Project Management Body of Knowledge 4 th Edition, Project Management.
CSSE Oct.2008 Monitoring and reporting project status Chapter 10, pages
Irwin/McGraw-Hill ©The McGraw-Hill Companies, 2000 Chapter 13 Progress and Performance Measurement and Evaluation.
Chapter 10: Monitoring and Controlling Change
Degree and Graduation Seminar Cost Management
Monitoring and Controlling
Project Monitoring and Control. Introduction Goal: ensuring that the project is on time and on budget and/or highlight any deviation from the plan Areas.
Where We Are Now. Where We Are Now Structure of a Project Monitoring Information System Creating a project monitoring system involves determining:
Project Management Process Project Description Team Mission/ Assignment Major Milestones Boundaries Team Identification Measures of Success Roles & Responsibilities.
Progress and Performance Measurement and Evaluation CHAPTER THIRTEEN Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved.
Project Evaluation and Control
Project Management 6e..
This work is licensed under a Creative Commons Attribution 3.0 Unported LicenseCreative Commons Attribution 3.0 Unported License (CC-BY). Project Management.
PowerPoint Presentation by Charlie Cook THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Progress and Performance Measurement and Evaluation Chapter.
Project Management Methodology Project monitoring and control.
Progress and Performance Measurement and Evaluation CHAPTER THIRTEEN Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved.
Chapter 13: Progress and Performance Measurement and Evaluation
PPMT CE-408T Engr. Faisal ur Rehman CED N-W.F.P UET P.
Conducted By: Dr. Madhu Fernando, PMP, DBA, MEng. MGT PROJECT MANAGEMENT LESSON 5 AND 6: PROJECT PLANNING – TIME AND COST PLANNING AND MANAGEMENT.
PowerPoint Presentation by Charlie Cook Copyright © 2006 The McGraw-Hill Companies. All rights reserved. THE MANAGERIAL PROCESS Clifford F. Gray Eric W.
PowerPoint Presentation by Charlie Cook Copyright © 2006 The McGraw-Hill Companies. All rights reserved. THE MANAGERIAL PROCESS Clifford F. Gray Eric W.
9-1 Project Management from Simple to Complex. 9-2 This work is licensed under the Creative Commons Attribution-Noncommercial-Share Alike 3.0 Unported.
EARNED VALUE MANAGEMENT (EVM)
Project Cost Management
PowerPoint Presentation by Charlie Cook Copyright © 2006 The McGraw-Hill Companies. All rights reserved. THE MANAGERIAL PROCESS Clifford F. Gray Eric W.
Project Management 6e..
EARNED VALUE MANAGEMENT (EVM) TUTORIALS
Report Performance Monitor & Control Risk Administer Procurement MONITORING & CONTROLLING PROCESS.
Department of CS & Eng. MSSE Program, © Fissure 1 SOFTWARE PROJECT MANAGEMENT COURSE Executing, Monitoring and Controlling Session #7.
Earned Value Analysis Tracking Project Progress. Introduction | Components | Project Scenario | Values | Calculations | Forecasts | Summary l What Is.
Where Module 04 : Knowing Where the Project Is 1.
Information Technology Project Management, Six th Edition Kathy Schwalbe Copyright Disampaikan Oleh : Wiwid Dolianto S.Kom, MT Universitas Muhammadiyah.
EVM – Do You Really Know What the Numbers Mean? Booz | Allen |Hamilton Seth Huckabee EVP, PMP, PMI-SP.
1 Understanding Earned Value in Under an Hour Breakout Session # A11 Name: Wayne Brantley, MS Ed, PMP, ITIL Senior Director of Professional Education.
EARNED VALUE  Earned Value Management Systems  Earned Value Analysis.
0 Earned Value Management. 1  What is it?  Where did it come from?  What’s so special about it?  How do you do it?  What is an EVMS?
Information Technology Project Management, Seventh Edition Note: See the text itself for full citations.
Agenda ‒ Cost Management ‒ Cost Budgeting ‒ Cost Control Learning Goals 1.Cost Control 2.Earned Value Management.
Project Management 1 Project Control. Project Management 2 Topics Project Control Status Reporting Earned Value Analysis.
PowerPoint Presentation by Charlie Cook THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Progress and Performance Measurement and Evaluation Chapter.
Project Cost Management
MISUSE OF EARNED VALUE MANAGEMENT RESULTS IN ERRONEOUS CONCLUSIONS
Earned Value Analysis by Miles M. Hamby, PhD Copyright©2014 Miles M
Project Monitoring
Monitoring and Information Systems
“PMP® Exam Prep” Earned Value Management
Project COST Management
Budget Planning.
CHAPTER:7 Project Cost Management
Project Management – PTM712S
Chapter 7: Project Cost Management
Project Communication, Tracking, and Reporting
Project evaluation and control
5. Cost resources & PLAN DURATION
Project Cost Management
Earned Value Management
Project Cost Management
Earned Value Measures Planned Value (PV) Earned Value (EV)
5. Cost resources & PLAN DURATION
5. Project PLAN & cost estimation
Project Cost Management
Monitoring and Controlling
Managing Project Work, Scope, Schedules, and Cost
Where We Are Now. Where We Are Now Structure of a Project Monitoring Information System Creating a project monitoring system involves determining:
Presentation transcript:

EARNED VALUE MANAGEMENT SYSTEM A Project Performance Tool By Roy T. Uemura, PMP, P.E., MBA Project Management Consultant Project Professionals, LLC

How Is Your Project Doing? Ahead of schedule? Within your approved Budget?

