___________________________________________________________________________ Quantitative Methods of Management  Jan Fábry Project Management Example -

Slides:



Advertisements
Similar presentations
IE 2030 Lecture 5: Project Management Drawing Gantt Charts Time on horizontal axis, Activities on vertical axis. 1 bar per activity Length of bar = required.
Advertisements

464 Lecture 09 CPM Revision. Scheduling Techniques r The scheduling techniques are î To plan, schedule, budget and control the many activities associated.
Critical Path Analysis Activity duration Shower3 Dry hair8 Fetch car7 Iron clothes12 Dress and make-up10 Drive to interview20 Example 4.1 textbook pages.
1 1 Slide © 2006 Thomson South-Western. All Rights Reserved. Slides prepared by JOHN LOUCKS St. Edwards University.
Chapter 13 Project Scheduling: PERT/CPM
1 1 Slide © 2008 Thomson South-Western. All Rights Reserved Slides by JOHN LOUCKS St. Edwards University.
Based on the book: Managing Business Process Flows
Spring 2008, King Saud University Arrow Diagramming Dr. Khalid Al-Gahtani 1 CPM Network Computation Computation Nomenclature The following definitions.
1 1 Slide © 2001 South-Western College Publishing/Thomson Learning Anderson Sweeney Williams Anderson Sweeney Williams Slides Prepared by JOHN LOUCKS QUANTITATIVE.
Terminology Project: Combination of activities that have to be carried out in a certain order Activity: Anything that uses up time and resources CPM: „Critical.
D1: Critical Events And Critical Paths. D1: Critical Events And Paths A critical path is the list of activities on an activity network that, if they are.
1.040/1.401 Project Management Spring 2007 Deterministic Planning Part I Dr. SangHyun Lee Department of Civil and Environmental Engineering.
Gantt Chart Graph or bar chart with a bar for each project activity that shows passage of time Provides visual display of project schedule Slack amount.
1 1 Slide © 2005 Thomson/South-Western Q 5 – 13 x 1 = the probability that Station A will take Sitcom Rerun x 2 = the probability that Station A will take.
1 1 Slide © 2004 Thomson/South-Western Chapter 12 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
1 1 Slide © 2000 South-Western College Publishing/ITP Slides Prepared by JOHN LOUCKS.
1 1 Slide © 2011 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole.
CPA A house is to have new carpets fitted throughout. The work involved has been divided into a number of tasks, as shown in the table.
1 1 Slide © 2009 South-Western, a part of Cengage Learning Slides by John Loucks St. Edward’s University.
___________________________________________________________________________ Quantitative Methods of Management  Jan Fábry Project Management.
Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
D1: Event Times.
Activity networks – Example 1 TaskDuration (hours)Immediate predecessors A3- B4- C6- D5A E1B F6B G7C, D, E The table below shows the tasks involved in.
Network planning Learning objectives After these lectures you should be able to: - Produce and analyse activities networks - Calculate earliest and latest.
1 1 Slide © 2008 Thomson South-Western. All Rights Reserved Slides by JOHN LOUCKS St. Edward’s University.
ME 380 Project Planning. Critical Path Method (CPM) Elements: Activities & Events Feature: Precedence relations ActivityDurationPrecedence A4- B5- C3A.
Chapter 10 Project Scheduling: PERT/CPM
Module 5 – Networks and Decision Mathematics Chapter 24 – Directed Graphs.
1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM Project Scheduling with Known Activity Times Project Scheduling with Known.
Precedence Network Calculations the basic information that should be calculated in the precedence network are: 1) Early activity start (ES) 2) Early activity.
15C Backward scanning and crashing
Software project management (intro) Scheduling Network.
Prof. Awad Hanna Estimating Activity Duration Time Interval  Time Interval is selected according to the nature of the activity (seconds - minutes…) 
___________________________________________________________________________ Operations Research  Jan Fábry Project Management.
___________________________________________________________________________ Operations Research  Jan Fábry PERT Project Management.
Activity Time (hours) Preceding Activities Decorating & furnishing a spare bedroom 1 Remove old furniture Remove carpet Take down curtains & rail Remove.
1 Project Planning, Scheduling and Control Project – a set of partially ordered, interrelated activities that must be completed to achieve a goal.
Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999 PROJECT MANAGEMENT 18-1 Project Management.
1 1 Project Scheduling PERT/CPM Networks. 2 2 Originated by H.L.Gantt in 1918 GANTT CHART Advantages - Gantt charts are quite commonly used. They provide.
1 1 © 2003 Thomson  /South-Western Slide Slides Prepared by JOHN S. LOUCKS St. Edward’s University.
Project Management - PERT/CPM What is project management? Consider building a house: Step A: Prepare site. (5 days) Step B: Build foundation. (8 days)
In Chapter 5: Scheduling the Project From Action Plan and WBS to Gantt chart and project network.  Gantt Chart  Project Network  Activity-on-arrow 
Analysing the AoN network Project Management (seminar)
___________________________________________________________________________ Quantitative Methods of Management  Jan Fábry PERT Project Management.
___________________________________________________________________________ ___________________________________________________________________________.
University of Sunderland CIFM02 Unit 2 COMM02 Activity Planning Unit 2.
Project Management Chapter 13 Sections 13.1, 13.2, and 13.3.
 Chapter 6: Activity Planning – Part 3 NET481: Project Management Afnan Albahli.
15B Critical path analysis. In a critical path analysis, edges represent activities. Nodes (vertices) represent the end of one activity and the start.
 Chapter 6: Activity Planning – Part 2 NET481: Project Management Afnan Albahli.
PROJECT MANAGEMENT ENCE-7323 TO 763-N CLASS 3 September 17, 2001 Carl E. Edlund
Network Analysis Prepared by hanadi. NetWork(start/end node) A.Draw network? B. Determine the critical path DurationActivity (I,j) 5A(1,2) 4B(1,4) 3C(1,5)
IE 366 Chapter 6, Section 10 Project Planning and Scheduling.
Network Diagram Prob 1 Activity Predecessor Duration (days) A None 2 B
Activity networks – Example 1
Project Scheduling Lecture # 1.
Project Management for Business
معرفي روش هاي برنامه ريزي شبكه و محاسبات زمان
Analysing the AoA network
Analysing the AoA network
Chapter 6 Network-Based Scheduling
BEST VIEWED IN SLIDE SHOW MODE
Activity Networks
Critical Path Analysis
Critical Path Analysis
Activity Networks
Slides Prepared by JOHN LOUCKS
Exercise – A small building.
Operations Research Lecture 7.
Critical Path Analysis
Presentation transcript:

___________________________________________________________________________ Quantitative Methods of Management  Jan Fábry Project Management Example - Music DM, Inc. Solution - CPM 1) Construct the network 2) Event analysis - forward pass - backward pass 3) Activity analysis - critical activities - noncritical activities CPM

___________________________________________________________________________ Quantitative Methods of Management  Jan Fábry Project Management Example - Music DM, Inc. 1) Construct the network One start node & one end node Each activity  one arc Two nodes are connected maximally by one arc CPM

___________________________________________________________________________ Quantitative Methods of Management  Jan Fábry Project Management Example - Music DM, Inc. 1) Construct the network i j i < j CPM

___________________________________________________________________________ Quantitative Methods of Management  Jan Fábry Project Management Example - Music DM, Inc. Activity DescriptionDurationPredecessors A Songs Selection 15None BMastering8A C Promotion Material Elaborating 6A D Customers Analysis 7A E Promotion Material Production 4 C, D F Promotion Material to PH 5E G Customers Selection 3D CPM

___________________________________________________________________________ Quantitative Methods of Management  Jan Fábry Project Management Example - Music DM, Inc. Activity DescriptionDurationPredecessors H Make CD Copies 12 B, D I Data to PH 3G J Laser Print 9 F, I KMailing8 H, J CPM

___________________________________________________________________________ Quantitative Methods of Management  Jan Fábry Project Management Example - Music DM, Inc A B D C D1D1 E FH D2D2 GI J KCPM

___________________________________________________________________________ Quantitative Methods of Management  Jan Fábry Project Management Example - Music DM, Inc CPM

___________________________________________________________________________ Quantitative Methods of Management  Jan Fábry Project Management Example - Music DM, Inc. 2) Event analysis - forward pass The earliest event time for a node is the earliest time at which all the preceding activities have been completed. j ET j CPM

___________________________________________________________________________ Quantitative Methods of Management  Jan Fábry Project Management Example - Music DM, Inc. 2) Event analysis - forward pass ET 1 ET 1  ET 2 ET 2  ET 3 ET 3 …  ET n Ascending order: The earliest event time for completing a project is the earliest time of the last event. T = ET n CPM

___________________________________________________________________________ Quantitative Methods of Management  Jan Fábry Project Management Example - Music DM, Inc. 2) Event analysis - backward pass The latest event time for a node is the latest time at which the event can occur without delaying the determined completion time of the project. i LT i CPM

___________________________________________________________________________ Quantitative Methods of Management  Jan Fábry Project Management Example - Music DM, Inc. 2) Event analysis - backward pass LT 1  LT 2  LT 3  …  LT n Descending order: The latest event time for completing a project can be set in the planning process or can be considered as the earliest event time for completing a project. LT n = T = ET n or LT n = T PL > T CPM

___________________________________________________________________________ Quantitative Methods of Management  Jan Fábry Project Management Example - Music DM, Inc. 3) Activity analysis Total float: i LT i ET i j ET j LT j t ij CPM

___________________________________________________________________________ Quantitative Methods of Management  Jan Fábry Project Management Example - Music DM, Inc. 3) Activity analysis Critical activity: TF ij = 0 TF ij = T PL - T if LT n = T = ET n if LT n = T = ET n if LT n = T PL > T if LT n = T PL > T Noncritical activity: TF ij > 0 TF ij > T PL - T if LT n = T = ET n if LT n = T = ET n if LT n = T PL > T if LT n = T PL > T CPM

___________________________________________________________________________ Quantitative Methods of Management  Jan Fábry Project Management Example - Music DM, Inc. 3) Activity analysis Critical path: A B D C D1D1 E F H D2D2 GI J KCPM

___________________________________________________________________________ Quantitative Methods of Management  Jan Fábry Project Management Example - Music DM, Inc. 3) Activity analysis Noncritical activity 1) Start of the activity can be postponed 2) Duration of the activity can be extended 3) Combination of 1 and 2 CPM