COMP2001 HNC Project. Project Characteristics A project must have: clear objectives planning & control resources assurance of quality.

Slides:



Advertisements
Similar presentations
Project Management Concepts
Advertisements

CP Chapter 4 Schedule Planning.
PRJ566 Project Planning and Management Lecture: Network Diagrams.
Work Breakdown Structures
Chapter 3 Managing the Information Systems Project
Network Diagramming Network Analysis  The common term for network analysis is PERT  PERT stands for Program Evaluation and Review Technique  The word.
© 2005 by Prentice Hall Chapter 3 Managing the Information Systems Project Modern Systems Analysis and Design Fourth Edition Jeffrey A. Hoffer Joey F.
Responsibility Assignment Matrix (RAM) — Purpose  Ensure that all tasks are assigned to people  Show levels of involvement of people to work.
Chapter 10: Project Schedule Planning
Defining activities – Activity list containing activity name, identifier, attributes, and brief description Sequencing activities – determining the dependencies.
CS3500 Software Engineering Project Management (1) In 1986 one well-known software engineer (Tom DeMarco) made the simple but important observation: “You.
Managing Project Scheduling. What is Project Scheduling? The process of: – defining project activities – determining their sequence – estimating their.
1 Operations Management Lesson 5 Project Management.
Importance of Project Schedules
11 October Project Management Discipline of planning, organizing, and managing resources to bring about the successful completion of specific project.
1 © Bennett, McRobb and Farmer 2002, and De Montfort University 2002 Based on Chapter 21 of Bennett, McRobb and Farmer: Object Oriented Systems Analysis.
Project Time Management
Engineering Design Development. Turner College and Career High School.
Project Tracking and Scheduling Infsy 570 Dr. R. Ocker.
Gantt Chart Engineering Design Development. Turner College and Career High School.
This work is licensed under a Creative Commons Attribution 3.0 Unported LicenseCreative Commons Attribution 3.0 Unported License (CC-BY). Project Management.
CS 160: Software Engineering October 20 Class Meeting Department of Computer Science San Jose State University Fall 2014 Instructor: Ron Mak
HIT241 - TIME MANAGEMENT Introduction
© 2006 ITT Educational Services Inc. System Analysis for Software Engineers: Unit 5 Slide 1 Chapter 3 Managing the Information Systems Project.
Project Management An overview. What is a Project A temporary job to accomplish a specific task A temporary job to accomplish a specific task Attributes.
Time Management Week 7 - Learning Objectives You should be able to: n List and describe the processes, activities, inputs, and outputs in time management.
 Probably the most time-consuming project management activity.  Continuous activity - Plans must be regularly revised.  Various different types of.
Managing the Design Process Project must  Accomplish the goals - scope  Be done within resources - spending  Be done on time - scheduling.
Work Organization Methods and Schemes
Chapter 6: Project Time Management
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Projects CHAPTER 10. Learning Objectives 1. Explain what project management is and why it is important. 2. Identify the different ways projects can be.
~ pertemuan 6 ~ Oleh: Ir. Abdul Hayat, MTI 03-Apr-2009 [Abdul Hayat, Project Time Management, Semester Genap 2008/2009] 1 PROJECT TIME MANAGEMENT.
Information Technology Project Management, Seventh Edition Note: See the text itself for full citations.
COMP 208/214/215/216 Lecture 3 Planning. Planning is the key to a successful project It is doubly important when multiple people are involved Plans are.
Lecture 3 Scheduling CSCI – 3350 Software Engineering II Fall 2014 Bill Pine.
Lecture4 : Project planning Lecturer: Kawther Abas 447CS – Management of Programming Projects.
IT Project Management, Third Edition Chapter 6 1 Chapter 3: Project Time Management.
Switch off your Mobiles Phones or Change Profile to Silent Mode.
Dr. Jana Jagodick Polytechnic of Namibia, 2012 Project Management Chapter 7 Project Manager’s Toolkit for Time Management.
BIS 360 – Lecture Two Ch. 3: Managing the IS Project.
Software Project Management
© Pearson Education Limited 2004 OHT 8.1 Cadle and Yeates: Project Management for Information Systems, 4th edition Critical Path Method(CPM)
Objectives 4 Understand the basic concepts of project planning and control 4 Explain PERT and Timeline (Gantt) charts.
Project Planning Techniques U08784Software Project Management Rosemary Phillimore.
Collecting requirements – Different methods Defining scope – Estimates for all resources Creating the WBS – Different approaches Verifying scope – Formal.
1 OMGT 3123 Project Management  Project Controlling  Project Management Techniques: PERT And CPM  The Framework Of PERT And CPM  Network Diagrams And.
Richard Fisher 1 The University of Texas at Dallas Project Management Richard Fisher The University of Texas at Dallas.
A2 Technology Product Design Systems and Control Notes DT4 - Exam.
Project Management. Introduction  Project management process goes alongside the system development process Process management process made up of three.
Project Time Management
Managing programs that promote personal effectiveness.
MARCH 1 Project Management Problem statement l no hurdles, no problem just a goal l open-ended … no single correct answer l closed-ended … single answer.
Switch off your Mobiles Phones or Change Profile to Silent Mode.
Event Project Management By: Zhou Chunlin School of Tourism, Conference and Exhibitions Henan University of Economics and Law.
P3 Business Analysis. 2 Section F: Project Management F1.The nature of projects F2. Building the Business Case F4. Planning,monitoring and controlling.
IT-301 Project Management I: Unit 4: Cost Management.
PROJECT MANAGEMENT TOOLS AND TECHNIQUES SEMINAR December 2003.
Project Scope, Time and Cost IT Project Management PM Knowledge Areas:
Project Management Planning and Scheduling. “Failing to plan is planning to fail” by J. Hinze, Construction Planning and Scheduling Planning: “what” is.
Tools to Help  Product flow Dependencies and relationships of deliverables  Work breakdown structure The parts  PERT charts Program Evaluation and.
Project Management – PTM721S
PROJECT MANAGEMENT.
PERT & GANTT CHARTS An Introduction.
Activity Planning.
CHAPTER 6 PROJECT TIME MANAGEMENT
SE Tasks for a Concept Development Project
Tools for Visualization
Importance of Project Schedules
CHAPTER 6 PROJECT TIME MANAGEMENT
Presentation transcript:

COMP2001 HNC Project

Project Characteristics A project must have: clear objectives planning & control resources assurance of quality

Project Definition A project is defined in terms of its: - background - objectives - scope - constraints

Project Schedule Determine project approach (buy or build) Estimate effort Prepare project plan Prepare project budget Document project progress

Project Schedule Time ordered sequence of deliverables Used for: organising work effort working towards project goals & obj. tracking the project

Tasks Smallest unit of work Each task only occurs once Suitably described Enough details to be measurable

Milestones Point in schedule to measure progress Contains a sequence of tasks

Project Management Techniques Traditional project management techniques widely used in many other industries. These include:- –Work Breakdown Structure (WBS). –Gantt chart. –PERT chart (critical path or network diagram).

Work Breakdown Structure Very useful for initial planning. Helps identify required resources. Structured list of all tasks and activities that must be carried out to complete project. Usually, sequence is unimportant. Main purpose is checklist for completeness.

WBS example: “clean bedroom” hoovering –get hoover –move furniture –hoover floor dusting –get duster –move ornaments –do dusting change bed, etc.

Gantt Chart The classic “bar-chart”. Often based on WBS, but includes time dimension. hoover floor get hoover move furniture put furniture back put hoover away time

PERT Chart or Critical Path Chart “Programme Evaluation and Review Technique”. Designed to show interdependencies between tasks: –“get hoover” must be complete before “do hoovering” starts (i.e. B depends on A); –“move furniture” can happen before or after “get hoover” (no dependency). Often derived directly from Gantt Chart.

Network Diagram A Get Hoover TM (2) B Move Furniture (3) C Hoover TM Floor (14) Activity Event Event No. Event Latest Time Slack/Float Event Earliest Time

Resource Levelling First-cut chart is not always the most efficient. It may be possible to: –reduce overall resources required, –reduce total project time. “Levelling” means: –use available float time on non-critical tasks, –move spare resources from one task to another. A matter of judgement - no one best way.

Suggested Reading Project Management for Information Systems D Yeates & J Cadle