Optimizing Your Configuration of MSP with CA PPM

Slides:



Advertisements
Similar presentations
Microsoft Project Tutorial for Chapters 6 & 7
Advertisements

CC SQL Utilities.
Integrating MSP with Clarity
Polycom Quotes on Demand Tool Partner User Guide Version 1.1
6 th Annual Focus Users’ Conference 6 th Annual Focus Users’ Conference Understanding the School Set Up Menu Presented by: Josh Mostyn Presented by: Josh.
McGraw-Hill/Irwin © The McGraw-Hill Companies, All Rights Reserved Creating Gantt Charts With Microsoft Project Technology Plug-In T12.
Building Your Project Work Plan in March 2, 2007 HP Project & Portfolio Management by Dan Gallagher See NOTES page for Presentation Discussion, Tips &
| | Tel: | | Computer Training & Personal Development Microsoft Office Project 2003 Intermediate.
TFACTS Private Provider Financial/Invoicing Overview 1.
Payment History Wizard June 20, Payment History Wizard  Payment history can be entered in ACT 7 for prior years by using the Addback wizard. 
Project Plan Optimization Lesson 13. Skills Matrix SkillsMatrix Skill Make time and date adjustments Adjust fiscal year settings within Microsoft Project.
Clarity Educational Community Resource Management Overview Presenters: Jerry Dolak and Karl Lockwood.
1 of 4 This document is for informational purposes only. MICROSOFT MAKES NO WARRANTIES, EXPRESS OR IMPLIED, IN THIS DOCUMENT. © 2007 Microsoft Corporation.
Microsoft Windows Vista Chapter 6 Customizing Your Computer Using the Control Panel.
USC’s Internet-based Time and Attendance Management System.
Projmgmt-1/23 DePaul University Tracking the Progress of Your Project In MicroSoft Project Instructor: David A. Lash.
We are partners in learning.. Note: Office 365 works best in Internet Explorer V 9 or above. Some features do not work in PWCS’s Chrome Browser or in.
Microsoft Project Presentation By Corey Johnson 10/11/00.
Copyright © Software Process Group 1 Software Process Group Microsoft Project Tutorial Steve Meyers
How to Get The Most Out of Outlook 2003 Michele Schwartzman Division of Customer Support Summer 2006.
Office 2003 Advanced Concepts and Techniques M i c r o s o f t Outlook Project 2 Scheduling Management and Instant Messaging Using Outlook.
Working with SharePoint Document Libraries. What are document libraries? Document libraries are collections of files that you can share with team members.
Advanced Tables Lesson 9. Objectives Creating a Custom Table When a table template doesn’t suit your needs, you can create a custom table in Design view.
Teacher Access Center Gradebook
Refining Your Project Plan Lesson 4. Skills Matrix SkillsMatrix Skill Apply a task calendar to an individual task Change task typesChange scheduling formula.
Panorama High School E.G.P./ Training to Put Students’ Grades on the Website Wednesday, September 29,
September 5, 2015 Office Setup. Lesson Overview: Office Setup  In this lesson we will cover:  Adding new offices to COM  Individual office setup 
Working with a Database
Overview of Reading-Program Data Tools in the Member Center
Air Quality System Precision and Accuracy Data Transaction Generator (AQSP&A) Training Session.
Smart Data OnLine Training
So – You want to learn how to put an article onto the state website. (Note: If you have not done so, you will need to review the web training provided.
Moodle (Course Management Systems). Assignments 1 Assignments are a refreshingly simple method for collecting student work. They are a simple and flexible.
Copyright © 2007, Oracle. All rights reserved. Managing Concurrent Requests.
Excel Connector for JIRA Installation and functional presentation.
