Work Package Controls MACS Week June 2010 June 24th, 2010 Johannes Gutleber PR-100616-a-JGU, June 24th, 2010 J. Gutleber 1 R. Gutleber.

Slides:



Advertisements
Similar presentations
Ninth Lecture Hour 8:30 – 9:20 pm, Thursday, September 13
Advertisements

<<replace with Customer Logo>>
Information Systems Analysis and Design
WP CO Status and Progress December 8th, 2010 Johannes Gutleber PR a-JGU, December 8th, 2010 J. Gutleber 1 R. Gutleber.
ITIL: Service Transition
Sixth Hour Lecture 10:30 – 11:20 am, September 9 Framework for a Software Management Process – Artifacts of the Process (Part II, Chapter 6 of Royce’ book)
Chapter 9: Moving to Design
Effort in hours Duration Over Weeks Or Months Inception Launch Web Lifecycle Methodology Maintenance Phases Copyright Wonderlane Studios.
Project Management and Scheduling
MACS Architecture MACS Week June 24th, 2010 Johannes Gutleber PR b-JGU, June 24th, 2010 J. Gutleber 1 R. Gutleber.
Configuration Management Process and Environment MACS Review 1 February 5th, 2010 Roland Moser PR a-RMO, February 5 th, 2010 R. Moser 1 R. Gutleber.
Chapter 9 Elements of Systems Design
LCG Milestones for Deployment, Fabric, & Grid Technology Ian Bird LCG Deployment Area Manager PEB 3-Dec-2002.
RUP Fundamentals - Instructor Notes
Safety concept and scope for WP Controls Fabian Moser February 5, 2010.
Mantychore Oct 2010 WP 7 Andrew Mackarel. Agenda 1. Scope of the WP 2. Mm distribution 3. The WP plan 4. Objectives 5. Deliverables 6. Deadlines 7. Partners.
Rational Unified Process Fundamentals Module 4: Disciplines II.
Texas Integrated Energy Solutions. Development Team, Background, Objective, & Justification 2.
MD Digital Government Summit, June 26, Maryland Project Management Oversight & System Development Life Cycle (SDLC) Robert Krauss MD Digital Government.
WP CO Column Status and Progress October 7th, 2010 Johannes Gutleber PR a-JGU, October 7th, 2010 J. Gutleber 1 R. Gutleber.
Cosylab/EBG Organization of common work Joze Dedic … on behalf of CSL MA team the best people make cosylab.
PR a-JGU, October 3rd, 2011 J. Gutleber 1 WP CO Progress and Status Q2-Q October 3rd, 2011 Johannes Gutleber.
ISM 5316 Week 3 Learning Objectives You should be able to: u Define and list issues and steps in Project Integration u List and describe the components.
OOI CI LCA REVIEW August 2010 Ocean Observatories Initiative OOI Cyberinfrastructure Architecture Overview Michael Meisinger Life Cycle Architecture Review.
ProShell Procedure Framework Status MedAustron Control System Week 3 December 8 th, 2010 Roland Moser PR a-RMO, December 8 th, 2010 Roland Moser.
ProShell Procedure Framework Status MedAustron Control System Week 1 March 28 th, 2011 Roland Moser PR a-RMO, March 28th, 2011 Roland Moser 1 R.
Project Life Cycle.
Beam Interlock System PR b-CTM, October 7th, 2010 Cesar Torcato de Matos.
FAIR Accelerator Controls Strategy
HLRF DRAFT Global Design Effort 1 Defining EDR* Work Packages [Engineering Design Report] Ray Larsen SLAC ILC Division for HLRF Team DRAFT April.
Fifth Lecture Hour 9:30 – 10:20 am, September 9, 2001 Framework for a Software Management Process – Life Cycle Phases (Part II, Chapter 5 of Royce’ book)
The Virtual Accelerator Allocator Status PR a-CTM, December 8 th, 2010 Cesar Torcato de Matos 1 R. Gutleber.
Work Package Controls Inception Phase Review February 5th, 2010 Johannes Gutleber PR a-JGU, February 5th, 2010 J. Gutleber 1 R. Gutleber.
