MSI-V J. Borburgh, B. Balhan, E. Carlier, J.M. Cravero, B. Goddard, D. Nisbet, P. Van Trappen, F. Velotti.

Slides:



Advertisements
Similar presentations
Internal H0/H- dump Cesare Maglioni, Melanie Delonca Thanks to: R. Chamizo, R. Versaci, O. Aberle, J. Borburgh.
Advertisements

Design and Technical Challenges of the ILC Small Angle Interaction Regions October 20 th, 2006J. Borburgh, CERN, AB/BT Electrostatic separator limits and.
Yury CHESNOKOV Crystal Collimation workshop, March 7, 2005 CALIBRATION of CMS CALORIMETERS with LHC PROTON BEAM DEFLECTED BY CRYSTAL CALIBRATION of CMS.
FCC-hh Injection and Extraction
4 November 2014 Mike Hourican TE/ABT1 LIU-SPS Injection Upgrade With input from Jan Borburgh, Bruno Balhan.
Sergey Antipov, University of Chicago Fermilab Mentor: Sergei Nagaitsev Injection to IOTA ring.
LHC Beam Screen Heaters: System overview, consolidation needs and project planning 4 February TE-CRG/JCC (Beam Screen Heater Review) 1.
CIEMAT ACTIVITIES ON STRIPLINE KICKERS I. Rodríguez.
Powering the main linac implications Daniel Siemaszko, Serge Pittet OUTLINE : Cost impact of power converters, power consumption and powering.
PSB h- injection Layout issues –Are 3 or 4 KSW needed –Geometry of the injection –Element lengths and locations Element performance specifications H 0.
Eric Prebys USPAS, Knoxville, TN, Jan , 2014.
Design and operation of existing ZS B.Balhan, J.Borburgh, B.Pinget B.BalhanDesign and operation of existing ZS SPS ZS Electrostatic Septum Upgrade Review.
Design and Technical Challenges of the ILC Small Angle Interaction Regions October 19 th, 2006J. Borburgh, CERN, AB/BT Electrostatic separator limits With.
HPS Collaboration Meeting JLAB, May Tracker Design Status M.Oriunno, SLAC.
F Booster Long Straight Corrector Upgrade Technical Status and Schedule for Installation Craig Drennan DOE Tevatron Operations Review March 27, 2007.
ALBA Vacuum System, E. Al-Dmour Vacuum Systems for Synchrotron Light Sources 12 th -13 th Sep ALBA Vacuum System ALBA VACUUM SYSTEM E. Al-Dmour On.
New injection region 1L1 Engineering Change Request PSB-L-EC-0001 EDMS Wim Weterings PLI Meeting Wednesday 14 th January 2015.
The Stripping Foil Test Stand in the Linac4 Transfer Line
2 Davide Aguglia TE-EPC-FPC Sept. 23 rd rd PSB injection EPC powering rack space coordination meeting Stripping foil chicane BSW magnets powering.
BI.DIS10: Magnets & generators R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November
Sketching Basic Kicker System Parameters W. Bartmann, T. Fowler, B. Goddard, T. Kramer.
Transformer positions for BISMV and BSW M. Hourican 2 March 2015.
Discussion and preliminary conclusions LIU-SPS ZS Electrostatic Septum Upgrade Review M.J. Barnes.
7 November 2003 Status of CNGS NBI presented by K. Elsener 1 Status of CNGS Konrad Elsener CERN – Accelerators+Beams Division.
R. Rosol, LIU-PSB review, 10 September BI.DIS Pulse generators R. Rosol, LIU-PSB review, 10 September Luc SERMEUS, Rodolphe ROSOL Laurent.
Proposed Conventional Sextupole for Installation at A0 Introduction (Dean Still) Reasons for installation- Reduce I in S6 feeddown sextupole circuit at.
Consolidation of the Booster Injection Quadrupole Magnets (part 2) A. Aloev 14 th February 2013.
ESS | A Preliminary Feasibility Assessment of Power Converters and Magnets for Beam Raster System| | Carlos A. Martins, ESS Preliminary Feasibility.