1 OPOL Training (OrderPro Online) Prepared by Christina Van Metre Independent Educational Consultant CTO, Business Development Team © Training Version.
1. Chapter 25 Protecting and Preparing Documents.
Office 2003 Advanced Concepts and Techniques M i c r o s o f t Access Project 6 Switchboards, PivotTables, and PivotCharts.
Microsoft Project 2010 ® Tutorial 6: Sharing Project Information with Other People & Applications.
Training Guide for Inzalo SOP Users. This guide has been prepared to demonstrate the use of the Inzalo Intranet based SOP applications. The scope of this.
Advanced Project Plan Tracking Lesson 15. Skills Matrix SkillsMatrix Skill Record actual start, finish, and duration values of tasks Enter actual start.
Diagnostic Pathfinder for Instructors. Diagnostic Pathfinder Local File vs. Database Normal operations Expert operations Admin operations.
Microsoft Project – Tutorial 4 Leveling Overallocations In some cases, a resource could be assigned more work in a given time period than it has working.
Microsoft Access 2010 Chapter 10 Administering a Database System.
The Next Generation. Parent Access Grade History and Attendance.
Rev.04/2015© 2015 PLEASE NOTE: The Application Review Module (ARM) is a system that is designed as a shared service and is maintained by the Grants Centers.
HP Project & Portfolio Management Entering Actual Hours for Project work July 11, 2007 CIMpleBS.com/HP-PPM/Training-Time Sheets.pps By Dan Gallagher See.
PPM Educational Community (half day) Building Solutions with Open Workbench.
1 / 61 Using the Customer Support Web Site © 2006, Universal Tax Systems, Inc. All Rights Reserved. Customer Support Site Objectives –In this chapter you.
Ceridian Time Solutions Hourly/Non-Exempt & (Non- Contracted) Per Diems Key Entry.
Information Security 493. Lab # 4 (Routing table & firewalls) Routing tables is an electronic table (file) or database type object that is stored in a.
Hatrak Scheduler UsOn Line Demo HATRAK SCHEDLER.
Ceridian Time Solutions Supervisor. IMPORTANT If you are not the manager of an employee but have been assigned the task of approving time for that employee,
Staff Module and Summary of Changes 1. Icon Changes: Page 3 Signing In and Password/Pin Changes: Page 4 Logging Out: Page 8 Staff Module Changes: Page.
Project Plan Tracking – Fundamentals Lesson 8. Skills Matrix SkillsMatrix Skill Establish a project baseline Track a project as scheduled.
2007 TAX YEARERO TRAINING - MODULE 61 ERO (Transmitter) Training Module 6 Federal and State Installation and Updates.
Project Setup and Execution For PMPlan Enterprise Presented by AlNik Solutions Copyright ©
Microsoft Project Tutorial for CSCI 577 Fall 2006 Jesal Bhuta
Microsoft Office 2013 Try It! Chapter 4 Storing Data in Access.
Microsoft Project 2010 ® Tutorial 4: Assigning Resources and Costs.
Microsoft Project 2010 ® Tutorial 5: Tracking Progress and Closing the Project.
SNG via Webinar. Where’s Webinar??  Double click Aflac 2000 folder  Highlight “SNGWebCommunicator”  Right Click and “Send To - Desktop”
Active-HDL Server Farm Course 11. All materials updated on: September 30, 2004 Outline 1.Introduction 2.Advantages 3.Requirements 4.Installation 5.Architecture.
Step 1 Lead Notifications Dear Partner, New leads have been assigned to your organization based on customer preference and are available for you.
Should you use the Microsoft Project CA PPM Connector
NetApp Online Ordering User Tutorial
Expense Report Training
SSI Toolbox Status Workbook Overview
Expense Report Training
Administrator’s Manual
Presentation transcript:

Optimizing Your Configuration of MSP with CA PPM Presented by: Lisa Olsen

Agenda Installing the CA PPM Microsoft Project Interface What’s New? MSP Option Setup Opening the Project Schedule in MSP Improving Performance Customizing MSP Views and Making them Global Resource Availability vs. Resource Calendar Allocation, Max Units and Assignment Units Understanding Task Types Task Constraints Why Task Dates Change Maintaining and Controlling the Project Schedule MSP Prior Start, Prior Finish and Open for Time Entry Fields Saving the Project Schedule to CA PPM and Working Off-line

Overview CA PPM is a centralized project, resource, and portfolio management tool that can help manage, schedule, track, and report on projects When Microsoft Project is integrated with CA PPM, project managers are no longer working in a stand-alone MSP environment Consistent processes and accurate data are essential in providing accurate reporting and actionable metrics

CA PPM Schedule Connect CA PPM Schedule Connect provides a full bi-directional connection between CA PPM and Microsoft Project Whether you’re working directly in CA PPM or opened the project schedule from CA PPM to MSP, you’re always working with the most up-to-date information The Schedule Connect interface must be downloaded and installed by each user

Installing the CA PPM Microsoft Project Interface

MSP Settings in CA PPM CA PPM: Administration > Project Management > Settings Default Load Pattern: This should be set to “Uniform” which will map to the MSP “Work Contour” field. Only Export Current Baselines When Opening Investments in a Scheduler: This should be checked to improve performance. Round Allocation to Nearest %: This should be set to “0” to prevent rounding issues when data is passed between CA PPM and MSP

MSP Settings in CA PPM Scheduler: This must be set to “Microsoft Project” % Complete Calculation Method: This should be set to “Manual” if MSP is being used with CA PPM or if you are using an external job to calculate % Complete. The % Complete field appears on the task properties page Track Mode: This should be set to “Clarity” if CA PPM Timesheets are being used to record time CA PPM: Project > Properties > Settings

Installation Prerequisites – MSP 2010 & 2013 The following third-party software must be installed on the workstation: MSP 2010 or MSP 2013 Microsoft .NET Framework 4 http://www.microsoft.com/downloads/en/details.aspx?FamilyID=0a391abd-25c1-4fc0-919f-b21f31ab88b7&displaylang=en Microsoft Visual Studio 2010 Tools for Office Runtime http://www.microsoft.com/en-us/download/details.aspx?id=44074 Pre - CA PPM Release 13.3: Java Runtime version (JRE) needs to be installed For MSP 64-bit installs - 64-bit JRE version needs to be installed For MSP 32-bit installs – 32-bit JRE version needs to be installed You CAN have both 64-bit and 32-bit JRE versions installed on the same machine CA PPM Release 13.3 & higher: No need to install Java

Installation Browser Settings – MSP 2010 & 2013 If using Microsoft Internet Explorer, verify that the “Do not save encrypted pages to disk” is unchecked From Internet Explorer, go to the Tools menu (gear icon towards top right of screen Click Internet Options and then the Advanced tab Under the Security section, uncheck “Do not save encrypted pages to disk” and click the OK button

Installation MSP Trust Center Level – MSP 2010 & 2013 Set Trust Center Level in MSP - Enable macros Open Microsoft Project Go to File > Options > Trust Center and then click “Trust Center Settings” Click Add-ins. Clear the “require application add-ins to be signed by trusted publisher” option Click Macro Settings and select the “enable all macros” option Click “OK” and then click “OK” again to close the option boxes Note: This action can be reverted following the installation

Installation – MSP 2010 & 2013 Install the Microsoft Project Interface: From the CA PPM Home Menu, under Personal, click on Account Settings > Software Downloads and then click the download link for the Microsoft Project Interface that matches your version of Microsoft Project Microsoft Project Interface (x86) – 32 bit Microsoft Project Interface (x64) – 64 bit Follow the instructions from the wizard and then select an interface version when prompted: Microsoft Project Interface – Provides the current, updated version with the new XML driver Microsoft Project Interface Legacy – Provides the legacy version

Potential Installation Issues If MSP does not open when trying to open a project schedule from CA PPM: Make sure Pop-Up Blocker is not on Turn off Active X Filtering – an “X” will appear on the IE tab

What’s New?

CA PPM 14.2: New MSP Interface -> New Driver Before CA PPM Release 14.1, there was one MSP Interface driver which was COM-based In CA PPM Release 14.1, a new XML-based driver option was introduced During the installation process, you can choose to install the Legacy “COM-based” driver or the New “XML-based” driver Both options are available for 32-bit and 64-bit environments

Noteworthy Differences with the NEW XML-based Driver Resource Pools are no longer available for Master Projects; all Resources will be on the Master Resource Sheet If a Task is created in CA PPM and NOT pinned through a dependency and does NOT start on the Project Start Date, MSP will NOT automatically put a Constraint on the Task “Number1” and “Number2” fields are no longer mapped to the “Proposed ETC” and “Pending Actuals” Fields Custom Views are no longer saved in the MPP file and should be saved in the Global.mpt file “Save As” is not available on EXISTING CA PPM Projects

CA PPM: New in 13.2 and 13.3 CA PPM 13.2: CA PPM 13.3: Projects with a Calculation Mode set to “off” can be opened from CA PPM to MSP without the tasks automatically re-calculating and updating dependent task dates CA PPM 13.3: Java Runtime is included in the download and is copied to the MSP Interface Installation directory on the workstation’s hard drive, eliminating all of the issues related to the JRE version incompatibility Resource Leveling in MSP is now supported

