Beam Dumping System – Failure Scenarios Brennan Goddard, CERN AB/BT How the dump system can fail Catalogue of primary failures Failure classes and protection.

Slides:



Advertisements
Similar presentations
12/03/2013MPP Workshop Annecy Update on Beam Failure Scenarios Jan Uythoven Thanks to: T.Baer, R.Schmidt, J.Wenninger, D.Wollmann, M.Zerlauth, other MPP.
Advertisements

Performance reach of LHC beam dump B.Goddard: input from L.Ducimetière, W.Bartmann, V.Mertens, J.Borburgh, F.Velotti, M.Barnes, C.Bracco, V.Senaj, M.Meddahi,
CAS June Stored energy and risks Failures Protection systems Beam Instrumentation Case studies Conclusions Machine Protection Rüdiger Schmidt CAS.
PAC June LHC Machine Protection Rüdiger Schmidt R.Assmann, E.Carlier, B.Dehning, R.Denz, B.Goddard, E.B.Holzer, V.Kain, B.Puccio, B.Todd, J.Uythoven,
Concept & architecture of the machine protection systems for FCC
FCC-hh Injection and Extraction
B.Goddard 08/11/04 HHH 2004 Workshop, CERN Beam Dump Brennan GODDARD CERN AB/BT The existing LHC beam dump is described, together with the relevant design.
BIW May 2004 LHCSILSystemsBLMSSoftwareResults Reliability of BLMS for the LHC. G.Guaglio, B Dehning, C. Santoni 1/15 Reliability of Beam Loss Monitors.
Overview of Machine Protection for the LHC
Changes to IR6 dump protection elements B.Goddard, W.Weterings, C.Maglioni, R.Versaci, T.Antonakakis, R.Schmidt, J.Borburgh, J.Blanco, plus many other.
The LHC injection systems located in points 2 and 8 are comprised of several elements common to the LHC ring and the downstream ends of the TI 2 and TI.
LER Workshop, CERN, October 11-12, 2006Detector Safety with LER - Henryk Piekarz1 LHC Accelerator Research Program bnl-fnal-lbnl-slac Accelerator & Detector.
1 Joint LHC Machine-Experiments Meeting on Experiment Protection from Beam Failures Summary and action list D. Macina TS/LEA/INT LEMIC 91.
Etienne CARLIER, LBDS Audit, 28/01/2008 LBDS Environmental Aspects EMC, radiation, UPS… Etienne CARLIER AB/BT/EC.
1 Beam Dumping System MPP review 12/06/2015 Jan Uythoven for the ABT team.
1 Reliability and Availability of the Large Hadron Collider (LHC) MachineProtection System Jan Uythoven CERN, Geneva, Switzerland Thanks to R. Schmidt,
B.Goddard LHC Risk Review6 th March 2009 Beam dump dilution failure B.Goddard CERN TE/ABT On behalf of the LHC Beam Dump project team.
1 Will We Ever Get The Green Light For Beam Operation? J. Uythoven & R. Filippini For the Reliability Working Group Sub Working Group of the MPWG.
1 CC & MP - CC10 - CERN Crab LHC J. Wenninger CERN Beams Department for the LHC Machine Protection Panel.
Status of ABT beam tests preparation 9-Oct-14. Preparation of sector test without beam I MKI: – Open valves, conditioning to 55 kV, softstart – Check.
Updates on FLUKA simulations of TCDQ halo loads at IR6 FLUKA team & B. Goddard LHC Collimation Working Group March 5 th, 2007.
Simulations of TCT beam impacts for different scenarios R. Bruce, E. Quaranta, S. RedaelliAcknowledgement: L. Lari, C. Bracco, B. Goddard.
B.GoddardChamonix LHC Performance1 Chamonix 2009 – LHC Performance Workshop Worst case beam incident causes and protection B.Goddard TE/ABT Based.
Overview WP14 Developments Hardware  Interferometry on the spare TDIs, planned to be installed Christmas stop 2015/2016. Final acceptance tests ongoing.
18 July Reminder Dilution kicker system MKB is staged (2H, 2V) –Limits extracted intensity at 7 TeV to 50% of nominal –For 25ns spacing, this is.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
FCC DUMP SYSTEM W. Bartmann, B. Goddard, R. Ostojic FCC Dump Meeting, 14 th Jan
LHC beam dump, injection system and other kickers B.Goddard, with input from L.Ducimetière, W.Bartmann, V.Mertens, J.Borburgh, M.Barnes, C.Bracco, V.Senaj,
Injection and protection W.Bartmann, C.Bracco, B.Goddard, V.Kain, M.Meddahi, V.Mertens, A.Nord, J.Uythoven, J.Wenninger, OP, BI, CO, ABP, collimation,
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Beam absorbers for Machine Protection at LHC and SPS
HL-LHC WP14 2 nd meeting: Intercepting devices and failure cases to be studied Anton Lechner, Jan Uythoven.
V. Kain AB/OP1Chamonix XV What is required to safely fill the LHC? V.Kain AB/OP Input from: B.Goddard, M.Jonker, Y.Kadi, R.Losito, V.Mertens, B.Puccio,
C. Bracco, R. Bruce, B. Goddard, C. Wiesner, A. Lechner, M. Frankl
The TV Beam Observation system - BTV
BEAM LOSS MONITORING SYSTEM
Dependability Requirements of the LBDS and their Design Implications
Beam dump XPOC analysis
Chamonix 2009 – LHC Performance Workshop
Surviving an Asynchronous Beam Dump?
The LHC Beam Dumping System
Introduction: FCC beam dumping system
LHC beam dump 7.56 TeV operation
SPS extraction, transfer lines, injection
The LHC - Status Is COLD Is almost fully commissioned
Potential failure scenarios that can lead to very fast orbit changes and machine protection requirements for HL-LHC operation Daniel Wollmann with input.
Jan Uythoven For discussion
LHC Risk Review: Kicker Magnet Reliability
FCC hh dump kicker - switch topologies and impact on beam
Overview on LHC Machine Failure Scenarios
Safe Injection into the LHC V.Kain AB/CO
BEAM LOSS MONITORING SYSTEM
Protection Against Accidental Beam Losses at the LHC
FCC-hh injection group 7
Safe Injection into the LHC V.Kain AB/CO
Initial Experience with the Machine Protection System for LHC
CNGS Primary Beam Results 2010
Machine Protection Xu Hongliang.
Interlocking of CNGS (and other high intensity beams) at the SPS
LHC Injection and Dump Protection
Beam Dumping System and Abort Gap
Chamonix 2006 – LHC Project Workshop
Protection against accidental beam loss at the LHC
Chamonix Workshop XIV CERN - 17th-21st January 2005
Will We Ever Get The Green Light For Beam Operation?
Machine protection and closed orbit
Machine Protection Issues for LHCb
The LHC Beam Interlock System
Interlocking strategy
Presentation transcript:

Beam Dumping System – Failure Scenarios Brennan Goddard, CERN AB/BT How the dump system can fail Catalogue of primary failures Failure classes and protection Specific failures cases –Dilution failure (missing) –Extraction kicker erratic –Extraction kicker missing –Injection / dump “single turn deadlock” Spares policy issues With R.Filippini, J.Uythoven, E.Carlier, V.Mertens, V.Kain, L.Ducimetiere, L.Bruno, W.Weterings, R.Assmann et al.

HW monitoring PIC, QPS, PCS, FCDM, system status Potentially dangerous events Injection process Single turn Circulating beam Beam Interlock system BIC, beam permit loop, data transmission, interfaces Beam dump system MKD, MSD, MKB, TDE, BET Effect on beam Transfer / injection process Settings monitoring Beam monitoring BLM, BCT, BPM, Collimators Passive protection systems TPSG, TCDI, TDI, TCDD, TCLI, TCDS, TCDQ HW changes Machine Protection System ‘core’Monitoring Fast (<few ms) Slow (>few ms) SW changes “Failures” Only one LHC beam dumping system : must not fail ‘unsafe’.  failures of the beam dumping system must either: - be safe for LHC (interlock, protection, no damage), or - have an extremely low probability to occur (≥ SIL3) Reminder

Dump system – functional blocks

Failures, protection and consequences Detection + PLL takeover TCDQ positioningConsequence success failure TCT positioning RF frequency signal failure success failure success failure Normal dump Asynch dump & IR6 quench TCT damage LHC triplet damage

Primary failure scenarios

1.Should not happen in the LHC lifetime (“beyond design”) –Not receiving trigger from Beam Interlock System after failure in LHC –Failure of beam energy tracking –< 14 / 15 extraction kickers –< 3 / 10 dilution kickers 2.Protected against by surveillance and interlocking (dump while conditions still ~ok) - majority –Failures of general services (electricity, vacuum, cooling, Ethernet, …) –Bad beam position (BPM, BLM) –Magnet powering failure (PIC, FCCM, BETS) –Large abort gap population 3.Cannot be prevented by surveillance (kicker faults associated with dump action) a)Can be tolerated without damage –Missing extraction kicker magnet –Missing dilution kicker magnet –Erratic dilution kicker magnet b)Cannot be tolerated: rely on passive protection devices –Extraction kicker erratic (spurious asynchronous trigger) –Single turn injection/dump deadlock Failure classes

Dilution kicker failures Nominal sweep profile Energy deposition in C dump block (7 TeV ultimate beam) 7 TeV 450 GeV Normal operation: sweep beam in ‘e’ shape over the face of the dump block 4xH and 6xV kicker magnets

Dilution kickers failures : missing units Nominal (4H, 6V) Missing 1H (3H, 6V) Missing 4H (0H, 6V) Missing 1V (4H, 5V) Missing 6V (4H, 0V)Missing 4H, 6V (0H, 0V) total dilution failure Shown for 450 GeV beam spot (   6 mm)

Energy deposition and  T Large amount of redundancy. Values quoted for LHC ultimate (50% above the nominal) Concern is total dilution failure: L.Bruno of either H or V leads to contained dump block damage (cracks) of both H and V leads to perforation of dump block & exit window. Dilution kickers failures : missing units

