Coral-Team 2001 Winter Presentation Coral University of Hawaii School of Engineering ArchitectureGuido Zimmermann Marcel Schuler University of applied.

Slides:



Advertisements
Similar presentations
Pacific Team TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert.
Advertisements

Introduction to Lateral Force Resisting Systems
CORE DESIGN.
>ENTER< [PLS PUT ON SAFETY HELMETS BEFORE ENTERING THIS SITE.]
Chp12- Footings.
By : Prof.Dr.\Nabil Mahmoud
Loads and Load Paths "Architecture is inhabited sculpture."
` Coral-Team 2001 Spring Presentation Coral University of Hawaii School of Engineering ArchitectureGuido Zimmermann Marcel Schuler University of applied.
CE A434 – Timber Design Structural Behavior.
A dome is a structural element of architecture that resembles the hollow upper half of a sphere. Dome structures made of various materials have a long.
Carl Hubben – Structural Option Ae senior thesis Office Building-G EASTERN UNITED STATES.
Express Team University of New Mexico February 24, 2006.
Bay team’s Output Engineer Yang, Yao-Hung Construction Manager David Walthall Architect Cindy Chan.
Picture Lake Geneva, Switzerland Surrounded by the Alps 20°C mean temperature in summer Annual snow fall – 30in Site Context.
W a v e Mildred van der ZwanArchitect - TUDelft Valerie OuEngineer – Stanford Diego AvilesConstruction Manager - Stanford Daniel KwonApprentice.
Milton S. Hershey Medical Center Biomedical Research Building Joshua Zolko, Structural Option.
TeamMembers Architect: Angela Ribas UC Berkeley Engineer: Matthias Niebling Bauhaus-University Weimar, Germany Construction Manager: Kevin Coyne Stanford.
The University Sciences Building Northeast, USA Final Presentation Chris Dunlay Structural Option Dr. Boothby.
for Earthquake Resistance
High Rise Structural Systems
2001 Winter Presentation. Site Location Site View.
Mountain Ridge Project - winter presentation - AEC The making of Ridge University Engineering Building E ngineerMartha Del Campo, Stanford, CA A rchitectKatrin.
Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering.
Samuel M. P. Jannotti Structural April 14, 2008 American Eagle Outfitters Quantum III: South Side Works.
2001 Final Presentation. The Atlantic Team JARED Georgia Tech Construction Manager PETER Georgia Tech Construction Manager HANS Georgia Tech Owner KIM.
360 State Street New Haven  CT  Structural | Sabrina Duk | T. Boothby.
construction manager Kit Fleming engineer Peng Li architect Xiang Liu owner Hans Verheij Collaboration in Cyberspace E X P R E S S T E A M C.
AE SENIOR THESIS APRIL 14 th, 2014 CHRIS DUARTE – STRUCTURAL Dr. THOMAS BOOTHBY ORCHARD PLAZA.
Reading Structural Drawings
RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN.
Lucas Pettinati Rafael Monzon Andreas Dinopoulos architect structural engineer construction manager Berkeley Georgia Tech Strathclyde, UK Luciana Barroso.
All Hakuna Resort photos in courtesy of LMN Development LLC Young Jeon Structural Option Advisor: Heather Sustersic Hakuna Resort AE Senior Thesis 2015.
Frames and Walls Lateral Stability
R I V E R A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e.
Nick Szakelyhidi Structural Option Office Building Washington, DC Nick Szakelyhidi Structural Option.
Team Central Winter Presentationslide 1 of 65 Winter Presentation AEC Global Team Class 2002 Winter presentation Team Central.