If you revise Duration… If you revise Duration… What’s New with - MSP 2010 & 2013 MSP 2010 MSP 2007 and prior How may this affect me? Task A is a “Fixed Unit” task and has one resource assigned at 100% for one day (8 hours) In previous versions of MSP, if the resource charged 10 hours to that task, the Assignment Units would change from 100% to 120% If you then changed the Work Hours or Duration on that task, it would recalculate the task based on the resource being assigned at 120% Now, with MSP 2010, the 120% is saved in the Peak Units field, so if the Duration or Work Hours are changed, the assignment will still be based on the original 100%   Task Type is: If you revise Units… If you revise Work… If you revise Duration… Fixed Units Duration changes Duration changes Work Fixed Work Peak Fixed Duration Changes   Task Type If you revise Units… If you revise Work… If you revise Duration… Fixed Units Duration changes Duration changes Work Fixed Work Assignment Units Fixed Duration Changes

MSP Option Setup

MSP 2010 and MSP 2013 Option Settings From the MSP Tools menu, select File > Options and refer to the following guidelines so MSP and CA PPM will effectively work together General Tab: Date Format: The storage of dates and timestamps are not consistent between tables in CA PPM. Some dates, like Task Start and Finish Dates, are recorded with specific timestamps. Some dates are recorded as the correct date with a timestamp of midnight. Some dates are recorded as a “plus 1” date, which means that the date stored in the table is one day later with a midnight timestamp. To avoid discrepancies, it is NOT recommended to use a date format with a timestamp.

MSP 2010 and MSP 2013 Option Settings Calendar Options: The “Week starts on” and “Fiscal year starts in” calendar fields should match your calendar settings in CA PPM. The other MSP calendar fields will map through the integration. Scheduling Options for this Project: This should be set to “All New Projects” in order for the settings to be effective for all new projects and not just the one that is open. New Tasks Created: Automatic calculation is the preferred setting, but it is not required. If you select Manual Calculation, you must manually calculate the project before saving it to CA PPM. Duration is entered in: Duration should be tracked in days since this is the lowest level that CA PPM is able to track. Schedule Tab:

MSP 2010 and MSP 2013 Option Settings, cont. Scroll Down on Schedule Tab….. Calculation Options for this Project: This should be set to “All New Projects” in order for the settings to be effective for all new projects and not just the one that is open. Updating Task status updates Resource Status: If checked, resource actuals, remaining work (ETC), and costs are automatically updated when percent complete, actual duration, or remaining duration is updated. This open should ONLY be checked when Actual hours are NOT being tracked through CA PPM timesheets. Inserted Projects are calculated like Summary Tasks: If checked, on a master project, project will display a single critical path for the Master Project and all of its sub-projects. Schedule Alerts Options: This should be set to “All New Projects” in order for the settings to be effective for all new projects and not just the one that is open. Calculate Project after each Edit: If “On” is selected, the project will automatically calculate after each edit. If set to “Off”, task scheduling that occurs as a result of task dependencies (predecessors) will be turned off within MSP as well as when a project schedule is re-opened from CA PPM to MSP.

MSP 2010 and MSP 2013 Option Settings, cont. Save Tab: Save Files in this Format: This option can be changed if you want to save the MPP file in a format that’s compatible with an older version of MSP. Default File Location: When saving the MPP file outside of CA PPM, you can change the default location where the file gets saved.

MSP 2010 and MSP 2013 Option Settings, cont. Allow Cell Drag and Drop: If checked, you can move cells by using the “drag and drop” functionality, moving the task ids with the task. Don’t use the “cut and paste” functionality to move tasks because MSP will change the task unique id which will affect the integration mapping. Automatically add new views, tables, filters, and groups to the global: (New in MSP 2010): If checked, any changes made to views, tables, filters and groups will automatically be available across your projects. In previous MSP versions, changes needed to be manually copied to the Global.mpt file through the Organizer. Advanced Tab:

MSP 2010 and MSP 2013 Option Settings, cont. Scroll Down on Advanced Tab… Show “Links between Projects” dialog box on open: This feature is incompatible with CA PPM external dependencies, and is ignored when selected.

Opening the Project Schedule in MSP

Opening the Project in MSP From CA PPM From MSP Choose either (Read-Write) or (Read- Only) from the Project > Properties or Tasks tab: The CA PPM “Scheduler Format” in Project > Properties needs to be set to “Microsoft Project.” Choose “Open” from the CA PPM Integration menu: You may be asked to login to CA PPM. Choose the project from the “Open from Clarity” selection box.

