1 Responsibilities & Cost ALICE DCS Review 14 Nov 05 For the DCS Team L.Jirden.

Slides:



Advertisements
Similar presentations
André Augustinus 22 June 2004 DCS Workshop Status on services controls.
Advertisements

1 DCS Cost DCS Workshop L.Jirden u Central DCS cost u Detector DCS cost.
The Detector Control System – FERO related issues
1 DCS Installation & commissioning TB 18 May 06 L.Jirden Central DCS Detector DCS Status.
CPV DCS STATUS REPORT Mikhail Bogolyubsky (IHEP, Protvino) Serguei Sadovsky (IHEP, Protvino) CERN, DCS meeting, 30 January, 2007.
André Augustinus 16 June 2003 DCS Workshop Safety.
André Augustinus ALICE Detector Control System  ALICE DCS is responsible for safe, stable and efficient operation of the experiment  Central monitoring.
1 ALICE Detector Control System (DCS) TDR 28 January 2004 L.Jirdén On behalf of ALICE Controls Coordination (ACC): A.Augustinus, P.Chochula, G. De Cataldo,
Supervision of Production Computers in ALICE Peter Chochula for the ALICE DCS team.
The Detector Safety System for LHC Experiments Stefan Lüders ― CERN EP/SFT & IT/CO CHEP03 ― UC San Diego ― March 27 th, 2003.
3 June 2003U. Frankenfeld1 TPC Detector Control System Status.
1 DCS TDR Key technical points & milestones TB 15 Dec 2003 L.Jirdén.
JPV, TB of Nov.15 th, ‘Rack Status‘ Jean-Pierre Vanuxem, PH-AIS.
Summary DCS Workshop - L.Jirdén1 Summary of DCS Workshop 28/29 May 01 u Aim of workshop u Program u Summary of presentations u Conclusion.
1 Status & Plans DCS WS L.Jirdén. 2 DCS Planning FINAL INST COM- MISS BEAM OP PRE- INST DET DCS URD ENG. SOLUTIONS PROTOTYPE SUBSYSTEM.
09/11/20061 Detector Control Systems A software implementation: Cern Framework + PVSS Niccolo’ Moggi and Stefano Zucchelli University and INFN Bologna.
1 ALICE Control System ready for LHC operation ICALEPCS 16 Oct 2007 L.Jirdén On behalf of the ALICE Controls Team CERN Geneva.
9th September 2001R. BARILLERE - IT-CO1 Industrial and Custom Front-End solutions for Process Controls.
JCOP Workshop September 8th 1999 H.J.Burckhart 1 ATLAS DCS Organization of Detector and Controls Architecture Connection to DAQ Front-end System Practical.
TPC DCS update. CR3 UX-A/C CR4-Z08 UX-A/C CR3 CR4-Z08 UX-A/C CR4-Y08 Chambers ISEG Chambers Wiener Ethernet RCU Chambers, detector ELMB
CERN Safety Alarm Monitoring Presented by Luigi Scibile ST division / MO group.
André Augustinus 16 September 2002 Safety issues.
Update on Database Issues Peter Chochula DCS Workshop, June 21, 2004 Colmar.
Peter Chochula ALICE DCS Workshop, October 6,2005 DCS Computing policies and rules.
XXVI Workshop on Recent Developments in High Energy Physics and Cosmology Theodoros Argyropoulos NTUA DCS group Ancient Olympia 2008 ATLAS Cathode Strip.
Ethernet IP solution for ATLAS IBL and CMS Pixel detectors CO 2 cooling plants Lukasz Zwalinski PH/DT/DI.
DCS Workshop - L.Jirdén1 ALICE DCS PROJECT ORGANIZATION - a proposal - u Project Goals u Organizational Layout u Technical Layout u Deliverables.
The Joint COntrols Project Framework Manuel Gonzalez Berges on behalf of the JCOP FW Team.
André Augustinus 10 September 2001 DCS Architecture Issues Food for thoughts and discussion.
1 Status and Plans DCS workshop L.Jirdén u Budget u Status u Planning u Goals for end 2002.
1 Responsibilities & Planning DCS WS L.Jirdén.
André Augustinus 17 June 2002 Technology Overview What is out there to fulfil our requirements? (with thanks to Tarek)
André Augustinus 10 October 2005 ALICE Detector Control Status Report A. Augustinus, P. Chochula, G. De Cataldo, L. Jirdén, S. Popescu the DCS team, ALICE.
André Augustinus 26 October 2004 ALICE Technical Board DCS for ‘services’ costs On behalf of Lennart Jirdén.