LER Workshop, October 11, 2006LER & Transfer Line Lattice Design - J.A. Johnstone1 LHC Accelerator Research Program bnl-fnal-lbnl-slac Introduction The.
Status of ATF Fast Kicker Experiment
Electronics issues for MTE Etienne CARLIER TE/ABT Outline: o CAMAC eradication o PPM limitations o Electronics & Controls for MTE only CT only CT-MTE hybrid.
Outline Injection septum SMH42 Injection bumper Resources Conclusion LIU-ABT review 20/11/2015 Status PS injection septa2.
Comparing current waveforms and shielding options for SMH42 Zsolt Szoke LIU-PS Meeting, 16/12/2014.
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
LIU-ABT systems: SPS T. Kramer, E. Carlier, L. Ducimetiere, L. Sermeus, J. Uythoven LIU-IONS 4 th November /11/2014 SPS LIU-ABT Systems Review2.
R. A. Barlow, LIU-PSB review, 20 Nov BI.DIS Pulse generators controls R.A.Barlow, LIU-PSB review, 20 Nov
FCC DUMP SYSTEM W. Bartmann, B. Goddard, R. Ostojic FCC Dump Meeting, 14 th Jan
Principals of fast injection and extraction R. Apsimon.
2016/3/31 Fast kicker Experiment at ATF ATF2 - 40nm beam production, measurement Extraction kicker The difficulty of the beam extraction is that the kick.
Preliminary Design of Electron Beam line F. Velotti, C. Bracco, B. Goddard and M. Meddahi.
The integration of 420 m detectors into the LHC
LHC beam dump, injection system and other kickers B.Goddard, with input from L.Ducimetière, W.Bartmann, V.Mertens, J.Borburgh, M.Barnes, C.Bracco, V.Senaj,
TPSG4 validation at HighRadMat #6 Cedric Baud, B. Balhan, Jan Borburgh, Brennan Goddard, Wim Weterings.
ELENA KICKERS AND SEPTA ELENA Meeting, Prepared by J. Borburgh, E. Carlier, A. Fowler, L. Sermeus TE/ABT.
L. Sermeus TE-ABT-FPSELENA IIC meeting 3 th April Review of ELENA Injection kicker Luc Sermeus on behalf of WP 2.8 (with informations from EN-MME)
Udo Blell - Synchrotrons 1 Udo Blell GSI, Darmstadt MAC – 7 April 2 th - 3 th, 2012 FZ - Jülich SIS 100 Injection / Extraction systems.
Beam transfer considerations for LAGUNA Angelina Parfenova, W. Bartmann, L. Ducimetiere, B. Goddard, V.Kain, M.A. Kowalska, M. Meddahi, B. Puccio, F. Velotti.
T. Kramer, CERN TE/ABT FCC-week 2016, Rome, Italy Acknowledgements
Cost and schedule for ELENA Beam Transfer Systems W. Bartmann, J. Borburgh, E. Carlier, L. Ducimetiere, T. Fowler, M. Hourican, R. Ostojic, L. Sermeus.
MSE Pulsed Septum for g-2 and Mu2e Design Review A. Makarov 2/11/2016.
26/11/2015 LIU-PSB meeting, Status of BE and BT kickers and septa 2 Extraction and Recombination Septa and Kickers status Jan Borburgh, M. Atanasov, W.
Baseline Injection/Extraction Configuration Aimin Xiao and Louis Emery, September 12th 2006.
PS2 WG Injection and extraction systems Basics and assumptions
Areal RF Station A. Vardanyan
TPS pulse magnet measurement
SMH16 eddy current septum
BEAM TRANSFER CHANNELS, INJECTION AND EXTRACTION SYSTEMS
LINAC4 ADVISORY COMMITTEE
(Beam) Impact of MTE on the PS septa
AD consolidation activities in LS2
Power converters for 2GeV injection
PROGRESS REPORT OF A NLNS-FFAG ADS MAGNET
Possible causes for SPS ZS2 misalignment
Arc magnet designs Attilio Milanese 13 Oct. 2016
Septa requirements and suitable septa topologies for FCC
Power supply and Electrostatic separator for CEPC
Main magnets for PERLE Test Facility
Compact and Low Consumption Magnet Design The DESY Experience
FCC-hh injection group 7
III. Correction Dipoles MDG Accessories for all Magnets V. Summary
Presentation transcript:

MSI-V J. Borburgh, B. Balhan, E. Carlier, J.M. Cravero, B. Goddard, D. Nisbet, P. Van Trappen, F. Velotti

outline 1.Septum requirements 2.Retained septum concept 3.Mechanical concept and integration 4.Magnet control electronics 5.Power supply 6.Planning and resource requirements

Injection trajectory MSI-V blade Courtesy: F. Velotti TIDVG MSI

Septum requirements Beamp [GeV/c]B.Rho [T.m]Angle [mrad]B.dl [T.m] LHC/FT ions LHC p CNGS p Values indicated assume:  3.0 m magnetic length  60 mm full vertical gap  5 mm septum width Flat-top: tentatively over at least 100 µs (depending on timing accuracy?) Requested margin on magnet strength: being able to deflect protons 13 mrad at 26 GeV

outline 1.Septum requirements 2.Retained septum concept 3.Mechanical concept and integration 4.Magnet control electronics 5.Power supply 6.Planning and resource requirements

Basic magnet characteristics Under vacuum pulsed magnet Assuming half sine with third harmonic: 100 μs at precision → pulse width >~800 μs Layout proposed: 2 magnet blocks under vacuum 5 mm thick copper/stainless steel septum blade 1 single vacuum vessel

Magnet parameters Magnetic length mm Physical length mm Gap height60.4mm Horizontal aperture102mm Magnetic field0.541T ∫B.dl T.m Deflection angle mrad I peak 28.2kA Pulse width~3ms Septum thickness (copper + s.steel)mm Vacuum tank length~ 2500mm Expected lifetime # pulses

Radial septum position 1/2 FT beam at entrance of septum Ion beam at exit of septum Septum blade position at grazing incidence with orbiting FT beam

L physical = 3000 mm, downstream in the ‘shade’ of MSI (~ 40 mm septum thickness). Radial position blade incidence with orbiting FT beam : – 48 mm upstream, 43 mm downstream mrad) Radial position blade incidence with orbiting ion beam (since closer to orbiting beam than FT): – 72 mm upstream, 51 mm downstream mrad) Proposed positioning range (septum downstream): Radial: 42 – 52 mm Angular: 0 – 8 mrad No retracting foreseen Radial septum position 2/2

outline 1.Septum requirements 2.Retained septum concept 3.Mechanical concept and integration 4.Magnet control electronics 5.Power supply 6.Planning and resource requirements

Mechanical Concept 2 magnets, 1 common vacuum vessel 1 feedthrough per magnet Outside vacuum remote displacement system Impedance screen 2 VPI’s (tbc.) 2 transformers close to tank.

Design and integration Bruno Mechanical design Overall footprint Integration into SPS Impedance? Downstream Cross-Section Upstream Cross-Section Top Cross-Section

Possible integration

Cooling Magnet needs water cooling: ΔP = 12 bar P in max. = 15 bar Flow: Q ≈ 10 l/min. Auxiliary pump may be required in tunnel to keep pressure within range magnet operating range.

outline 1.Septum requirements 2.Retained septum concept 3.Mechanical concept and integration 4.Magnet control electronics 5.Power supply 6.Planning and resource requirements

Controls needs Dead beat control system by switching on/off 48V AC motors Local control with Touch Panel, remote control through FESA Siemens S7-300 F-CPU system with SIMOCODE modules for motor management Fail-safe modules for human and machine protection Position measurement by potentiometers, precision 100 µm Voltage measurement by analogue input cards; this limits cable length to 200 m when shielded

outline 1.Septum requirements 2.Retained septum concept 3.Mechanical concept and integration 4.Magnet control electronics 5.Power supply 6.Planning and resource requirements

Powering Proposal is to use MegaDiscaP type converter that is a high power / fast pulsed current source. MegaDiscaP converters are used in AD since 2012 and will be used for BI.SMV (PSB injection) One power supply per coil is required to cope with total load resistance. Matching transformers with n=16 to be installed in the tunnel (1m 3 per transformer) close to the magnet. (estimated stripline length = 2m)

Maximum operating current30kA Flat-top duration (with current stabilization)500µs Current precision< 1000 p.p.m. Primary voltage2kV Transformer ratio16 Septum resistance (total)0.200mΩ converter output0.150Ω converter output820uH Estimated cable length250m Estimated stripline length2m Converter Parameters

Septum magnet current Septum Magnet Current MegaDiscaP Converter Still to be studied in detail: o DCCT current measurement installation o Matching transformer design

Outstanding  Leak field validation  Vacuum equipment requirements  Cooling system in the tunnel  Detailed integration study  Impact of radiation on system Integrated leak field

outline 1.Septum requirements 2.Retained septum concept 3.Mechanical concept and integration 4.Magnet control electronics 5.Power supply 6.Planning and resource requirements

Proposed strategy and planning For LIU-PSB BT.SMV magnets will be removed from the vacuum tanks for newly constructed septa. As from 2018, at least 3 magnets will be available, with 6 more after LS2. These magnets could be re-used to construct 1 MSI-V for installation in LS2 and spares to be build after LS2. 1 magnet installed + 1 operational spare

Resource requirements Material budgetkCHF Mechanical design, drawing office60 Vacuum equipment, incl. bake out system, ion pump, gauges 2 x 80 Vacuum vessel2 x 100 Mechanical support30 Remote displacement system mechanics2 x 50 Electrical connection, incl. feedthrough, stripline, under vacuum connection 2 x 50 Hydraulics, under vacuum, connections in tunnel 50 Remote displacement electronics plus bake- out electronics, incl. cabling and FSU support 120 Power supply, including cabling to tunnel and transformer 500 TOTAL1320 ManpowerMY Septum hardware0.8 Septum electronics0.5 Power supply1.0