Opening the Project Schedule in MSP When opening a project schedule from CA PPM to MSP, an “.mpp” file is created on the local drive and then: If the project was previously saved from MSP, that last saved “.mpp” file from the CA PPM database is downloaded and will overwrite the “.mpp” file on the local drive The MSP schedule will be updated with any changes that were made in CA PPM since the “.mpp” file was last saved Actuals Posted from Timesheets Task Level Updates Project Team Updates Resource Assignment Updates

Improving Performance

Improving Performance How can you decrease the amount of time it takes to export a project schedule from CA PPM to MSP? Set the CA PPM default loading pattern to “Uniform” – which will map to a “Flat” work contour in MSP Select Only Export Current Baselines When Opening Investments in a Scheduler in CA PPM Administration > Project Management > Settings Remove unnecessary assignments Increase the memory on the workstation to at least 512 MB (ideally 1 GB)

Customizing MSP Views and Making them Global

MSP Organizer When customizing views in MSP by rearranging columns or adding and removing fields, the changes are only visible in the project you’re currently working on You can copy your customization to the Global Template so all the changes are available in future projects, as well as projects that were created in the past To create a global template, open an empty project or the project that has the customization directly from MSP MSP 2007 Tools menu > Organizer MSP 2010 File > Info > Organizer

MSP Organizer, cont. Once the changes are made, you can see the active project’s customizations on the right-side panel of the Organizer From the “Views” tab, highlight all of the views from the right-side panel and then click “<<Copy” Do the same for the “Tables” tab

MSP 2010 Organizer Note In Microsoft Project 2010, the organizer behaves a bit differently By default, new views are automatically saved to the global template file and are made available to future projects (as are new tables associated with the view). To change this setting, on the File tab, click Options, and then click Advanced. Find the setting in the Display section Changes to existing view elements are not automatically saved to the Global template with this setting. This only applies to NEW views, tables, filters and groups

Resource Availability vs. Resource Calendar

Base Calendars The CA PPM default Base Calendar is the “Standard” calendar If you have resources in different locations that have different daily availability hours, you can create additional Base Calendars Default shifts on the Standard Calendar represent 8 hours per day

Base Calendars, cont. To represent a 7 hour work day Create a new calendar and choose the Standard calendar as the Base Calendar Set the Shifts to represent the number of hours in the work day

Resource Calendar Select the correct Base Calendar for each resource from the Resource > Calendar page The Resource Availability on the Resource > Properties page will automatically update to reflect the working hours from the resource’s Base Calendar

Resource Availability Do Not change a Resource’s Availability from the Resource > Properties page; this field is calculated based on the resource’s base calendar If this is not done properly, you may see an invalid number in the Resource Availability field

Allocation, Max Units and Assignment Units

Allocation, Max Units & Assignment Units Allocation (CA PPM) – the expected amount of time that a resource is expected to work on the project. Max Units (MSP) – the maximum percentage of working time that a resource is available to work on project tasks. Assignment Units (MSP) – the percentage of working time that a resource is assigned to work on that one task.

Allocation – Based on Percent Enter the % Allocation on the Team > Resource > Properties page As of CA PPM Release 13.1, the Allocation % is “Average Allocation %”

Allocation – Based on Hours Enter the number of Allocated Hours by time period The % Allocation segments are calculated on the Properties page based on the Allocation Hours entered

Max Units Average Allocation % and Allocation Hours from CA PPM Team Page: MSP Resource Sheet – Max Units: The 36% comes from the Allocation % Segment that matches the current date In CA PPM, it’s displayed to the hundredths, but is rounded to a whole number in MSP

Assignment Units When Tasks are created and resources are assigned, the Assignment Units for each resource is defaulted from their Max Units The two tasks below were entered with 40 hours of work and then assigned to each resource Since Jerry’s Assignment Units is 100% on a 40 Work Hour task, the Task Duration was calculated to be 5 days Since Lisa’s Assignment Units is 36% on a 40 Work Hour task, the Task Duration was calculated to be 14 days Note: The Assignment Units for a resource on a task can be changed when assigning the resource to the task. This will not change the Max Units.