GARY NEWMAN STRUCTURES OPTION ADVISOR: DR. HANAGAN SENIOR THESIS PRESENTATION SPRING 2008.
BRYAN DARRIN SENIOR THESIS PRESENTATION MILLENNIUM HALL DREXEL CAMPUS PHILADELPHIA, PA.
+ Sill and Floor Construction Vocabulary. + Anchor Bolt A threaded rod inserted in masonry construction to anchor the sill plate to the foundation.
SEAN BEVILLE STRUCTURAL OPTION ADVISOR: PROF. BOOTHBY APRIL 13, 2009 TEMECULA MEDICAL CENTER “STRUCTURAL SYSTEM OPTIMIZATION” THE DEPARTMENT OF ARCHITECTURAL.
Mildred van der ZwanArchitect - TUDelft Valerie OuEngineer – Stanford Diego AvilesConstruction Manager - Stanford Daniel KwonApprentice – Stanford Brooke.
Building Fun You will have 30 minutes to build the strongest structures you can with only the materials you are provided with. Explain to the class the.
Third Avenue NY, New York Michelle L. Mentzer Structural Option.
Howard County General Hospital Patient Tower Addition Columbia, MD Kelly M. Dooley Penn State Architectural Engineering Structural Option.
Jonathan Goodroad Structural Option 2005 Thesis Penn State AE Delaware State University Administration and Student Services Building.
Project Introduction  New high-tech classroom and lab facility  Area : 30,000sq.ft.  Function –To provide a home for innovative courses that take a.
Brad Oliver – Structural Option Advisor – Professor Memari.
Oklahoma University Children’s Medical Office Building Oklahoma City, Oklahoma AE Senior Thesis Final Report April 14, 2014 Jonathan Ebersole Structural.
Fordham Place Bronx, NY Aric Heffelfinger Structural Option Spring 2006.
Justin Purcell Structural Option Advisor: Dr. Hanagan.
Architect (K.U.) ADAM GUMOWSKI V p A c i e w Engineer (S.U.) JASON STONE C.M. (S.U.) BOB FARMAN Winter Quarter Presentation acific P niversity.
Park Potomac Office Building “E” Kyle Wagner l Structural Option AE Senior Thesis l Spring 2010 Faculty Consultant l Prof. Kevin Parfitt.
Eastern USA University Academic Center Alexander AltemoseIStructural Option.
FLAT SLAB Flat slab are also known as beamless slab, is a type of slab in which the flooring slab is directly supported on columns without the agency of.
Framed Structures Luisana Hernández.
Michael A. Troxell Structural Option Senior Thesis 2006 The College of Business Administration Northern Arizona University Flagstaff, Arizona.
Biobehavioral Health Building The Pennsylvania State University Daniel Bodde Structural Option Advisor – Heather Sustersic.
THE NORTHBROOK CORPORATE CENTER Redesign of the Lateral Load Resisting System.
The Mountain Ridge Team Mountain Ridge Team Final Presentation The Ridge University Engineering Building May 15, 1998 Architect: Humberto Cavallin Engineer:
Structural Systems Design for a Laramie Office Building
Structural Systems Design of the Lincoln Fire Department Headquarters Michelle Burback Structural Engineering Capstone and Senior Honors Project.
Building Construction
DESIGN OF AIRPORT TERMINAL AND CONTROL TOWER
TeamMembers Team members of the Team members of the Angela Ribas
Prepared by John R. Henry, P.E. Senior Staff Engineer
Lucas Pettinati Rafael Monzon Andreas Dinopoulos
The Mountain Ridge Team
Mississippi Riverbank Project (Final Presentation) May 14, 1999
North Shore at Canton The Pennsylvania State University
Masonry Bearing Walls.
Presentation transcript:

Coral-Team 2001 Winter Presentation Coral University of Hawaii School of Engineering ArchitectureGuido Zimmermann Marcel Schuler University of applied siences Aargau, Switzerland EngineeringSarah Diegnan Stanford University, California ConstuctionChunyan Ge Stanford University, California OwnerChad Green

Coral-Team 2001 Winter Presentation Design Considerations Analysis: ­ Vision of a future school system ­ Information technology ­ Going wireless ­ Think-Tank

Coral-Team 2001 Winter Presentation Site information  Climate (Temperature and precipitation ) 95 (temperature) 50 (temperature) 0.2 inch/day(Precipitation) Finish foundation before Nov. Material suit for humid and warm weather. Hawaii Honolulu

Coral-Team 2001 Winter Presentation Steel (Popular in Hawaii) Concrete (A common material in Hawaii, easy to get) Bamboo ( For small project, a nature material) Plexiglass $20/SF (Plexiglass Roof) Wood (Traditional material, cheap and easy to get) Construction Material

Coral-Team 2001 Winter Presentation Site plan

Coral-Team 2001 Winter Presentation Design Loads Dead Loads Concrete Slab-38 psf Steel Deck psf Int. Partition-10 psf Girders - 30 plf Floor Beams – 20 plf Columns – 50 plf Misc – 12 psf Exterior Clad –25 psf Live Load Corridors psf Offices - 50 psf Classrooms - 50 psf Auditorium - 50 psf Lateral Load Wind Design Speed 80 MPH V = 105 kips Earthquake – Zone 4 UBC ’97 Unconsolidated sand/silt Piers to bed rock Mat Design Dead Load = 100 psf Design Live Load = 70 psf Lateral Load = Earthquake 18” Mat Foundation

Coral-Team 2001 Winter Presentation New-Solution #1 Vision out of the site-context Maximum flexibility Exposure the center of the building

Coral-Team 2001 Winter Presentation New-Solution #1 Floor 1 Floor 2 Floor 3 Faculty School (Class. Lab) Auditorium Technical Restroom Circulation Organisation Model 3D-Model Ground plan Legend

Coral-Team 2001 Winter Presentation New-Solution #1 Structural Option 1 Gravity System – 5.5” cast-in-place Lateral System – SMRF perimeter with first floor concrete –Base Shear = 465 Kips W18X40W14X60 W14X48 Beams Girders Columns SMRF Vierendeel Truss Concrete Floor 1Floor 2, Connection

Coral-Team 2001 Winter Presentation New-Solution #1 Structural Option 1 Gravity Lateral Load Paths

Coral-Team 2001 Winter Presentation New-Solution #1 Structural Option 1 Structural System with Architecture

Coral-Team 2001 Winter Presentation New-Solution #1 Structural Option 2 Gravity System – 5.5” cast-in-place concrete slab Lateral system – EBF Core –Base Shear = 567 Kips W14X40 6”X6” t=3/8” W14X43 Beams Girders Columns EBF Vierendeel Truss Concrete W14X43 W14X30W18X Floor 1Floor 2, 3 Connection

Coral-Team 2001 Winter Presentation New-Solution #1 Structural Option 2 Gravity Lateral Load Path

Coral-Team 2001 Winter Presentation New-Solution #1 Structural Option 2 Structural System with Architecture

Coral-Team 2001 Winter Presentation New-Solution #1 Structural Option 1,2 38 Foot Cantilever Vierendeel Truss – unbraced frame

Coral-Team 2001 Winter Presentation Equipment Link-Belt HTC-8640 Hydraulic Truck Crane Selection Criteria: Maximum load; Maximum reach Costs; Site accessibility The Caterpillar Hydraulic Excavator

Coral-Team 2001 Winter Presentation  Plexiglass roof: Construction Method. The costs may go up $10,846.  Excavated cost for sunken auditorium (20,000 cy) at about $40,000.  Steel SMRF more labor-intensive than EBF New-Solution #1 Construction IssuesConstruction Issues NPV is the net present value Structure budgetTotal budget Solution 1 – Construction Issues

Coral-Team 2001 Winter Presentation Solution 1: Schedule New-Solution #1 Structural Option 2 Milestone1: finished the foundation (Nov.25) Building enclosed (Mar. 5) The end of the project (May. 20)

Coral-Team 2001 Winter Presentation New-Solution #2 Two cubes: school-/faculty-block Two vertical developments Classrooms oriented to the seaside