9 Systems Analysis and Design in a Changing World, Fourth Edition.
9 Systems Analysis and Design in a Changing World, Fourth Edition.
1 1. Some recent views ( ) 2 Linac tunnel
Requirements Management with Use Cases Module 10: Requirements Across the Product Lifecycle Requirements Management with Use Cases Module 10: Requirements.
PR a-JGU, October 9th, 2011 J. Gutleber 1 MedAustron PXI Systems at CERN Johannes Gutleber Roland Moser.
NCSX Systems Engineering Management Plan Peer Review Bob Simmons May 15, 2003.
Software Project Management (SEWPZG622) BITS-WIPRO Collaborative Programme: MS in Software Engineering SECOND SEMESTER /1/ "The content of this.
Overview of RUP Lunch and Learn. Overview of RUP © 2008 Cardinal Solutions Group 2 Welcome  Introductions  What is your experience with RUP  What is.
1 The ILC Control Work Packages. ILC Control System Work Packages GDE Oct Who We Are Collaboration loosely formed at Snowmass which included SLAC,
Injector RF and Synchrotron RF Present Status, Activities, Plans PP a-GKO_MACS_RfStatus G. Kotzian WP RF - Present Status 1.
ProShell Procedure Framework Status MedAustron Control System Week 2 October 7 th, 2010 Roland Moser PR a-RMO, October 7 th, 2010 Roland Moser 1.
State of Georgia Release Management Training
Advances In Software Inspection
Tobias Stadlbauer Special Magnets MedAustron 7-8 October 2010 Special Magnets Controls Status and Plans IntroductionPower SupplySlow ControlsAOB.
SwCDR (Peer) Review 1 UCB MAVEN Particles and Fields Flight Software Critical Design Review Peter R. Harvey.
ProShell Procedure Framework Status MedAustron Control System Week 3 October 3 rd, 2011 Roland Moser PR a-RMO, October 3rd, 2011 Roland Moser 1.
Linac2 and Linac3 D. Küchler for the linac team. Planning first preparative meeting for the start-up of Linac2 in June 2013 –this early kick-off useful.
Beam Interlock System Technology Evaluation and Design MACS Week 1, 2011 Hannes Pavetits 1 R. Gutleber PR a-HPA, March 28 th, 2011 H. Pavetits.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Electrical Engineering for NSS - Status and Planning- Thomas Gahl Electrical Engineering Group Leader February 26, 2014.
Collaborating for Quality Quality Assurance (QA) & Quality Control (QC) in the Accelerator Project (ACCSYS) Matthew Conlon ACCSYS QA/QC
Online Software November 10, 2009 Infrastructure Overview Luciano Orsini, Roland Moser Invited Talk at SuperB ETD-Online Status Review.
Marco Cattaneo, 3-June Event Reconstruction for LHCb  What is the scope of the project?  What are the goals (short+medium term)?  How do we organise.
9 Systems Analysis and Design in a Changing World, Fifth Edition.
Tobias Stadlbauer, Tony Fowler Special Magnets MedAustron 28 June 2011 Special Magnets Controls Status StatusIntroductionDetailsStatusAOBComponents.
> Blueprint Executive Summary >. Presentation Purpose; This Executive Summary captures the key details and outputs which merit stakeholder alignment to.
Collaborating for Quality through the Project Quality Plan Matthew Conlon ESS ACCSYS QA/QC Quality Learning & Planning.
Project Management PTM721S
Process 4 Hours.
ITIL: Service Transition
PERSONAL SAFETY INTERLOCKS External EHS Expert Panel Workshop
The ILC Control Work Packages
Session II: System authority for ERTMS 4RP Trackside approval
Object Oriented Analysis and Design
Rational Unified Process
PSS verification and validation
ESHAC #8 Safety Readiness Review Thomas Hansson, ESH
Presentation transcript:

Work Package Controls MACS Week June 2010 June 24th, 2010 Johannes Gutleber PR a-JGU, June 24th, 2010 J. Gutleber 1 R. Gutleber

STATUS REPORT PR a-JGU, June 24th, 2010 J. Gutleber 2

Contents What has happened since Feb 5, 2010 (4 months)? Where do we stand with respect to the planning? What are our current activities? Where are we heading for the next 6 months (Dec. 2010)? PR a-JGU, June 24th, 2010 J. Gutleber 3

Core Team Composition Johannes Gutleber – WP leader Roland Moser – Junior partner Markus Marchhart – Automation technology engineer Angela Brett – Software engineer Cesar Torcato de Matos – Embedded systems engineer Franz-Michael Coreth – IT coordinator (50%) Michael Thonke – System administrator (since June) Fabian Moser – doctoral student, 20% beam verification analyst PR a-JGU, February 5th, 2010 J. Gutleber 4

Procurement Framework Agreement with Cosylab As of April 2010 team of up to 5 FTE for requirements, design, software and hardware developments CNAO Repository Management System (RMS) As of June 18, source code, user documentation of software “AS IS” Software not in use yet IBM Global Technology Services IT infrastructure architecture As of June 11, common project until mid December to elaborate the requirements and the architecture of the overall IT infrastructure. Output are “ready for tendering” documents Includes processes, procedures, organization, hardware and software PR a-JGU, June 24th, 2010 J. Gutleber 5

Framework Agreement EU tendering procedure completed Framework Agreement with Cosylab in field of accelerator controls Provision of software and hardware development services “Leasing” of skilled personnel that in close cooperation with WP controls core team creates the system Includes requirements re-scoping and design Work according to ISO 9001 QA process Call-off-contract/Contract Work Order principle Payment of lump sum per CWO Work items and deliverables for time frames of about 6 months PR a-JGU, February 5th, 2010 J. Gutleber 6

First Experience Alignment of development processes completed Cosylab project team identified and assigned Current work items Main Timing System (MTS) Power Converter Controller (PCC) Optical link from PCC to power converter Labview real-time framework (FECOS) First CWO (4 months) completed Company works according to well-defined QA process Company helps in requirements finding (WHAT needs to be done) Company showed flexibility in adapting schedule PR a-JGU, June 24th, 2010 J. Gutleber 7

Status at Inception Phase Milestone Defined work package scope Agreement with other work packages on scope Cost and schedule estimated Project risk management process defined Major risks identified and acknowledged by top management Parameters from existing processes and designs identified Project environment defined Initial requirements defined Project plan defined Project plan aligned with top management Development process defined and accepted Medical device safety concept/scope completed PR a-JGU, June 24th, 2010 J. Gutleber 8

Achievements since Feb 2010 Architecture described (ES a-JGU) Main Timing System (MTS) requirements settled MTS technology chosen and design started Power Converter Controller (PCC) requirements settled PCC technology chosen and design started Optical link evaluation between PCC and PCO performed Labview-RT framework rapid prototyping started (FECOS) Requirements collected for source, conventional and special magnets slow controls Beam Interlock System requirements (initial) IT infrastructure requirements and architecture started PR a-JGU, June 24th, 2010 J. Gutleber 9

Interfaces with Subsystems Identification of controls contact for each WP Contact persons should act autonomously in requirements definition and report/consult their WP holders in case of technical/organizational doubts Progress made, but not all contacts yet defined/available Requirements document with each work package Capture controls requirements Capture requirements on interface with SCS/ACS Capture safety requirements PR a-JGU, June 24th, 2010 J. Gutleber 10

Interfaces With Subsystems (1/3) PCO (ES a-JGU, ES a-JGU, ES a-JGU) Perform slow-control Provide set points and set-point sequences to power converters Provide triggers to power converters Magnets (ES a-MMA) Read out temperature and flow status Send control commands to magnet positioning system (septa) Vacuum (ES a-MMA) Interface to vacuum local control system (LCS) LCS designed and implemented according to controls guidelines Beam Interception Devices (action needed) Command devices Record device status PR a-JGU, February 5th, 2010 J. Gutleber 11

Interfaces With Subsystems (2/3) Ion Sources (ES a-MMA in progress) Configure devices and command device parameters Change and record device status RFQ, IH structure and RFC (TBD next) Configure RFC local control system Change and record LCS states Provide main timing system events and triggers Beam Diagnostics and Instrumentation (TBD) Provide T4 programming framework and guidelines Configure T4 processing equipment Change and record T4 processing equipment states Provide main timing system events and triggers Provide Signal Acquisition and Distribution System (SADS) PR a-JGU, February 5th, 2010 J. Gutleber 12

Interfaces With Beam Delivery (3/3) Beam positioning devices (WP BDS requires definition) Configure devices and record states Provide set points in real-time Beam verification monitors (WP BDS requires definition) Acquire digital signals and transmit to BDCS Record operational conditions Beam activation/de-activation devices (action needed) Configure devices and record states Provide triggers to activate/de-active beam PR a-JGU, February 5th, 2010 J. Gutleber 13

Interfaces With External Systems Med. Software Systems (IS a-RTR, PM a-RTR) Interface to be elaborated in cooperation with MSS work package Mastership in clinical mode lies within PRVS PRVS controls patient positioning, gantry and MTE devices Building Automation System (TBD IT coordinator) Request uniform Authentication & Authorization solution Receive and report status Access Control/Safety Management System (TBD IT) Request uniform Authentication & Authorization solution Receive and report status Beam Interlock System (ES a-MMA, in progress) Safety system that is orthogonal to operational functions Covered by work-package PR a-JGU, February 5th, 2010 J. Gutleber 14