Back in CA PPM… Since MSP rounds Max Units to a whole number, the Allocation % Segments are rounded to a whole number after saving the schedule back to CA PPM Based on those new Allocation % Segments, the Allocation Hours get recalculated

Understanding Task Types

Task Types MSP uses the following scheduling formula when calculating tasks: Work = Duration x Assignment Units Each value of the formula corresponds to a Task Type: Fixed Work Fixed Duration Fixed Units Which task type should be used? It depends on the processes in the organization

Fixed Work If work hours are used to estimate how long deliverables will take on a project based on resource assignment All Fixed Work tasks are Effort Driven Example: Team Leads will look at project requirements and provide an estimate in hours for each project deliverable Project Managers will estimate how many hours each deliverable will take based on experience or a project sizing tool

Fixed Duration If Duration (number of days) is used to estimate how many hours deliverables will take to complete based on resource assignment Example: Team Leads will provide the estimated number of days or weeks that deliverables will take to complete Project Managers will estimate how many days each deliverable will take based on experience or a project sizing tool

Fixed Unit If resources are managed and allocated to projects based on a percentage of their time or if projects are estimated based on the number of resources needed in each role, then “Fixed Units” would work Example: “Resource A” is assigned to a project for 100% of their time to work on tasks. It’s the Resource Manager’s responsibility to make sure they are adequately utilized Projects are estimated and staffed with one Project Manager, two Business Analysts, four Software Engineers, etc.

Task Constraints

Task Constraints All “automatically” scheduled tasks will have an “As soon as possible” constraint If tasks are created in CA PPM or copied from a template and the Task Start Date is not the same as the Project Start Date, MSP will place a “Start No Earlier” constraint on the Task when the Project Schedule is first opened from CA PPM to MSP This applies to the Legacy Driver ONLY; no constraints will be applied using the new XML driver Constraint Types As Late As Possible Forces a task to start on a date in order for it to finish before the end of the project Finish No Earlier Than/Finish No Later Than Sets the completion of the task to fall no sooner or no later than the specified date Must Finish On/Must Start On Forces a task to Finish or Start on the specified date Start No Earlier Than/Start No Later Than Sets the start of the task to fall no sooner or later than the specified date

Why do Task Dates Change?

How Actuals Affect the Project Schedule When Actual Work hours are posted to projects via CA PPM Timesheets, tasks dates in Microsoft Project may change the next time the project schedule is opened in MSP Actuals posted to one task may affect the dates of another task if they are dependent on one another

Actuals – Same Number of Hours Resource submitted their timesheet with the same number of hours assigned Assigned Hours vs. Actual Hours: Results:   Thu 1/23 Fri 1/24 Mon 1/27 Tue 1/28 Wed 1/29 Thu 1/30 Assigned Hours 8 Hours Entered on Timesheet

Hours Entered on Timesheet Actuals – Fewer Hours Resource submitted their timesheet with FEWER hours than assigned Assigned Hours vs. Actual Hours: Results: Since only 4 of the 8 hours that were assigned were recorded, the duration increased by .5 days for both the Fixed Units and Fixed Work Task Types   Thu 1/23 Fri 1/24 Mon 1/27 Tue 1/28 Wed 1/29 Thu 1/30 Assigned Hours 8 Hours Entered on Timesheet 4

Actuals – Fewer Hours, cont. The Fixed Duration task didn’t change the duration, but distributed the additional 4 hours over the last two days so Work is now 10 hours for Tuesday and Wednesday

Hours Entered on Timesheet Actuals – More Hours Resource submitted their timesheet with MORE hours than assigned Assigned Hours vs. Actual Hours: Results: The Fixed Units and Fixed Work task Durations went back down to 5 days since the resource “caught” up   Thu 1/23 Fri 1/24 Mon 1/27 Tue 1/28 Wed 1/29 Thu 1/30 Assigned Hours 8 Hours Entered on Timesheet 4 12

Actuals – More Hours, cont. The Fixed Duration assigned hours for Wednesday went back down to 8 hours since the resource submitted additional hours the day before

Hours Entered on Timesheet Actuals – Skipped a Day Resource skipped the last day of assigned work and then entered fewer hours on the day after the task was supposed to finish Assigned Hours vs. Actual Hours: Results: Since zero hours were recorded on Wednesday, the task gets split Fixed Units and Fixed Work task types will calculate Duration without counting the days in between the split Fixed Duration tasks WILL count the days in the middle of the split   Thu 1/23 Fri 1/24 Mon 1/27 Tue 1/28 Wed 1/29 Thu 1/30 Fri 1/31 Assigned Hours 8 Hours Entered on Timesheet 4 12