Coral-Team 2001 Winter Presentation New-Solution #2 Floor 1 Floor 2 Floor 3 Faculty School (Class. Lab) Auditorium Technical Restroom Circulation Organisation Model 3D-Model Ground plan Legend

Coral-Team 2001 Winter Presentation New-Solution #2 Structural Option1 Gravity System – 5.5” cast-in-place concrete Lateral System – Shear Wall Core and Special Concentrically Braced Frames Cantilever – 16’ 6”X6” t=3/8” W14X30 W18X50 W14X48 W18X86 Beams Girders Columns Concrete Cantilever Braces Shear Wall Floor 1Floor 2,3 12’ t=12” 14.5’ t=12”

Coral-Team 2001 Winter Presentation New-Solution #2 Structural Option1 GravityLateral Load Path

Coral-Team 2001 Winter Presentation New-Solution #2 Structural Option 1 Structural System with Architecture

Coral-Team 2001 Winter Presentation New-Solution #2 Structural Option 2 Knee BracesShear Walls Timber Knee Brace Tie Strap Timber Columns Anchor Strap Wall End Wall Roof Simple Structure

Coral-Team 2001 Winter Presentation New-Solution #2 Structural Option 2 Nail Couple Free body of Single sheet of Plywood Nail Couple Resist M M in BoardStud/Joist Shear Force Resisting Force

Coral-Team 2001 Winter Presentation Solution 2 – Construction Issues New-Solution #2 Structural Option1 Building is separated into 2 parts. The auditorium is sunken into the ground assuming that it has been excavated. Constructibility difficulties arise for sun protection. It is possible but increased costs.

Coral-Team 2001 Winter Presentation Solution 2 – Construction Issues New-Solution #2 Inflexible solar shading from aluminum lamella with different incline angles. Laminated coatings: vinyl films are used to provide nonmetallic color and long-lasting finish, and won’t aggregate heat in surrounding area.

Coral-Team 2001 Winter Presentation Solution 2 – Cost Estimate New-Solution #2 Structural Option1 Cost = $5.39M

Coral-Team 2001 Winter Presentation Solution 2 – Schedule New-Solution #2 Structural Option1 Milestone1: finished the foundation(Nov. 20) Building enclosed (Mar. 10) The end of the project (May 22)

Coral-Team 2001 Winter Presentation Solution 2 – Timber New-Solution #2 Structural Option2 AdvantageDisadvantage Material cheap and easy to get Overturning forces need deep foundation A traditional structure in Hawaii Decay and termite control Combine the advantage of steel and wood structure Separation of wood from Ground

Coral-Team 2001 Winter Presentation Re - Design #1 Minimum intervention Architectural division: new cube / existing building

Coral-Team 2001 Winter Presentation Re - Design #1 Floor 1 Floor 2 Floor 3 Public (Cafe, Gym) Faculty School (Class. Lab) Auditorium Technical Restroom Circulation Organisation Model 3D-Model Ground plan Legend

Coral-Team 2001 Winter Presentation Re-Design #1 Structural Option 1 Gravity System – 5.5” cast-in- place concrete Lateral System – SMRF/Braced Frame Two Separate buildings

Coral-Team 2001 Winter Presentation Re-Design #1 Structural Option 1 Bridge UBC Building Separation: All structures shall be separated from adjoining structures. Separation shall allow for the displacement D M. Adjacent buildings on the same property shall be separated by at least D MT where D MT = Ö (D M1 ) 2 + (D M2 ) 2 D M1 and D M2 and are the displacements of the adjacent buildings. When a structure adjoins a property line not common to the public way, that structure shall also be set back from the property line by at least the displacement D M of that structure. Hinge Connection Rest on top

Coral-Team 2001 Winter Presentation Re-Design #1 Structural Option 1 Glass Rigid Connection to New Building Expansion Joint in between Emseal (

