Presentation is loading. Please wait.

Presentation is loading. Please wait.

The Mountain Ridge Team

Similar presentations


Presentation on theme: "The Mountain Ridge Team"— Presentation transcript:

1 The Mountain Ridge Team
Mountain Ridge Team Final Presentation The Ridge University Engineering Building May 15, 1998 Architect: Humberto Cavallin Engineer: Alec Zimmer Construction Manager: David Miller Owner Representative: Luciana Barroso The Mountain Ridge Team

2 The Mountain Ridge Team
Presentation Outline The Project Statement Early Proposed Concepts The Idea: Product, Evolution, and Process The Final Product Summary: The Team Process The Mountain Ridge Team

3 The Mountain Ridge Team
Project Definition Facility: A new 30,000sf academic building for The Ridge University School of Engineering with classrooms, labs, offices and auditorium Year: 2010 Location: Tahoe City, California The Mountain Ridge Team

4 Project Definition: Physical Constraints
Must use one of 2 existing footprints The Mountain Ridge Team

5 Project Definition: Physical Constraints
Must use one of 2 existing footprints 35’ height restriction Very heavy snow loads Moderate to high seismicity (Zone 3) Remote site with limited access The Mountain Ridge Team

6 Proposed Concept - Lshape1
The Mountain Ridge Team

7 Proposed Concept - Square1
The Mountain Ridge Team

8 Proposed Concept - Lshape2
The Mountain Ridge Team

9 Proposed Concept - Square2
The Mountain Ridge Team

10 Proposed Concept - Square2
The Mountain Ridge Team

11 The Mountain Ridge Team
The Iterative Process Square2 E C Lshape2 A O Square1 Lshape1 First Quarter Second Quarter The Mountain Ridge Team

12 The Mountain Ridge Team
Site Plan The Mountain Ridge Team

13 The Mountain Ridge Team
The Building 1 2 3 The Mountain Ridge Team

14 The Mountain Ridge Team
Activities Administrative Students Educational The Mountain Ridge Team

15 Architectural Evaluations - Floor 1
The Mountain Ridge Team

16 Architectural Evaluations - Floor 2
The Mountain Ridge Team

17 Architectural Evaluations - Floor 3
The Mountain Ridge Team

18 Architectural Evaluations - Section
The Mountain Ridge Team

19 Architectural Evaluations - Section
The Mountain Ridge Team

20 Engineering Loads- Gravity Loads
Dead Loads Including 25 psf floor & partitions 10 psf MEP equipment 83.5 psf for 6.5” slab and metal deck 109.6 psf total (205 psf is seismically effective) Live Loads Including 100 psf in halls & library 50 psf in offices 40 psf in classrooms The Mountain Ridge Team

21 Engineering Loads- Seismic and Snow Loads
223 psf Ground Snow 1.0 Importance Factor 0.6 Exposure D Factor Nominally Flat Roof 133 psf roof snow load (75% is seismically effective) Seismic Loads from 1994 UBC Z = 0.3 Seismic Zone 3 T = by Method A C = 2.75 for firm soil Rw = 8 compromise for this dual system Vbase = 608 kip Mot = 9426 k-ft The Mountain Ridge Team

22 Engineering Evaluations - Floor Details and Load Path
Composite steel deck - concrete slab Shallow beam sections Typical Sections: Beams sizes from W10x12 to W12x30, unshored construction All columns W12x40 to facilitate connections Shear connections only Cross Beam: W10x19, Typ. Ext. Girder: W10x22, Typ. Typ. Vertical Gravity Load Transfer Column: W12x40, Typ. 12” Shearwalls Resist All Lateral Loads Second Floor Beams - Plan View The Mountain Ridge Team

23 Engineering Evaluations - ETABS model
Verify period with modal analysis Evaluate deflections and interstory drift Verify load path assumptions Problems in model The Mountain Ridge Team

24 Engineering Evaluations - Cross Sections at Lines 1 and 3
Note typical sections and detail references The Mountain Ridge Team

25 Engineering Evaluations - Critical Connection Details
Third Floor Moment Frame Connection Detail The Mountain Ridge Team

26 Engineering Evaluations - Shear Wall-Beam Connection Details
The Mountain Ridge Team

27 Engineering Evaluations - Shear Wall Design
Resist all lateral loads, both seismic and wind Mot = k-ft per wall Vbase = 484 k No boundary zones No additional moment reinforcement Torsional effects are negligible The Mountain Ridge Team

28 Engineering Evaluations - MEP Assumptions
Steam heat and chilled water from central facility 15’ x15’ room provided on ground floor for equipment Circular ducts standard throughout with rectangular ducts in congested areas, 18” max. Small equipment rooms provided on all floors for advanced communications equipment Air requirements in auditorium are 20 CF/person/minute, given an approximate capacity of 250 people The Mountain Ridge Team