Actuals – Skipped a Day, cont. The Task Finish Dates all changed to Friday, 1/31, to accommodate the extra 4 hours needed to complete the task

Maintaining and Controlling the Project Schedule

Maintaining the Project Schedule Once a resource charges time to a project and those hours are posted as Actuals, the Project Manager needs to frequently maintain the project schedule Step 1: Open the Project Schedule from CA PPM to MSP Step 2: Review new Actual Work Hours to ensure they look accurate Step 3: For Tasks that are Complete: Verify that the Remaining Work field is zero (0) If there are hours, enter zero (0), which will reduce the Work field so it matches the Actual Work field Enter “100%” in the “% Complete” field Mark the task as “Not Open for Time Entry”

Maintaining the Project Schedule, cont. Step 3 – For Tasks that are Complete, cont. To “Close” this Task: Work was planned to take 40 hours, but the task was completed with 16 hours: Right Way Enter “0” for Remaining Work Enter “100” for % Complete Wrong Way

Maintaining the Project Schedule, cont. Step 4: For Tasks that are still in progress: Adjust any Work hours that need to be increased Verify that all tasks have values in the Remaining Work field Reschedule any task with a “Finish Date” in the past Reschedule any task with a “Start Date” in the past that hasn’t started yet

Copying Tasks You CAN use copy/paste to create a New Task DO NOT use cut/paste to move a task in the project schedule This will change the unique ID on the task that is used by the CA PPM – MSP Integration

MSP Prior Start, Prior Finish and Open for Time Entry Fields

Prior Start and Prior Finish Fields One of the biggest complaints from Project Managers is that CA PPM changed their MSP task dates in their project schedule When many task dates change, it’s difficult for the PM to find the root cause By default, Task Start and Finish Dates are already mapped between CA PPM and MSP Those dates may change as Actuals are applied to the project schedule You can extend the mapping table with the following MSP fields to make it easier: Start10 Prior Start Finish10 Prior Finish

Prior Start and Prior Finish Fields, cont. The extended mapping should NOT be bi-directional; it should be on “Export from Clarity” only When a project schedule is exported from CA PPM to MSP, the Task Start and Finish Dates will be copied to both the MSP Start and Finish fields as well as the new Start10 and Finish10 fields The Actuals are then applied to the schedule which may cause the original Task Start and Finish Dates to change, but not the new Start10 and Finish10 fields

Prior Start and Prior Finish Fields, cont. The Project Manager is now able to compare the following fields to find the first task with a difference. Start >> Prior Start Finish >> Prior Finish You can then look at that task and any predecessors to see what Actuals were applied that caused the dates to change

Open for Time Entry Field You can extend the mapping table by adding the “Open for Time Entry” (Flag11) field so Project Managers can better control what tasks are open for time entry from MSP This should be a bidirectional mapping so the data flows from CA PPM to MSP and from MSP to CA PPM In CA PPM, the Open for Time Entry field defaults to “Yes” for new tasks and in MSP it defaults to “No” for new tasks

Saving the Project Schedule and Working Offline

Save to CA PPM To save a project schedule back to CA PPM that was opened from CA PPM to MSP, click on the “Save” button under the “CA Clarity PPM Integration” menu When the schedule has been saved back to CA PPM, you will see a “Project successfully Saved” message flash on the screen

“Save As” to CA PPM The “Save As” button should only be used to save the existing project schedule as a new project in CA PPM or if you want to copy the project schedule to another project in CA PPM, which is a great way to “copy” a CA PPM Project If using the new MSP XML-based Drive, the “Save As” option is NOT available when saving to an EXISTING CA PPM project

Save to Your Local Drive If you would like to work on the project schedule offline or disconnected from CA PPM, you can: Open the Project from CA PPM to MSP in Read/Write mode From the MSP file menu, click File > Save As and select a location on your local hard drive Exit out of MSP You can now work on the project schedule that was saved to your local drive CA PPM will maintain a lock on the project until it is successfully saved back to CA PPM When you’re ready to save it back to CA PPM, open the file and click on “Save” under the CA PPM Integration Toolbar. You may need to log back into CA PPM

Questions Phone Email Website We hope that you found this session informative and worthwhile. Our primary goal was to increase your understanding of the topic and CA PPM in general. There were many concepts covered during the session, if you would like to contact any presenter with questions, please reach out to us. Thank you for attending regoUniversity 2015! Phone 888.813.0444 Email info@regouniversity.com Website www.regouniversity.com