T0 DCS Status DCS Workshop 13-14 March 2006 T.Karavicheva on behalf of T0 team.

Similar presentations


Presentation on theme: "T0 DCS Status DCS Workshop 13-14 March 2006 T.Karavicheva on behalf of T0 team."— Presentation transcript:

1 T0 DCS Status DCS Workshop 13-14 March 2006 T.Karavicheva on behalf of T0 team

2

3

4 Status [HV/LV]

5 DCS, March 13,2006 T.Karavicheva HV/LV: a prototype of the system running, with FSM

6 DCS, March 13,2006 T.Karavicheva HV Sub-system -Standard:PVSS 3.0 + Framework + OPC 2.7 + FSM -Customized user Panel (not yet optimized)

7 Status [FEE] FEE (readout): very similar to TOF FEE (Fast electronic): Implement a “Lab setup”: PVSS-DIM-device is ready for~ 30%. We develop DIM server to communicate VME create via controller V1718 with PVSS. Ready in 2 weeks Implement FSM – not yet ready. Implement the PVSS configuration, archival and alarms – not yet ready Implement operations panels – not yet ready. Fast electronics crate (VDL, MPD,TVDC) V1718 VME- USB Bridge

8 Status [ELMB+DAC for threshold CFD] Warsaw University of Technology, Faculty of Phisics hardware –ready RadomirKupczak,RadomirKupczak software (PVSS, LabView)-ready Marcin Zaremba DAC ELMB +DAC

9 Status [Laser Calibration] Laser Attenuator Detector Ethernet-RS232 interface (Digi One)

10 DCS, March 13,2006 T.Karavicheva Attenuator sub-system: a prototype of the system running, with FSM

11 DCS, March 13,2006 T.Karavicheva Laser Attenuator Implement a “Lab setup”: PVSS-device is ready. We use DiGi ONE to communicate PC with attenuator. It tested in November 2005 Implement FSM – ready for 100%. It tested in November 2005 Implement the PVSS configuration, archival and alarms – PVSS configuration and alarms are ready. Archive is not ready Implement operations panels -. We use our own panels for FSM( not yet optimized).

12

13 Plans Sub system Implement a “Lab setup”: PVSS-OPC- device Implement FSM Implement the PVSS configurati on, archival and alarms Implement software interlocks (if required) Implement operations panels Hand-over PVSS project to ACC for verific. & integration Install, cable & commission the devices at P2 Commission the devices with detector HV Ready (without Archival) End of April Ready (not yet optimized ) End of April ?? LV Ready (without Archival) End of April End of April End of April ?? FEE (readout) October November ?? FEE (fast electronics) End of April End of April End of April End of April End of April November ?? ELMB Ready (without Archival) Ready (not yet optimized ) November ?? Laser Ready (without Archival) Ready (not yet optimized End of April ??


Download ppt "T0 DCS Status DCS Workshop 13-14 March 2006 T.Karavicheva on behalf of T0 team."