29 Engineering Evaluations - Three-Dimensional Model
The Mountain Ridge Team

30 The Mountain Ridge Team
Contractor - Site Plan The Mountain Ridge Team

31 Contractor - Fall 2011 Schedule
The Mountain Ridge Team

32 The Mountain Ridge Team
Contractor - Spring 2012 Schedule The Mountain Ridge Team

33 Contractor - Winter Respite Analysis
Impractical to weatherproof before winter weather hits Either shut job down during winter or rent tent for $42,000 per month Project can still be completed comfortably if dormant for <4 months Respite allows for coordination and planning The Mountain Ridge Team

34 Contractor - Estimate Details
Location adjustment factor of 1.15 $160/s.f dollars ($210/s.f dollars) 6% Contractor fee 10% Architecture and Engineering fee The Mountain Ridge Team

35 Contractor - Critical Phases of Work
Heaviest lift complete The Mountain Ridge Team

36 Contractor - Critical Phases of Work
Floors and roof complete The Mountain Ridge Team

37 Contractor - Equipment
Crane selection for steel erection 50T hydraulic rough terrain crane with 65’ boom Critical lift: 4 ton beam at 60’ radius Gradall material handlers The Mountain Ridge Team

38 Contractor - Estimate Progression
The Mountain Ridge Team

39 Contractor - Schedule Loading
2011 2012 The Mountain Ridge Team

40 Contractor - Budget Breakdown
The Mountain Ridge Team

41 Contractor - Inflation Analysis
The Mountain Ridge Team

42 Contractor - Construction Cost Index
The Mountain Ridge Team

43 Product, Evolution, and Process
A/E/C/O Height variance Ramp in rear of building 2 plane vs. 4 plane roof system C/E Beam spacing Floor system A/E/O Window wall Balcony in rear 3rd floor Shearwall Entrance façade column locations A/C/O Cladding Excavation costs The Mountain Ridge Team

44 Floor and Structural Systems - E/C Trade-off Analysis
Concrete for floor decks: Lightweight concrete? Normal weight concrete? Steel Framing: Moment resistant frames - shop welded? Eccentrically braced frames? Simple gravity frames? The Mountain Ridge Team

45 Beam Spacing - E/C Trade-off Analysis
20’ column grid Beams can be spaced at 10’ or 20’ on center? Larger beam spacing means fewer pieces, fewer connections and thus faster construction. But, also requires deeper slabs Cost basically unaffected Long-term usability chosen over short-term construction schedule benefits The Mountain Ridge Team

46 Basement Layout vs. Excavation - A/E/C/O Trade-Off Analysis
Building Functioning Space allocation slope floor, owner requirement Costs Activities and program requirements O/A Evaluation The Mountain Ridge Team

47 Ramp in Rear of Building - A/E/C/O Trade-Off Analysis
Relationship with the excavation Development of the option Rejection of the ramp alternative The Mountain Ridge Team

48 East Balcony and Column Locations - A/E Trade-Off Analysis
Owner requirements for a balcony Architectural solution - cantilever Engineer’s response with additional columns - spares moment connections Added Columns Plan of East Balcony The Mountain Ridge Team

49 Window Wall and West Balcony - A/E/O Issues
The Requirements of O/A/E The communications breakdowns The positioning of walkway supports The Mountain Ridge Team

50 Exterior Cladding - A/C/O Cost vs. Appearance Concerns
Plaster or stone Stone more has institutional, timeless appearance Stone $1 million than plaster Stone/plaster combination chosen The Mountain Ridge Team

51 Product, Evolution, and Process
The building solution is the PRODUCT The A/E/C team interaction is the PROCESS The iterations along the way are EVOLUTION Process is the Cause Evolution is the Effect Product is Summation of those effects The Mountain Ridge Team

52 Evaluation of Communication Media and Resources
Hardware vs. Software Progress in the Future The Mountain Ridge Team

53 At the Core of Our Process...
Complementing skills Sharing points of view Mutual concern for cross disciplinary problems Mentor Interaction The Mountain Ridge Team

54 Summary of Team Process
Importance of information flow transfer Team dynamic The role of the owner O C A E The Mountain Ridge Team

55 Creating a Better Solution
Dave’s Axiom 2 times better process = 8 times better product! The Mountain Ridge Team

56 The Mountain Ridge Team
We acknowledge the support of Luciana Barroso and the Course Mentors! The Mountain Ridge Team


Download ppt "The Mountain Ridge Team"

Similar presentations


Ads by Google