Entering Elaboration Phase Focus on requirements, architecture, design Prototype implementation and technology evaluation Prepare development setup PR a-JGU, February 5th, 2010 J. Gutleber 15

Preliminary Schedule PR a-JGU, February 5th, 2010 J. Gutleber RMS Proc. FW Navigator FECOS CM Environment PCO MTS RFC SRC RFQ/IH SADS BID BIS MAG VAC BDCS IT Adaptation Framework Procedures Op. Panels Production Installation PCC MACS Framework Ready for WPs to work with MACS Framework Ready for WPs to work with MACS Transition Release Ready for Commissioning MACS Transition Release Ready for Commissioning gn Survey Dev Adaptation Dev FED PCC Framework API Desi MACS Column GUI-SCADA-Proc. FW-T4 MACS Column GUI-SCADA-Proc. FW-T4

Current Activities Finalize Requirements (MTS, PCC, FED) Main Timing System (MTS) design Power Converter Controls (PCC) design Front End Control Operating System (FECOS) design Framework for Labview real-time used for all developments Integration of FECOS with PVSS via OPC and DIM GUIs for FECOS and PCC Integration of PVSS with NI Measurement Studio Simulator components Procedure framework (ProShell) design started Used to script control procedures for operation and machine development PR a-JGU, June 24th, 2010 J. Gutleber 17

Goals for December 2010 Complete architecture and implementing first components Complete and MTS design and demo core functionality Complete PCC design and demo core functionality Make PCO FED ready for production Elaborate ProShell design and API skeleton Demonstrate use of RMS, database filler, PVSS filler Have development infrastructure (HW, SW) operational PR a-JGU, June 24th, 2010 J. Gutleber 18 All goals are part of the MACS Column

MACS COLUMN 2010 PR a-JGU, January 20 th, 2010 J. Gutleber 19

MACS Column Functional vertical cut through the control system architecture for confirming technology choices Refining the design Improving project cost/time estimate Providing users with a working infrastructure skeleton To be replicated for each subsystem Leads to a scalable system In terms of performance In terms of management PR a-JGU, January 20 th, 2010 J. Gutleber 20 Presentation tier (1) Processing tier (2) Equipment tier (3) Frontend tier (4)

Individual Columns PR a-JGU, January 20 th, 2010 J. Gutleber 21 VAC MAG SRC PCO RF BDI BDS

Unified at Later Stage PR a-JGU, January 20 th, 2010 J. Gutleber 22 Uniform Presentation Layer Uniform SCADA layer and use of common services VAC MAG SRC PCO RF BDI BDS

MACS Column Technologies PR a-JGU, January 20 th, 2010 J. Gutleber 23 DIM HTTP Windows, NI Measurement Studio GUIs and PVSS Panel Navigator SCADA and ProShell skeleton Main Timing System demo Control and Data Exchange FECOS Power Converter Controller Timing Network Power Converter optical link for waveforms Optical link to transmit setpoint sequences and acquire measurements from power converter FED

Column Time Frame 2010 PR a-JGU, January 20 th, 2010 J. Gutleber 24 JANFEBMARAPRMAYJUNJULAUGSEPOCTNOVDEC Framework Agreement T4 framework def. PCO Interface PC Interface Def./Impl. MTS Definition MTS development PCC def. PCC development Column Demo 1 SW engineer Contractor Production FECOS development Repo Sw. Adoption Repo Sw. Package 1 Power Converter Interface Recommendation Tech. Eval. Beam Interlock System Specification and Development 1 engineer WP JP Identify requirements Postponed PVSS/C#, environment, testing Procedure Fw Definition RMS not available Skeleton Development Postponed

SUMMARY AND OUTLOOK PR a-JGU, February 5th, 2010 J. Gutleber 25

Summary Requirements and design work has well progressed Planning requires adaptation Work with contractor Requirements needed to be reduced and clarified (re-scoping) Followup of deliverables (geographical separation) Change in power converter control strategy Elaboration of multiple options and support in decision making process Inhouse software development New team members need time to adapt to project goals Taking responsibilities and autonomous work needs to be fostered PR a-JGU, June 24th, 2010 J. Gutleber 26

Outlook MACS column remains on track (scope and deadline) Delivery of production grade software in time of originally planned WP CO schedule Team members should act more independent from now on Ensure that goals beyond 2010 are clear to everyone PR a-JGU, June 24th, 2010 J. Gutleber 27