Data Center Construction Project Updates and Experiences Gary Stiehr May 6, 2008 HEPiX Spring 2008.

Slides:



Advertisements
Similar presentations
SM. FlexPod site readiness assessment services verify that all required Layer 1 Physical Infrastructure items are in- place, properly installed, and correctly.
Advertisements

Your Business Continuity Partner ! PEAK 10 – SOUTH FLORIDA.
Cabling system components
Chemistry safety Part 2.
Matt Warner Future Facilities Proactive Airflow Management in Data Centre Operation - using CFD simulation to improve resilience, energy efficiency and.
Network Design Issues Design and Documentation Prepared by: Aline L. Mendoza.
Cooling Strategies for Small IT Rooms Presented by Jim Magallanes TechniCool Innovations Inc Upham Street Suite B-1, Broomfield.
Managing Data Center Organizing your way to an easier Job.
The CDCE BNL HEPIX – LBL October 28, 2009 Tony Chan - BNL.
MAIN ELECTRICAL SURVEY ITEMS, GENERATORS AND GOVERNORS,, CIRCUIT BREAKERS, SWITCHBOARDS AND FITTINGS (Adapted from:D.T. Hall:Practical Marine Electrical.
Stairways and Ladders 1926 Subpart X - Stairways and Ladders
Cooling Product Positioning
Telenor Tier 3 Data Center April About Telenor Tier 3 Data Center Telenor built it´s own Data Centar in accordance with the latest industrial standards.
Chapter 19 Electrical Plans.
Chapter 6: Creating Robust Electrical System. What you will learn: Key element for building a reliable DC electrical system Design strategies for in-room.
OSHA Office of Training & Education
1 Telecom Cabling Ladder safety. 2 OSHA Office of Training & Education ation Telecom Cabling Stairways and Ladders.
DATA CENTERS INTRODUCTION Dr. Natheer Khasawneh. Goal… How Data Centers are critical environments for companies. Aspects of a Data Center's physical component.
 Site  Requirements  Local Resources  Initial layout ideas  Brief material selection  Supply options.
Computer Room Experiences A medium sized tier-2 site view Pete Gronbech GridPP Project Manager HEPIX April 2012.
Data Center Design Christopher Geyer. A Data Center Highly secure, fault-resistant facilities housing equipment that connect to telecommunications networks.
1 Telecom Cabling Ladder racks systems and relay racks Ladder racks systems and relay racks.
Design Considerations for Telecommunications Pathways and Spaces
1 Telecom Cabling Patch panels, cabinets and raised floors.
Campus Network Infrastructure Bangladesh University of Professionals(BUP) Prepared By: Mazharul Islam Tuhin.
October 23rd, 2009 Visit of CMS Computing Management at CC-IN2P3.
CSG Panel – May 10, 2006 Key Lessons for New Data Centers Project overview Requirements Lessons learned Going Forward.
31, May 2007 ILC DESY 07 1 Surface Building Design Development Tom Lackowski GDE.
Applying Precision Air Conditioning Systems
University of Michigan, CSG, May 2006 UM/MITC Data Center.
Office Layout Techniques and Space Requirements
Means of Egress Chapter 4.
New Data Center Update Brian Shannon & Anne Silvester.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
IMPACTS OF INSTALLING THE REFERENCE MAGNET PLACEMENT IN B december 2014 Fulvio Boattini & Natacha Lopez Hernandez.
Progress Energy Corporate Data Center Rob Robertson February 17, 2010 of North Carolina.
HVACR416 - Design Heat Loss / Heat Gain Part 1. Why? The primary function of Air Conditioning is to maintain conditions that are… o Conductive to human.
Thermal Design Project Final Report John Wallerich Principal Engineer Wallerich Group, LLC.
Infrastructure Improvements 2010 – November 4 th – Hepix – Ithaca (NY)
Nikhef/(SARA) tier-1 data center infrastructure
ID 234 Building Codes Fall 2012 Means of Egress Chapter 4.
Utility Engineers, PC.  Generation  Transmission  Distribution.
Requirements for computing room A. Gianoli, M. Serra, P. Valente.
Data Center Facility & Services Overview. Data Center Facility.
Computing Facilities CERN IT Department CH-1211 Geneva 23 Switzerland t CF CERN Computer Centre Consolidation Project Vincent Doré IT Technical.
Eastern USA University Academic Center Alexander AltemoseIStructural Option.
Modul ke: Fakultas Program Studi Teknologi Pusat Data 06 FASILKOM Teknik Informatika Approaching the Data Center Project.
Vault Reconfiguration IT DMM January 23 rd 2002 Tony Cass —
Hot /Cold Aisle Containment  Traditional Data Center/Telco designs are changing significantly!
1 PCE 4.4 New Development In DC Containment Steve Howell.
1 ITM 1.2 How IT Decisions Impact Data Center Facilities: The Importance of Collaboration Lars Strong P.E. Upsite Technologies, Inc.
CMTF GROUNDING FOR PIP-II K. Carlson PXIE Electrical Coordination Meeting December 19 th, 2013.
Accelerator Tunnel Layout (G01) Nick Gazis Senior Mechanical Engineer Review of ESS Accelerator Conventional Facility Design.
Flammable Liquids Directorate of Training and Education
Drafting 2 (Arch) Quiz Review #3 Quiz Review. 1.Dashed lines that follow the counters in a kitchen floor plan most likely represent: A dishwasher Upper.
West Cambridge Data Centre Ian Tasker Information Services.
FACILITIES PLANNING ISE310L SESSION 25 Warehouses, November 17, 2015 Geza P. Bottlik Page 1 OUTLINE Questions? Any supply chain or facilities stories or.
The Genome Sequencing Center's Data Center Plans Gary Stiehr
CANOVATE MOBILE (CONTAINER) DATA CENTER SOLUTIONS
Data centre network map
Unit 2: Chapter 2 Cooling.
Update of MVD services and requests
CERN Data Centre ‘Building 513 on the Meyrin Site’
WP02 PRR: Master Oscillator and RF Reference Distribution
Extension SR1 WP3 Electrical installations
Engineering Project Cable Management.
Chapter 19 Electrical Plans.
ActivRAC® Layout Considerations
Liebert DSE High efficiency thermal management
Approaching the Data Center Project
Presentation transcript:

Data Center Construction Project Updates and Experiences Gary Stiehr May 6, 2008 HEPiX Spring 2008

Overview Existing data center filled and power and cooling at their limits Started construction approximately 10 months ago on new data center Originally expected four phases to get to 1,800 kW of redundant power/cooling Expanded Phase 1 to 750 kW from 450 kW Anticipate just two more phases

Clarification Clarification from data center talk at HEPiX Fall 2007 in St. Louis: 16,000 sq. ft. figure mentioned includes all real estate space inside and outside and partial second floor 3,200 sq. ft. is usable data center space, about 96 sq. ft. used by Remote Power Panels. Many sites not calculating usage of external real estate space; only percentage of raised floor space used by infrastructure

Current Status Phase 1 is mostly complete: power and cooling for 750 kW Installing seismic bases, racks and structured cabling this week and next week Delay from manufacturer for 5kV switch gear –No generator backup until mid June –Temporary solution in place; no downtime to fix

Equipment Racks Standardizing racks, especially height –Height: 47U 40U for equipment 7U for patch panels and other (e.g., switches, monitoring devices, grounding bus bar, etc.) –Width: 24” (610 mm) for servers, 32” (813 mm) for network –Depth: 48” to accommodate more power without taking away from cable management space Standardization: versatile, consistent deployment, easier to enclose cold aisles

Equipment Racks: Considerations Check that doorways are tall enough throughout delivery path to accommodate taller racks Fire codes/regulations require a minimum clearance from ceiling to top of racks for fire suppression system Isolating seismic vibration Weight limits: increasing density and weight Baying together helps with tipping hazards?

Power Delivery 3-phase, 30 A, 208 V to the rack: Need to balance between phases in rack? Use 60 A circuits for racks with higher loads? –Fewer power whips to rack –Fewer PDUs in the rack –More expensive to construct power whips? Does anything need 120 V any more? –L21-30R vs. L15-30R receptacles

Floor Layout Remote Power Panel (RPP) cabinets –Larger than originally specified –Placed such that row starts with a half tile –One at each end of row so racks confined between them Considerations for seismic isolation –St. Louis is in a 2A seismic zone –Bracing to concrete floor thought to pass vibration to equipment, which may cause damage –Using ISO-Base™ Seismic Isolation Platform Requires 8.5” (215.9 mm) clearance on all sides Plus additional 2” (50.8 mm) at ends if leveling feet are used on racks

Floor Layout (2) Racks may set on multiple tiles due to wider racks, RPP clearances and seismic base clearances: –Raised floor cutouts may cross two tiles –Implications on how to adjust cooling for a particular rack –Rack labeling scheme needs to take this into account if it is based off of raised floor tile grid system

Structured Cabling Patch panels in each rack (EDA), running to core patch cabinets (MDA) Category 6a (a=augmented) standards recently ratified –10 Gb/s over copper over longer distances More 10 Gb/s copper-based devices? –Comparing costs with fiber and SFPs –For cost, use cat5e/6 patch cables for management networks?

Safety 3-foot raise floor: block off work areas as usual ServerLift for loading equipment racks ECARO-25 clean agent fire suppression Alarms, controls: –White light and alarm for external fire/smoke –Amber light and alarm for ECARO-25 stage 1 fire/smoke inside server room –Bell ringing for stage 2; 30-seconds to release EPO (Emergency Power Off) button ECARO-25 temporary abort button ECARO-25 forced activation button

Building Services Do you know who will provide these: Maintenance on electrical/HVAC systems Custodial/Housekeeping services inside server room, office, mechanical rooms, etc. Staffing receiving dock (and when). Access control (e.g., swipe card system) Telecommunications (e.g., phone lines, fax) Cardboard recycling, disposal of other packaging?

Future Work Establishing more formal monitoring of temperature, air flow and electrical usage Phase 2 planning is beginning –Increase redundant power/cooling capacity to 1350 kW –Potentially enclose cold aisles but may wait for next and final phase to gather enough data

Lessons/Advice If you are new to data center planning: Start thinking about the considerations/options early Consider dedicating most of an FTE to this planning and narrowing options Continually verify measurements and placements within server room.

Questions?