Coral-Team 2001 Winter Presentation Re-Design #1 Structural Option 2 Gravity System – 5.5” cast-in- place concrete Lateral System – SMRF/Braced Frame Tie Buildings Together

Coral-Team 2001 Winter Presentation Re-Design #1 Structural Option 2 Bridge UBC Ties and continuity : All parts of a structure shall be interconnected and the connections shall be capable of transmitting the seismic force induced by the parts being connected. As a minimum, any smaller portion of the building shall be tied to the remainder of the building with elements having at least a strength to resist.5CaI times the weight of the smaller portion. A positive connection for resisting a horizontal force acting parallel to the member shall not be less than.5CaI times the dead plus live load. Elements must resist.5CaIW = 79.2 kips

Coral-Team 2001 Winter Presentation Re-Design #1 Structural Option 2 Glass  Mullions – Rigid Connections Braces – Simple Connections 

Coral-Team 2001 Winter Presentation Re-Design #1 Structural Option1&2 Structural System with Architecture

Coral-Team 2001 Winter Presentation Underpinning foundation in the new part of the building The excavation is open excavation. We use standard wellpoint system to dewater the area prior to excavation. Re-Design #1 Structural Option1&2 Construction Issues

Coral-Team 2001 Winter Presentation Underpinning foundation Re-Design #1 Structural Option1&2 Construction Issues

Coral-Team 2001 Winter Presentation Re - Design #2 Existing structure / new room organisation Natural exposure of rooms

Coral-Team 2001 Winter Presentation Re - Design #2 Floor 1 Floor 2 Floor 3 Public (Cafe, Gym) Faculty School (Class. Lab) Auditorium Technical Restroom Circulation Organisation Model 3D-Model Ground plan Legend

Coral-Team 2001 Winter Presentation Re-Design #2 Structural Option Gravity System – 5.5” cast-in-place concrete Lateral System – SMRF/Concentrically braced frames Cantilevered area with Café underneath – 9’ clear

Coral-Team 2001 Winter Presentation Re-Design #2 Structural Option 1 Cantilever Non- Composite Beam design – W44 X 230

Coral-Team 2001 Winter Presentation Re-Design #2 Structural Option 2 Simple Truss - still too large and does not meet architects standards

Coral-Team 2001 Winter Presentation Re-Design #2 Structural Option 3 Complex Truss - Carries the load like a bridge

Coral-Team 2001 Winter Presentation Re-Design #2 Structural System with Architecture

Coral-Team 2001 Winter Presentation Redesign #1 and #2 Cost Estimate Total Cost: 935,000 Total CF of building: 76,000cf Underpinning Total Cost: 381,000 Total CF of building: 15,162cf Big cantilever

Coral-Team 2001 Winter Presentation Sample Iteration Solution 2 E developed preliminary structure C Had a problem with cladding A Adjusted plans for sun protection E Had problem with columns A Decided to adjust wall instead of columns- Produced 3D model A Developed Plans A/E/C Discussed cladding problem in NetMeeting

Coral-Team 2001 Winter Presentation Decision Matrix SolutionProsCons SMRF Simple Design, symmetric Flexible, Central Circulation Quick to erect Cantilever No reference to the location Cost more than EBF EBF Core Lateral Load Path Flexible, Central Circulation More connection Details, Cantilever No reference to the location Cost less Shear Wall Core Utilizes Stair-well Arrangement of the rooms analogous to utilization Easy material accessibility Accidental Torsion Require additional formwork Timber Unexplored Arrangement of the rooms analogous to utilization Cost less when space is small Fear of the unknown Not good for big space, need consider life cost Architect EngineerConstruction Manager

Coral-Team 2001 Winter Presentation Looking Ahead and Behind Behind We all did a good job of informing each other when work would be done and then sticking to it MSN Messenger is a great tool Switzerland is 9 hours ahead of PST Ahead More communication with work done More interaction with Mentors/Owners A tighter work schedule 3D/4D models