2011 Raze & Removal Pilot The WisDOT Northeast Region embarked on a new raze and removal process on a project in Sheboygan & Fond du Lac. It’s purpose.

Slides:



Advertisements
Similar presentations
FAA Project - Bidding Phase FAA Recommends.. Consider how you would like to bid the project early on in the design. Due to possible budget constraints.
Advertisements

Metro Muncipal Agreement Program
East Hampton High School July 2013 – July 2014 Design Phases.
Requirements for Federal Aid Project Contracts Kenneth Spear, Contracts & Estimates Engineer.
 Examples of bid-splitting Acceptable – When a project involves different trades and is not interdependent on the other. - If you are upgrading a room.
Open Procurement Process Gauteng Provincial Treasury Process Mapping 30 th October 2014.
Oklahoma Department of Transportation Susan McClune Regulatory Services.
John Boon ZUT November Procurement Systems The organisation of the interaction between the purchaser of a new building and the suppliers of goods.
Skyscraper Construction
Dillon and Christina Project Area Lander Streets and Utilities 2015 Public Meeting No. 2.
With the Genesee County Road Commission By Fred Peivandi, P.E. And Ken Johnson, P.E. Local Road Funding.
AWARD OF CONTRACT FOR CONSTRUCTION OF MASTER DRAINAGE FACILITY LINES D & D1 CIP NO City Council Meeting December 20, 2011.
Marcy Mealy Procurement Specialist CDBG Program
1 Construction Cost Impacts Florida DOT Experience Greg Davis State Estimates Engineer Florida Department of Transportation Greg Davis State Estimates.
Hide-A-Way Lake, Inc. Low Pressure Sewer System Prepared by Dungan Engineering, P.A.
Undulator Long Lead Procurements Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center.
Understanding Right of Way Process Dawn Haecker - Training & Technical Support Supervisor INDOT Trent Newport - VP, CrossRoad Engineers.
Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015.
PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract.
What Are Construction Documents Construction documents serve as a means of obtaining bids from contractors and are used by contractors to obtain price.
Chapter 4 The Construction Process. Objectives After reading the chapter and reviewing the materials presented the students will be able to: Explain the.
SPORT MANAGEMENT 302 (a) B. FLAHERTY Questions/Comments?? Quiz next week, Chapters 1-6 Complete Chapter 7 “Funding and the Bid Process” Chapter 8 “Constructing.
Public Works Contracting Marsha Reilly Office of Program Research House of Representatives recommended.
Bridge Building Timelines Presented by The Richland County Engineers Office Thomas E. Beck, PE, PS 77 North Mulberry Street Mansfield, Ohio Jan.
Purchase Plus Improvements Financing Seminar. “You Love The House, But……!!!”
ESTIMATES UPDATE TRAINING BULLETINS FOR 2013 Melissa Hollis, Basis of Estimates Coordinator August 1, 2013 webinar.
U.S. General Services Administration Term Contracts Drand Dixon Sales Contracting Officer Federal Acquisition Services Drand Dixon Sales Contracting Officer.
Mn/DOT AUDIT COUNTY HIGHWAY ACCOUNTANTS SINGLE AUDIT DISCUSSION.
Armstrong World Industries Ceiling Tile Recycling Neal McDwyer Recycling Manager Hi I am Anita Snader from Armstrong World Industries, Commercial Ceilings.
NC Region Speakers:. Now What?  EBS  Pothole  Vac Truck  T & M  Force Account  Con Mod/Change Order  LCS  QMP (QC, QV, IA)  QC  QV  IA Excavation.
HIGHWAY/UTILITY PROGRAM OVERVIEW ROADWAY CONFERENCE APRIL 20, 2009.
Working Successfully With Property Managers: An Interactive Engagement
PROPERTY MANAGEMENT RAZE & REMOVAL. PROPERTY OWNER HAS FIRST RIGHT OF REFUSAL n The property owner has first right of refusal to retain and move their.
Requirements for Federal Aid Project Contracts Kenneth Spear, Contracts & Estimates Engineer.
2010 CDBG Recipients’ Workshop The Housing Rehabilitation and Reconstruction Monitoring Reviews… How to Successfully Pass.
YUSUF OZ FATIH BOLUKBAS HUSEYIN ANIL KARABULUT. A contract is a legally binding agreement between two or more parties.
Understanding Right of Way Process Dawn Haecker, Training & Technical Support Supervisor, INDOT Trent Newport, VP, CrossRoad Engineers.
1 Procurement. 2 Overview Every municipality should keep procurement records that allow an auditor or other interested party to track the specific nature.
Residential Permit Requirements. When do I Need a Permit A new building, structural change, addition, finishing and unfinished area Deck Covered porch.
Local Government Section Welcome Marty Andersen ODOT Local Government Section 355 Capitol Street NE, Rm. 326 Salem, Oregon Ph:
This certificate is awarded to _____________________ on this 31 st day of May, _____________________.
Contractor having difficulties performing work Contract Default Read Spec section 8-9. Talk with DCE about options. Various letters of concern may come.
Estimating PS&E – Plans, specifications and estimate 1.
Asbestos Renovations and Demolitions in South Carolina Lynn Barnes, Manager Asbestos Section SC Dept. of Health & Env. Control Phone: (803)
IDM Chapter 104 Utility Coordination Gail Lee Utility and Railroad Engineer, INDOT June 10, 2015.
DESY_ILCW07 Global Design Effort-CF&S 1 Beam Delivery System & Interaction Region Fred Asiri CF&S Point of Contact.
FOR CLERKS AND RECORDERS  Planning Commission – public meeting and a public hearing  City Council – public hearing  Must contain: - a map of expansion.
Mark Krause and Kassandra Walbrun WisDOT-BTS Session C.
Dawn Van Oudenhoven – WisDOT NE Region Jacob Hoagland – Asset Equipment Appraisals September 30, 2015 Chula Vista Resort, Wisconsin Dells.
CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE.
PUBLIC INPUT SESSION NOVEMBER 10, 2015 City of Asbury Birchwood Drive Reconstruction Project.
Stacy Hagenbucher.  Process Improvements  Clarification  Trends  Finals Tracking  Trends  Why Missing Dates  Additional Resource  Issues on sites.
Introduction to Procurement for Public Housing Authorities Sealed Bids Unit 5.
Permit Process & Application Guide
WEST DES MOINES LIBRARY ADDITION Team North Final Presentation Team North The Ace Mentor Program career direction for students in architecture,
PROJECT DEATH Stephanie Rich. Corrective Work Punch List Punch List Work Complete Date Work Complete Date Request Final(s) Request Final(s) Comprehensive.
The Public Tendering and Bidding (招投标) Law of the People's Republic of China Effective since January 1, 2000.
PUBLIC IMPROVEMENT HEARING 2015 Street, Utility and Retaining Wall Improvements - Grandview Boulevard November 12, 2014 (continued to December 9, 2014)
The Housing Rehabilitation and Reconstruction Monitoring Reviews… How to Successfully Pass.
City of Dayton Department of Planning & Community Development
Mike Ellis Executive Director – Property + Projects
The Alabama Transportation Rehabilitation and Improvement Program
Estimating Project Costs
PS&E – Plans, specifications and estimate
2429 Iowa (Suite B-D) Your Business 13,000 SF available Office Space
How & When to Get Permits for Work in Your Home
Understanding the Right-of-Way Process
Payment of the contractor: the cumulative value of work done
Diversity management system (DMS)
Fiber Reinforced Polymer Systems
Presentation transcript:

2011 Raze & Removal Pilot The WisDOT Northeast Region embarked on a new raze and removal process on a project in Sheboygan & Fond du Lac. It’s purpose was to: Reduce time frames to clear sites Reduce possibility of vandalism Reduce efforts on Property Management

Begin the Process Real Estate Property Manger will obtain assessment cards for each parcel Project Development Creates the Contract Determines weight of each structure by using the square footage Use Bing Maps to verify the structures Use surveys that were used in the planning of the project to determine property lines

Estimating Weights House – 1 st Floor w/roof 60#/SF – 2 nd Floor 40#/SF Outbuildings – Pole Shed 40#/SF – Sheds 40#/SF – Garages 40#/SF – Barns 60#/SF Decks – 26#/SF Foundations, concrete floors and driveways were estimated by square foot but were not estimated per pound. The contractor bidding on the project would have to add that into his bid.

Contract Includes Remove all structures (house, barn, silos) Remove foundations, concrete & asphalt Remove septics & wells Remove all landscaping & fencing Backfill & grading Fertilize & seed – Contractor will have 10 days to begin demolition – Has 14 working days for removal – Contractor is paid on quantities not lump sum as done with other contracts

Project Development creates contract documents, Special Provisions, and sets LET date Madison will award contract to lowest bidder

Property Manager’s Responsibility once parcel is vacated Order asbestos inspection & removal Disconnect all utilities Complete Certificate of Right of Way for each parcel as it becomes available and send it to the Project Development Section with the asbestos information.

Project Development’s Responsibility: Send Certificate of Right Way to Bureau of Technical Services in Madison for approval Issues a Notice to Proceed parcel by parcel to the Project Engineer & Demolition Contractor Project Engineer on site verifies any measured quantities and collects weight tickets Project Engineer notifies Project Development Section when site is cleared

Comparing the Old to the Pilot