1 Cost of controls TB L.Jirdén. 2 LAN WAN Storage Configuration DB, Archives FSM servers Terminal servers, ACR consoles, etc Experimental equipment.
FAIR Accelerator Controls Strategy
Peter Chochula DCS Remote Access and Access Control Peter Chochula.
André Augustinus 6 October 2005 Cabling, Interlocks, Racks Some remarks.
20th September 2004ALICE DCS Meeting1 Overview FW News PVSS News PVSS Scaling Up News Front-end News Questions.
Virtualization for the LHCb Online system CHEP Taipei Dedicato a Zio Renato Enrico Bonaccorsi, (CERN)
André Augustinus 10 March 2003 DCS Workshop Detector Controls Layout Introduction.
15-16/3/04 DCS workshop G. De Cataldo, A,.Franco and A. Tauro 1 Answers from the HMPID to the ACC questions 1.Concerning global DCS overview drawing 2.Concerning.
JCOP Review, March 2003 D.R.Myers, IT-CO1 JCOP Review 2003 Architecture.
CERN, O.Pinazza: ALICE TOF DCS1 ALICE TOF DCS Answers to DCS Commissioning and Installation related questions ALICE week at CERN O. Pinazza and.
ACC ? Detector PVSS II Ethernet Database(s) OPC client DIM client High VoltageLow Voltage User interface PVSS II LV PMD Control room (ACR) [FSM?]
The DCS lab. Computer infrastructure Peter Chochula.
IDE DCS development overview Ewa Stanecka, ID Week, CERN
News from Alberto et al. Fibers document separated from the rest of the computing resources
André Augustinus 16 June 2003 DCS Workshop General Purpose Monitor.
Alice MTR DCS F.Jouve 15 th DCS workshop CERN 13/03/2006 UX-A,B,D Detector PVSS II Detector Ethernet Database(s) OPC client DIM client 1672 Detector ?
DCS Software Installation computing, network, software guidelines, procedures Peter Rosinsky, Peter Chochula, ACC team ALICE DCS Workshop, CERN, 5-6 March.
ClinicalSoftwareSolutions Patient focused.Business minded. Slide 1 Opus Server Architecture Fritz Feltner Sept 7, 2007 Director, IT and Systems Integration.
DCS Workshop, CERN MARCH ACORDE (Alice Cosmic ray detector) 60 scintillator modules (120 HV channels) Each module will have two scintillator counters.
DCS overview - L.Jirdén1 ALICE ECS/DCS – project overview strategy and status L.Jirden u Organization u DCS system overview u Implementation.
5th March 0718th DCS Workshop1 News on ISEG & WIENER Lionel Wallet, CERN High Voltage, Low Voltage & VME Crate control.
14 November 08ELACCO meeting1 Alice Detector Control System EST Fellow : Lionel Wallet, CERN Supervisor : Andre Augustinus, CERN Marie Curie Early Stage.
Clara Gaspar, April 2006 LHCb Experiment Control System Scope, Status & Worries.
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
ATLAS DCS ELMB PRR, March 4th 2002, H.J.Burckhart1 Embedded Local Monitor Board ELMB  Context  Aim  Requirements  Add-ons  Our aims of PRR.
T0 DCS Status DCS Workshop March 2006 T.Karavicheva on behalf of T0 team.
DCS workshop,march 10th P.Saturnini, F. Jouve Slow control trigger of the muon arm Muon trigger of the muon arm Low voltage VME Crate External parameters.
E Ethernet C CAN bus P Profibus HV HV cables LV LV cables (+busbar) S Serial (RS232) Signal cable Other/Unknown Liquid or Gas Cable and/or Bus PCI-XYZ.
1 Planning DCS WS L.Jirdén. 2 TPC HMPID ACORDE FE PC Console DSS Disk SRV DB-SRV App GW sensors actuators DSS sensors actuators PC room SXL2.
The (prototype) C&V Framework component used for the SPD Cooling Control A.Tauro, G.De Cataldo.
JCOP Framework and PVSS News ALICE DCS Workshop 14 th March, 2006 Piotr Golonka CERN IT/CO-BE Outline PVSS status Framework: Current status and future.
1 COSTING DCS WS L.Jirdén. 2 LAN WAN Storage Configuration DB, Archives FSM servers Terminal servers, ACR consoles, etc Experimental equipment.
ALICE. 2 Experiment Size: 16 x 26 meters (some detectors >100m away from IP) Weight: 10,000 tons Detectors: 18 Magnets: 2 Dedicated to study of ultra.
Presentation transcript:

1 Responsibilities & Cost ALICE DCS Review 14 Nov 05 For the DCS Team L.Jirden

2 Responsibilities u ACC (and its CERN partners) will provide u DCS H/W Infrastructure u Back-End System u Common Services u Interface to TRG, DAQ, HLT, LHC via ECS u S/W Infrastructure for Detector Applications u Detectors will provide u Detector Sub-System Devices and Cabling u Detector Specific Networking (Ethernet switches) u Detector Applications for each Sub-System u Detector Specific Services u Integration of all Detector Sub-Systems to a full Detector Control System u Interface to the Alice Detector Control System layer

3 Magnets Rack control Electricity Safety: DSS Safety: CSAM Infrastructure LAN WAN Storage Configuration DB, Archives FSM servers Terminal servers, ACR consoles, etc Experimental equipment Controller/ PLC VME Field Bus LAN Node cooling gas Services Central DCS Detectors Global Responsibilities ACC Detectors ACC Common items

4 Detector common items u Provided, installed, maintained by ACC (and their CERN collaborators) u DCS Racks in CR3 u Global network u Exception: detectors are responsible for the “on- detector” networks u Computers and interfaces u Software infrastructure for front-end computers u ELMB Controllers with centralized Power u CANbus cables - entry in cable dB u Device interlock cables - entry in cable dB WXP PCI OPCserver PVSS II FW LIBRARIES

5 Magnets Rack control Electricity Safety: DSS Safety: CSAM Infrastructure LAN WAN Storage Configuration DB, Archives FSM servers Terminal servers, ACR consoles, etc Experimental equipment Controller/ PLC VME Field Bus LAN Node cooling gas Services Central DCS Detectors Global Cost ACC Detectors ACC Common items ~1440K? ? ?

6 Central DCS Firewall Terminal Server IP Reach for KVM Domain Controller DB Server (Config.) DB Server (Archive) File Server Network and Security FSM Alarms General DCS Electricity & Racks Gas & Cooling Environment General services LHC & Access Alignment Information Server CERN System Management DCS Operator DCS Status Safety Status ConsolesRemote AccessBackend Servers Worker Nodes Detector DCS ACR Consoles DB Server (Archive) Infrastructure, network Racks, network, cabling KVM switches controlled power plugs Hot swap spare servers Disks & memories Spares 12 KCHF 13.1 KCHF34.5 KCHF 18.5 KCHF 43.6 KCHF On DAQ budget TOTAL: ~150 KCHF 7.1 KCHF DCS network