How Is Your Project Doing? What is your cost estimate at completion? Will you be ahead or behind the scheduled completion date?

Agenda Explanation of Earned Value Management (EVM) The traditional “Two Dimensional System” of Evaluation EVM “Three Dimensional System” of Evaluation Critical Variables in EVM EVM Formulas Applying EVM on projects Example

Earned Value Management Method for integrating scope, schedule, and resources, for measuring project performance. Compares what was planned with what was actually spent with what was actually “earned”

Earned Value Management Developed in the 1960’s Popular method for reporting and controlling project in the Department of Defense A common language to report progress and cost against a project Helps answer the questions: Are we on schedule? How much did the work we do cost? Are there variances? Based on these trends, how much will it cost by the end of the project?

Early Warning System “… based on the Project Performance Plan and Project’s Actual Performance against the Plan, the project will likely take this much time to finish, and spend this much money.”

Traditional System (Two Dimensional) Cost: compares what was planned to be expended versus what was actually expended Time: Compares the date you are on a project versus when the project is to be completed Production: Compares how much work was planned to be completed versus how much was actually completed.

Earned Value (Three Dimensional) 1. Actual work that was “earned” versus 2. Work that was accomplished 3. Work that was scheduled to be accomplished

Critical Variables to EV Performance Indices Quality of the project baseline plan Actual performance against baseline plan Management’s determination to control (change) the final results

Project Baseline Basis of performance measurement Represents technical, cost and schedule objectives of the project Cashflows Outside Material Outside Services

Scope of Work The scope of work of entire project must be defined The Work Breakdown Structure (WBS) identifies and groups major deliverables Integrate scope with budget and schedule.

Performance Measurement Methods Fixed formula by task: 0/100 %, 25/75%, 50/50 % Weighted Milestones Percent complete based on specific work (milestone) accomplished. Percent Complete Increment completed / total activity or task Equivalent Completed Units

Cost Account Plan

Project Description Installed approximately 14.5 miles of transmission line of which about 4,000 feet was installed underground. Installed 93 steel poles: 52 poles were direct buried and 41 were mounted on pier foundations. The project was to install about 14.5 miles of line to connect our Waialua and our Kuilima Substations. This involved installing about 4,000 ft. of underground lines which was located within the Haleiwa Special Design District. Just to give you some numbers, we installed 93 steel poles of which 41 of these poles were installed on pier foundations. Steel pole heights ranged from 40 - 111 ft AGL Foundations: about 5 ft diam. x 15 ft deep. (Largest hole: 7 ft. diam. x 23 ft. deep)

Kuilima The new Waialua-Kuilima line will provide a new source of power to Kuilima where the power could go East or West from Kuilima Substation in the event of a fault on the existing 46 kV system Waialua

Visual Progress Report Foundation: Dug Concrete Poured Pole Erection: Lines Strung: Trench: Conduit Installed: Cable Installed: Trench Covered:

Kuilima The new Waialua-Kuilima line will provide a new source of power to Kuilima where the power could go East or West from Kuilima Substation in the event of a fault on the existing 46 kV system Waialua

Controlling Change Essential: Change Management Control System in the Project Plan prevents incorrect, inappropriate, or unauthorized changes to the project. Inform appropriate stakeholders of authorized changes to the Baseline (scope/quality, schedule, cost)

EVM Input Data Required PLANNING PHASE Planned Value (PV) Budget At Completion (BAC) % Complete - Planned EXECUTING & CONTROLLING PHASES Actual Cost (AC) % Complete - Actual

Calculations from Input Data Earned Value - EV Cost Variance - CV Schedule Variance - SV

Calculations for Analysis Cost Performance Index - CPI Schedule Performance Index - SPI Budget at Completion - BAC Estimate to Completion - ETC Estimate at Completion - EAC To Complete Performance Index - TCPI

Primary Data Elements PV (Planned Value) The value of the amount of work that was planned to be accomplished on a task (or a project) as of a certain date in the baseline plan. BAC (Budget at Completion) Total cost of a task (or project) according to the baseline plan.

Primary Data Elements (cont’d) AC (Actual Cost) The actual amount of money spent on a task (or project) as of a certain date.

Performance Analysis EV = % Actual Complete x BAC EV (Earned Value). The value of the amount of work actually completed on a task (or project) as of a certain date, according to the baseline plan. EV = % Actual Complete x BAC

Performance Analysis (cont’d) CV (Cost Variance) The difference between the value of work that was actually completed (EV) on a task (or project) and the cost that was actually spend (AC) on the task (or project) as of a certain date. CV = EV - AC (+$ = spending less than planned)

Performance Analysis (cont’d) SV (Schedule Variance) The difference between the value of work that was actually completed (EV) on a task (or project) and the work that should have been done (PV) as of a certain date. SV = EV - PV (+$ = Ahead of Schedule)

Performance Analysis (cont’d) CPI (Cost Performance Index) The ratio of the value of work actually completed (EV) on a task (or project) and amount actually spent (AC) on a task (or project) as of a certain date. CPI = EV/AC (>1 = Spending less than planned) CPI: For every project dollar spent, $x.xx in physical work was accomplished, CPI is a powerful tool to predict the final costs needed to finish a job.