Local protection collimator TCDQ Extraction kicker failures : erratic (asynchronous dump) Retrigger remaining 14 kickers in ~ 700ns - Crossed and redundant retrigger lines ~120 bunches swept across LHC aperture - Local collimators protect & limit excursions R.Assmann

Asynchronous dump: elements at risk H-plane Extraction septumSC quadrupole Q4 TCDS (intercepts ~40 bunches) protects the extraction septum TCDQ +TCS (~27 bunches) protect Q4 magnet, AND downstream LHC - The latter implies precise (±0.5  ) positioning of the jaw WRT beam…. Septum collimator TCDS Q4 collimator TCDQ

Prototype TCDS collimator – graphite blocks and beam screen TCDS vacuum tanks and layout Prototype TCDS collimator – support structure Asynchronous dump : fixed septum collimator TCDS W.Weterings

Asynchronous dump – protection and energy deposition Instantaneous loads due to asynchronous dump at 7 TeV (ultimate beam) Peak load (J/cm 3 )  T (K) TCDS collimator MSD septum TCDQ collimator TCS collimator TCDQM mask MCBY corrector 26 7 MQY Q Q4 instantaneous damage limit = 87 J/cm 3 [OK] MSD design limit on  T = 100  C[OK] Graphite / C-C melting point = 3700  C[OK] C-C thermal shock checked [OK] Particle fluence scoring on TCDQ, TCS, MCBY and MQY (Q4) for async dump TCDQTCSTCDQM MCBYMQY (Q4)

Extraction kicker failures : missing unit n1=6.5 n1=6.9 22 22 100% 110% 5.7  TCDS MSDA MSDB MSDC 15/15 MKD 14/15 MKD At 450 GeV, worst case with 14/15 MKD gives ~2.7  clearance at TCDS, or ~10 12 p+ on collimator (well below damage limit, but may cause quench) At 7 TeV, enough aperture (~10  ) with 14/15 MKD to avoid losses on TCDS

Special “failure” – injection / dump single turn deadlock 1.Beam dump triggered 2.Injection inhibit sent to IR2 3.Injection just before signal arrives 4.Injected beam travels to dump, which is out of tolerance by the time it arrives A potential problem….

20  s :Time to generate Injection Inhibit signal 65  s :Time for signal to propagate 13 km from IR2 to IR6 20  s :Time for injection system to react to Injection Inhibit signal 45  s :Time for injected batch to travel 13 km from IR2 to IR6 150  s : Total (between beam dump trigger, and latest time an injected batch could arrive at the extraction kicker) Extraction kicker field: 81.6 – 83.9 % Injection / dump single turn deadlock

288 bunches not correctly kicked, but either all extracted or (in worst case trajectory) impact extraction septum collimator TCDS.  LHC is protected. Injection / dump single turn deadlock

“Beyond design” failures… Track beam trajectory to determine elements at risk. ~straightforward in dump region: damage to extraction elements (collimators, septa, dilution kickers) and Q4, Q5 machine elements.

Total dilution failure: spare dump blocks exist –Will take some days to change the elements –Down-time probably dominated by cool-down, inquiry, system inspection, etc. 2-9 extraction kickers missing: TCDS and septa damaged / destroyed –TCDS spares exist; for septa 3 spare magnets (1 per type) for 30 installed. Could damage 2-7 magnets (10-30m beam range) – e.g. all 5 of type A. –Rebuilding septa would presently take ~1-2 years. More spares? Alternatives? Some beam energy tracking failures: dilution kickers also at risk –1 spare magnet per type (H/V). Rebuild ~1-2 years. –More spares? Low-tech, sacrificial absorber to protect magnets? Needs study Asynchronous dump + mobile TCDQ collimator position failure : damage triplet collimators TCTs –Presently only few (1?) spares foreseen. Foresee more? Tracking needed. Worst-cases: Interlock, dump system, energy tracking failures: quantify expected damage for common initiators (trips, quenches) –Tracking studies needed to determine loss locations “Beyond design” failures and spares

Unexpected failures? Experienced one erratic in MKD kicker testing –30 kV high voltage, 2  C capacity means ~1.5 kJ energy in the capacitors –Not very much for the kicker magnet... ….but more than enough for the sparrow, which acted as an unorthodox switch to earth. (nb series generators fully enclosed) Serious message: this ‘failure’ in LHC would have lead to asynchronous dump  fault - tolerant design allows some unexpected failures to be survived MKD prototype generator HV terminal Sparrow

Conclusions Many possible failures for beam dumping system –Analyses to date (and results from prototypes) have given confidence in chosen solutions The identified failures are either safe for the LHC, or not expected to occur in LHC lifetime, or can be prevented with interlocking –Some difficult aspects remain to be demonstrated Safety of Beam Energy Tracking system (see next talk) Positioning of mobile collimator TCDQ with respect to beam –“Beyond-design” failures have serious consequences which could conceivably be ameliorated Tracking studies needed to quantify extent of potential damage Spares policy to re-examine, and/or other options to be studied (e.g. sacrificial absorbers), to reduce down-time for some cases