7 Detector DCS cost SPD21K75k SDD25K guess50k SSD25K20k TPC100K300k TRD80K guess82k TOF43K 89k HMPID80K15k PHOS44K150k CPV20K0 PMD11K100k FMD8K0 V07K0 T016K0 ZDC5K guess0 MUON TRK42K200k MUON TRG11K50k ACORDE5K guess0 TOTAL~ 550K~ 1130K Estimation today Quoted in MOU NOTE: Cables and connectors are probably under- estimated Installation cost is not included

8 Detector common items ItemnumberUnit price (KCHF) Total Cost (KCHF) DCS racks4832 Global network *130 Computers Interfaces Software infrastructure7600 ELMB’s ELMB power166 Total~ 330K * Very approximative - IT/CS will provide a precise offer

9 Magnets Rack control Electricity Safety: DSS Safety: CSAM Infrastructure LAN WAN Storage Configuration DB, Archives FSM servers Terminal servers, ACR consoles, etc Experimental equipment Controller/ PLC VME Field Bus LAN Node cooling gas Services Central DCS Detectors Global Cost ACC Detectors ACC Common items ~1440K~550K ~150K ~330K

10 DCS costs to be shared u Central DCS150K u Weighted according to agreed formula u Detector Common items330K u According to actually used items u TOTAL480K u via a DCS common budget code.

11 Thank you !

12 Backend servers Server RoleHardware ConfigurationCost (CHF) Primary Domain Controller1xXeon, 2 GB RAM2500 Secondary Domain Controller1xXeon 2 Gb RAM2500 Configuration Database Server2xXEON, 4 GB RAM4000 Archive Database Server (P2)2xXEON, 4 GB RAM4000 Archive Database Server (IT)2xXEON, 4 GB RAM, disk array DCS Disk server2xXEON, 4 GB RAM, disk array 7000 DCS Information ServerPIV or XEON, 4 GB RAM2500 Total (7 backend servers)34500

13 Worker Nodes WN RoleHardware ConfigurationCost (CHF) DCS network (monitor and management)PIV, 2 GB RAM1600 DCS general (FSM)PIV, 2 GB RAM1600 DCS general (alarm/messages)PIV, 2 GB RAM1600 DCS general (general DCS)PIV, 2 GB RAM1600 Infra/services (electricity & racks)PIV, 2 GB RAM1600 Infra/services (gas & cooling)PIV, 2 GB RAM1600 Infra/services (environment)PIV, 2 GB RAM1600 Infra/services (general services)PIV, 2 GB RAM1600 Infra/services (LHC & access)PIV, 2 GB RAM1600 Infra/services (alignment)PIV, 2 GB RAM1600 PCI + ELMB for infrastructure2500 Total(10 worker nodes)18500

14 Infrastructure and Network WN RoleHardware ConfigurationCost (CHF) 3 Powered Racks (8000/rack)24000 Network installation (400/port)To be detailed by IT/CO10000 KVM switchRaritan Z-series2000 KVM user stationsUSTSZ4000U – 20 pack3600 Power plug controlSpectrum control4000 Total43600

15 Remote access WN RoleHardware ConfigurationCost (CHF) Main network gateway/firewallTo be detailed by CNIC5000 DCS Terminal ServerPIV or XEON, 4 GB RAM2500 DCS Terminal ServerPIV or XEON, 4 GB RAM2500 IP reach for KVMRaritan IPR-M13100 Total13100

16 Consoles WN RoleHardware ConfigurationCost (CHF) DCS System Administrator ConsolePIV, 1 GB RAM + Monitor2500 DCS Operator ConsolesPIV, 1 GB RAM + Monitor2500 DCS Status DisplayPIV, 1 GB RAM + Monitor2500 Safety DisplayPIV, 1 GB RAM + Monitor2500 KVM Switches2000 ACR Consoles (on DAQ budget)0 Total(4 consoles)12000

17 Spares WN RoleHardware ConfigurationCost (CHF) Backend Server Spare (“hot swap”)PIV or XEON, 4 GB RAM2500 Worker Node Spare (“hot swap”)PIV, 2 GB RAM2500 Disks and memory modules3000 Total7100