Performance Analysis (cont’d) SPI (Schedule Performance Index) The ratio between the value of work that was actually completed (EV) on a task (or project) and the work that should have been done (PV) as of a certain date. SPI = EV/PV (>1 = Ahead of Schedule) SPI: For every dollar of physical work planned to accomplished, $x.xx was completed. SPI can be a valuable tool to forecast completion date for the project.

Performance Analysis (cont’d) ETC (Estimate To Completion) The forecasted cost of the remaining task (or project) is calculated by CPI or CPI x SPI ETC = Remaining Work / CPI = (BAC - EV/ CPI or ETC = Remaining Work/ (CPI x SPI) = (BAC - EV/(CPI x SPI)

Performance Analysis (cont’d) EAC (Estimate at Completion) The value expressed in either dollars or hours to represent the projected final cost of work when completed. The EAC equals the actual costs (AC) incurred plus the estimated costs to complete the remaining work (ETC). EAC = AC + ETC

Performance Analysis (cont’d) Ranges of Estimate at Completion High-End Projection (Cumulative CPI x SPI) EAC = AC + (BAC - EV) / (CPI x SPI) In-Between Projection (80% CPI x 20% SPI) EAC = AC + (BAC - EV) / (0.8 CPI x 0.2 SPI) Low-End Projection (Cumulative CPI) EAC = AC + (BAC - EV) / CPI

To Complete Performance Index TCPI: Project performance which must be achieved on all remaining work in order to meet the financial goal by management TCPI = Work Remaining / Funds Remaining = (Total Budget - Earned value) (BAC - Actual Costs) = (BAC - EV) (BAC - AC)

PMP Exam EAC = BAC Estimate At Completion (EAC) CPI Estimate to Complete (ETC) ETC = EAC - AC Rita Mulcahy, PMP Exam Prep 5th Edition (2005)

Example Time: 4th month of 10 month schedule Budget at Completion: BAC = $10,000 Planned Value: PV = $4,000 Actual Cost: AC = $3,800 Actual % Complete: 36% Earned Value: EV = 0.36 x $10,000 = $3,600

Earned Value Analysis Status Date BAC 1 2 3 4 5 6 7 8 9 10 Time $10,000 $5,000 PV = $4,000 AC = $3,800 EV = $3,600 1 2 3 4 5 6 7 8 9 10 Time

Performance Analysis Traditional Analysis Cost Variance:= Planned Expenditure - Actual Cost CV = PV - AC CV = $4,000 - $3,800 = $200 (under spent by $200) Earned Value Analysis CV = EV - AC CV = $3,600 - $3,800 = -$200 (spending more than planned for work performed) SV = EV - PV SV = $3,600 - $4,000 = -$400 (less work was done than planned)

Performance Analysis Cost Performance Index (CPI) CPI = EV / AC CPI = $3,600/$3,800 = 0.95 (<1, for every $1 spent, only $0.95 in physical work was done) Schedule Performance Index (SPI) SPI = EV / PV SPI = $3,600 / $4,000 = 0.9 (<1, for every $1 of physical work planned, only $0.9 was done)

Performance Analysis ETC = (BAC - EV) / CPI Estimate To Complete (ETC) ETC = (BAC - EV) / CPI ETC = (BAC - EV) / (CPI x SPI)

Performance Analysis EAC = AC + [(BAC - EV)/(CPI x SPI)] Estimate At Completion (EAC) EAC = AC + [(BAC - EV)/(CPI x SPI)] = 3,800 + [(10,000 – 3,600) / (0.95 x 0.90)] = $11,285 (high end) EAC = AC + [(BAC - EV) / CPI] = 3,800 + (10,000 – 3,600) / 0.95 = $10,537 (low end)

Performance Analysis To Complete Performance Index (TCPI) TCPI = (BAC - EV) / (BAC - AC) TCPI = ($10,000 - $3,600) / ($10,000 - $3,800) TCPI = $6,400 / $6,200 TCPI = 1.03

Analyzing Data for Trends $10 $5 $0 ($5) Schedule Variance ($10) ($15) Cost Variance ($20

Earned Value Analysis Time EAC $9.5 M CPI EAC ($7.5 M) SPI Baseline Budget CPI & SPI = 1 1.0 Time

Performance Report

Float and Management Reserves The project manager should control contingency reserve and schedule float The work at hand expands to fill the time available Expenditures will rise to meet the budget. The remaining “management reserves” should be added to EAC until such time when the reserve is no longer needed.

Earned Value Management System Performance Management Accurate Baseline Estimate Measure Performance against the Plan Analyze variances to Plan Assess impacts to Overall Plan Identify corrective actions Implement the corrective actions

Questions?